πŸ”† πŸ“– βž• πŸ‘€

Statutory Instruments

1996 No. 551

HEALTH AND SAFETY

Gas Safety (Management) Regulations 1996

Made

4th March 1996

Laid before Parliament

8th March 1996

Coming into forceβ€”

All regulations except

regulation 8

1st April 1996

Regulation 8

31st October 1996

The Secretary of State in exercise of the powers conferred on him by sections 15(1), (2), (3)(a), (4)(a), (5)(b), (6)(b) and 82(3)(a) of, and paragraphs 1(1)(c), 15(1), 16 and 21(a) of Schedule 3 to, the Health and Safety at Work etc. Act 1974(1) (β€œthe 1974 Act”) and of all other powers enabling him in that behalf and for the purpose of giving effect without modifications to proposals submitted to him by the Health and Safety Commission under section 11(2)(d) of the 1974 Act after the carrying out by the said Commission of consultations in accordance with section 50(3) of that Act, hereby makes the following Regulations:β€”

Citation and commencementI1

1. These Regulations may be cited as the Gas Safety (Management) Regulations 1996 and shall come into force on 1st April 1996 except regulation 8 which shall come into force on 31st October 1996.

InterpretationI2

2.β€”(1) In these Regulations, unless the context otherwise requiresβ€”

F1...

[F2β€œthe 1998 Regulations” means the Gas Safety (Installation and Use) Regulations 1998;

β€œbiogas” and β€œbiomethane” have the meanings given in section 100(3) of the Energy Act 2008;

β€œbiomethane production facility” means a facility for the production of biomethane from biogas;F2]

β€œdistribution main” has the same meaning as in regulation 2(1) of [F3the 1998 RegulationsF3] ;

β€œelectricity generating station” includes an electricity generating station used for generating electricity for use on the same premises on which it is situated;

β€œemergency control” has the same meaning as in regulation 2(1) of [F3the 1998 RegulationsF3] ;

[F4β€œemergency reporting service provider” is to be construed in accordance with paragraphs (3A) and (3B) of regulation 3;F4]

β€œemergency service provider” means a person appointed pursuant to regulation 7(11);

β€œthe Executive” means the Health and Safety Executive;

β€œgas” means any substance in a gaseous state which consists wholly or mainly of methane;

β€œgas fittings” means gas fittings as defined in regulation 2(1) of [F3the 1998 RegulationsF3] as if the phrase β€œ(other than the purpose of an industrial process carried out on industrial premises)” did not appear in that definition;

β€œgas processing facility” means any gas processing facility whichβ€”

(a)

blends or purifies gas, removes from gas any of its constituent gases or separates from gas any oil or water; and

(b)

is situated at a terminal which receives gas directly or indirectly from a gas production facility;

β€œgas production facility” means a facility for the extraction of gas from strata or for the manufacture of gas;

β€œinstallation pipework” has the same meaning as in regulation 2(1) of [F3the 1998 RegulationsF3] ;

β€œinterconnector” means a pipeline used for the conveyance of gas to Great Britain from another country;

[F5β€œLNG facility” means a facility for the reception and regasification of liquid natural gas and any activity, including temporary storage of gas or liquid gas, which is necessary for that reception or regasification.F5]

β€œnetwork” shall be construed in accordance with paragraphs (2) to (4);

β€œnetwork emergency co-ordinator” shall be construed in accordance with paragraphs (2) and (3) of regulation 3;

β€œpipe” includes a pipeline, distribution main, service pipe and any ancillary plant connected to a pipe and used for the conveyance of gas, but it does not include a pipe downstream of an emergency control;

β€œsafety case” shall be construed in accordance with paragraph (5);

β€œservice pipe” has the same meaning as in regulation 2(1) of [F3the 1998 RegulationsF3] ;

β€œsupply emergency” means an emergency endangering persons and arising from a loss of pressure in a network or any part thereof.

(2) Any reference in these Regulations to a network is, subject to paragraphs (3) and (4), a reference to a connected network of pipes used for the conveyance of gas from a gas processing facility[F6, a biomethane production facility, an LNG facilityF6] , a storage facility or an interconnector, except a connected network of pipes used exclusively for conveying gas to non-domestic premises.

(3) A network does not include pipes upstream from a junction on a pipe used exclusively for conveying gas to an electricity generating station; and in this paragraph the reference to a junction on a pipe used exclusively for conveying gas to an electricity generating station is a reference to the point where the upstream end of the pipe joins a pipe used for another purpose.

(4) Where gas[F7(other than biogas or any gas produced from biogas)F7] which does not conform with the requirements referred to in regulation 8(1) is conveyed from a gas processing facility[F8, or an LNG facility,F8] for treatment or blending so as to bring it into conformity with those requirements [F9β€”

(a)any pipes used exclusively for conveying gas (other than biogas or gas produced from biogas) from that facility to the point where the gas is treated or blended or to non-domestic premises (or to both) are not to be treated as part of a network for the purposes of these Regulations;

(b)any pipes used exclusively for conveying gas (including biogas or gas produced from biogas) from that facility to the point where the gas is treated or blended or to non-domestic premises (or to both) are not to be treated as part of a network for the purposes of these Regulations at any time when they are being used to convey gas which is not biogas or produced from biogas.F9]

(5) Any reference in these Regulations to a safety case is a reference to a document containing the particulars required by the provision of these Regulations pursuant to which the safety case is prepared, andβ€”

(a)insofar as the document contains other particulars it shall not be treated as part of the safety case for the purposes of these Regulations;

(b)nothing in these Regulations shall require the particulars to relate to a source of risk other than the gas itself.

(6) Any reference in these Regulations to the Executive accepting a safety case or revision thereof is a reference to the Executive notifying in writing the person who prepared it that it is satisfied with the case for health and safety made out in it.

(7) Any reference in these Regulations to the conveyance of gas is a reference to the conveyance of gas through pipes.

(8) Any reference in these Regulations to conveying gas in a network includes a reference to conveying gas in any part of the network.

(9) Any reference in these Regulations to preventing a supply emergency is a reference to preventing a supply emergency from occurring or continuing.

(10) In these Regulations any reference, in relation to a network, to the network emergency co-ordinator is a reference to the network emergency co-ordinator who has prepared and had accepted a safety case relating to that network pursuant to regulation 3(2) or 10(4).

[F10(10A)In these Regulations any reference, in relation to a network, to an emergency reporting service provider is a reference to an emergency reporting service provider who has prepared and had accepted a safety case relating to that network pursuant to regulation 3(3A).F10]

(11) Any reference in these Regulations to a person supplying or conveying gas, preparing a safety case or carrying out work in relation to a gas fitting is a reference to a person who does so in the course of a business or other undertaking carried on by him.

(12) Unless the context otherwise requires, any reference in these Regulations toβ€”

(a)a numbered regulation or Schedule is a reference to the regulation or Schedule in these Regulations so numbered;

(b)a numbered paragraph is a reference to the paragraph so numbered in the regulation or Schedule in which the reference appears.

Duties on persons conveying gasI3

3.β€”(1) No person shall convey gas in a network unlessβ€”

(a)F11he has prepared a safety case containing the particulars specified in Schedule 1 and that safety case has been accepted by the Executive; ...

[F12(aa)there is a sole emergency reporting service provider for the network; andF12]

(b)where any other person is conveying gas in that network, there is a sole network emergency co-ordinator for the network.

(2) For the purposes of these Regulations a network emergency co-ordinator is, subject to paragraph (3), a person who has prepared a safety case containing the particulars specified in Schedule 2 and has had that safety case accepted by the Executive.

(3) Where a network emergency co-ordinator has given written notice to the Executive and to all persons conveying gas in the network that he no longer intends to act in that capacity, he shall not be the network emergency co-ordinator for the purposes of these Regulations from the time such notice takes effect (which shall not be less than 6 months after it was given).

[F13(3A)For the purposes of these Regulations, an β€œemergency reporting service provider” is a person who has prepared a safety case containing the particulars specified in Schedule 2A and has had that safety case accepted by the Executive.

(3B)Where an emergency reporting service provider has given written notice to the Executive and all persons who are conveying gas in the network that they no longer intend to act in that capacity, that person ceases to be an emergency reporting service provider on the relevant date.

(3C)For the purposes of paragraph (3B) β€œthe relevant date” meansβ€”

(a)the date specified in the written notice given by the person, which may not be before the end of the period of two years beginning with the date on which the notice is given; or

(b)if earlier, the date on which another person who has prepared a safety case in relation to the relevant network containing the particulars specified in Schedule 2A has their safety case accepted by the Executive.F13]

(4) Nothing in these Regulations shall prevent a person who conveys gas in a network from also being the network emergency co-ordinator[F14or the emergency reporting service provider (or both)F14] .

Revision of safety casesI4

4.β€”(1) A person who has prepared a safety case pursuant to these Regulations shall revise its contents whenever it is appropriate, but nothing in this paragraph shall require him to have the revision accepted by the Executive.

(2) Where a revision proposed to be made under paragraph (1) will render the safety case materially different from the last version accepted by the Executive pursuant to these Regulations, the revision shall not be made unless the Executive has accepted the revision, and for the purposes of this paragraph in determining whether a proposed revision will render the safety case materially different from the version referred to above, regard shall be had to the cumulative effect of that proposed revision and any previous revisions made under paragraph (1) but not subject to this paragraph.

(3) A person who has prepared a safety case which has been accepted by the Executive pursuant to these Regulations shall make a thorough review of its contents at least every three years.

Duty to conform with safety caseI5

5.β€”(1) Where a person has prepared and has had accepted a safety case pursuant to these Regulations he shall ensure, so long as he conveys gas in the network to which the safety case relates or remains a network emergency co-ordinator[F15or an emergency reporting service providerF15] , as the case may be, that the procedures and arrangements described in the safety case and any revision thereof are followed.

(2) In criminal proceedings for a contravention of paragraph (1) it shall be a defence for the accused to prove thatβ€”

(a)in the particular circumstances of the case it was not in the best interests of health and safety to follow the procedures or arrangements concerned and there was insufficient time to revise the safety case pursuant to regulation 4; or

(b)the commission of the offence was due to a contravention by another person of regulation 6 and the accused had taken all reasonable precautions and exercised all due diligence to ensure that the procedures or arrangements were followed.

Co-operationI6

6.β€”(1) Every person to whom this paragraph applies shall co-operate so far as is necessary with a person conveying gas in a network[F16, with a network emergency co-ordinator and with any emergency reporting service providerF16] to enable them to comply with the provisions of these Regulations.

(2) Paragraph (1) applies toβ€”

(a)a person conveying gas in the network;

(b)an emergency service provider;

(c)the network emergency co-ordinator in relation to a person conveying gas[F17or an emergency reporting service providerF17] ;

[F18(ca)an emergency reporting service provider in relation to a person conveying gas or a network emergency co-ordinator;F18]

(d)a person conveying gas in pipes which are not part of a network by virtue of regulation 2(3) or (4);

(e)the holder of a licence issued under section 7A of the Gas Act 1986(2);

(f)a person exempted under section 6A(1) of the Gas Act 1986(3) from paragraph (b) or (c) of section 5(1) of that Act;

(g)a person referred to in paragraph 5(1) of Schedule 2A to the Gas Act 1986;

(h)the person in control of a gas production facility[F19, a biomethane production facilityF19] , a gas processing facility, a storage facility [F20, an LNG facilityF20] or an interconnector supplying gas to the network.

(3) The reference in paragraph (2)(h) to the person in control of a production facility isβ€”

(a)where the facility is a fixed installation within the meaning of regulation 2(1) of the Offshore Installations and Pipeline Works (Management and Administration) Regulations 1995(4), an operator within the meaning of that regulation;

(b)where the facility is at a borehole site within the meaning of regulation 2(1) of the Borehole Sites and Operations Regulations 1995(5), an operator within the meaning of that regulation.

(4) A person conveying gas in a network may, subject to paragraph (5), direct a person not to consume gas for the period specified in the direction.

(5) A direction under paragraph (4) mayβ€”

(a)only be given where it is necessary to prevent a supply emergency or to prevent danger arising from the use of gas not conforming with the requirements of regulation 8;

(b)be given orally or in writing and may be withdrawn at any time.

(6) Where a direction is given to a person pursuant to paragraph (4), that person shall comply with it during the period specified in the direction except that this shall not require him to comply with a direction after it has been withdrawn.

(7) In criminal proceedings for a contravention of paragraph (6) it shall be a defence for the accused to prove that he had no knowledge of the direction.

(8) A person who conveys gas in a network shall, where he is requested to do so by a person proposing to carry out work in relation to a gas fitting, provide him with information about the operating pressures of the gas at the outlet of a service pipe.

Gas escapes and investigationsI7

7.[F21β€”(1)An emergency reporting service providerβ€”

(a)must provide a continuously staffed telephone service for enabling persons to report an escape of gas from a network or from a gas fitting supplied with gas from a relevant network, and

(b)may provide other continuously staffed means for enabling persons to report such an escape to it.

(1A)In this regulation β€œrelevant network”, in relation to an emergency reporting service provider (β€œN”), meansβ€”

(a)the network for which N is the emergency reporting service provider, or

(b)where N is the emergency reporting service provider for two or more networks, any of the networks for which N is the emergency reporting service provider,

and references to a β€œrelevant service provider” are to be construed accordingly.

(1B)The telephone service provided for the purposes of paragraph (1)(a) must be contactable within Great Britain by the use of one telephone number.

(1C)Where the emergency reporting service provider is not the same for all networksβ€”

(a)the emergency reporting service providers must ensure, for the purposes of paragraph (1)(a), that they are all contactable within Great Britain by the use of the same telephone number, and

(b)where an emergency reporting service provider (β€œE”) also provides other means for enabling persons to report gas escapes to it, E must have in place arrangements to ensure that any gas escape notified to E which concerns a network for which E is not the emergency reporting service provider is notified forthwith to the relevant emergency reporting service provider.F21]

(2)[F22If an emergency reporting service providerF22] . is notified of such an escape of gas it shall, if it is not responsible for preventing the escape under paragraphs (4) or (5), report it forthwith to the person who is.

(3) A person referred to in regulation 6(2)(a) to (c) and the holder of a licence issued under section 7A(1) of the Gas Act 1986 who discovers or is notified of any such escape of gas (other than by virtue of a report made to him pursuant to paragraph (2)) shall report it forthwith to [F23the emergency reporting service provider for the relevant networkF23] .

[F24(3A)But paragraph (3) does not apply if the person who discovers or is notified of the escape of gas is the emergency reporting service provider for that network.F24]

(4) Where any gas escapes from a network the person conveying the gas in the part of the network from which the gas escapes shall, as soon as is reasonably practicable after being so informed of the escape, attend the place where the gas is escaping, and within 12 hours of being so informed of the escape, he shall prevent the gas escaping.

(5) Where any gas escapes from a gas fitting supplied with gas from a network, the person conveying the gas in the part of the network immediately upstream of the emergency control for the supply of gas to that fitting shall, as soon as is reasonably practicable after being so informed of the escape, attend the place where the gas is escaping, and within 12 hours of being so informed of the escape, he shall prevent the gas escaping.

(6) Where a person conveying gas in a network has reasonable cause to suspect that gas conveyed by him which has escaped has entered, or may enter, any premises, he shall, so far as is reasonably practicable, take all the steps necessary to avert danger to persons from such entry.

(7) If the responsible person for any premises knows or has reason to suspect that gas is escaping from a gas fitting in those premises supplied with gas from a network he shall immediately take all reasonable steps to cause the supply of gas to be shut off at such place as may be necessary to prevent further escape of gas.

(8) If gas continues to escape into those premises after the supply of gas has been shut off or when a smell of gas persists, the responsible person for the premises discovering such escape or smell shall immediately give notice of the escape or smell to [F25the emergency reporting service provider for the network from which the premises are supplied with gasF25] .

[F26(8A)But paragraph (8) does not apply if the responsible person is the emergency reporting service provider for that network.F26]

(9) Where an escape of gas has been stopped by shutting off the supply, no person shall cause or permit the supply to be re-opened (other than in the course of repair) until all necessary steps have been taken to prevent a recurrence of such escape.

(10) In any proceedings against a person for an offence consisting of a contravention of paragraphs (4) or (5) above it shall, in so far as the contravention is not preventing the escape of gas within the period of 12 hours referred to in those paragraphs, be a defence for the person to prove that it was not reasonably practicable for him effectually to prevent the gas from escaping within that period, and that he did effectually prevent the escape of gas as soon as it was reasonably practicable for him to do so.

(11) A person conveying gas[F27(β€œC”)F27] may appoint another person to act on [F28C’s behalfF28] to prevent an escape of gas, and where [F29C doesF29] so in advance of discovering or being notified of such an escapeβ€”

(a)[F30CF30] shall notify [F31the emergency reporting service provider for the networkF31] . of the name of the person appointed;

(b)the appointee shall in relation to the escape be responsible for complying with paragraphs (4) to (6) in substitution for [F32CF32] , and paragraph (6) shall have effect as if the reference to the person conveying gas having reasonable cause to suspect that the gas has entered or may enter premises were a reference to the appointee having such cause.

[F33(11A)But paragraph (11)(a) does not apply where C is the emergency reporting service provider for that network.F33]

(12) Where an escape of gas from a gas fitting on domestic premises has resulted in a fire or explosion, the person conveying the gas in the part of the network immediately upstream of the emergency control for the supply of gas to that fitting shall, as soon as is reasonably practicable after receiving notice of the fire or explosion, cause an investigation to be carried out so as to establish, so far as is reasonably practicable, whether the escape was from installation pipework or from an, and if so which, appliance.

(13) Where an escape of gas from a network has or was likely to have resulted in a fire or explosion, the person conveying the gas in the part of the network where the gas escaped shall, as soon as is reasonably practicable after receiving notice of the escape, cause an investigation to be carried out so as to establish the source of the escape and, so far as is reasonably practicable, the reason for it.

(14) Where an incident notifiable under [F34regulation 11(1) of the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013F34] has arisen as a result of an escape of carbon monoxide gas from incomplete combustion of gas in a gas fitting, the person who supplied the gas shall, as soon as is reasonably practicable after receiving notice of the incident, cause an investigation to be carried out so as to establish, so far as is reasonably practicable, the cause of the escape and accumulation of the carbon monoxide gas.

(15) Where a person who conveys gas receives notice of an incident referred to in paragraph (14), he shall, as soon as is reasonably practicable, inform the relevant gas supplier of that fact.

(16) A person who causes an investigation to be carried out pursuant to paragraphs (12), (13) or (14) shallβ€”

(a)ensure that the individuals who carry it out are competent;

(b)notify the Executive before the investigation begins of the intention to carry it out;

(c)ensure that a report of the investigation is prepared and a copy of it is sent to the Executive as soon as is reasonably practicable after the investigation has been completed.

(17) In this Regulationβ€”

(a)β€œthe responsible person” has the same meaning as in regulation 2(1) of [F35the 1998 RegulationsF35] ;

(b)any reference to an escape of gas from a gas fitting includes a reference to an escape or emission of carbon monoxide gas resulting from incomplete combustion of gas in such a fitting;

(c)any reference to a fire or explosion of gas is a reference to an unintended fire or explosion of gas;

(d)any reference to a person supplying gas does not include a reference to a person to whom the gas is supplied and who provides it for use in a flat or part of premises let by him.

Content and other characteristics of gasI8

8.β€”(1) No person shall, subject to [F36paragraphs (1A) to (4)F36] , convey gas in a network unless the gas conforms with the requirements specified in Part I of Schedule 3.

[F37(1A)A person may convey out of specification biogas from a relevant facility in a relevant pipe for treatment or blending so as to bring it into conformity with those requirements.

(1B)For the purposes of paragraph (1A)β€”

β€œout of specification biogas” means gas whichβ€”

(a)

is biogas or produced from biogas, and

(b)

does not conform with the requirements specified in Part 1 of Schedule 3;

β€œrelevant facility” means a biomethane production facility or a gas processing facility;

β€œrelevant pipe” means a pipe used exclusively for conveying gas (including out of specification biogas) toβ€”

(a)

the point where the gas is treated or blended, or

(b)

that point and non-domestic premises.F37]

(2) The network emergency co-ordinator may, where it is necessary to prevent a supply emergency and in accordance with the arrangements specified in his safety case pursuant to paragraph 3(d) of Schedule 2, authorise, for the period specified in the authorisation, gas not conforming with the requirements specified in Part I of Schedule 3 to be conveyed in the network if the gas conforms with the requirements specified in Part II of that Schedule.

(3) An authorisation under paragraph (2) may be given orally or in writing and may be withdrawn at any time.

(4) Where only one person conveys gas in a network, he may, where it is necessary to prevent a supply emergency and in accordance with the arrangements specified in his safety case pursuant to paragraph 19 of Schedule I, convey gas which does not conform with the requirements specified in Part I of Schedule 3 if the gas conforms with the requirements specified in Part II of that Schedule.

(5) A person who conveys gas in a network shall ensure that suitable and sufficient tests are carried out to ensure that the gas conforms with the requirements of paragraphs (1), (2) or (4), as appropriate.

[F38(6)But paragraph (5) does not apply in respect of any out of specification biogas which is conveyed in a relevant pipe as permitted by paragraph (1A).F38]

Keeping of documentsI9

9.β€”(1) A person who prepares a safety case pursuant to these Regulations shallβ€”

(a)ensure that when the safety case is sent to the Executive for acceptance it is notified of an address in Great Britain for the purposes of sub-paragraphs (b) to (f) below;

(b)keep the accepted safety case and any revision thereof or a copy thereof at that address;

(c)keep each audit report made by him or a copy thereof at that address;

(d)ensure that a record is made of any action taken in consequence of such an audit report and keep that record or a copy thereof at that address;

(e)ensure that a report is made of every review carried out by him pursuant to regulation 4(3) and ensure that a copy is sent to the Executive;

(f)keep such report or a copy thereof at that address; and

(g)ensure that a record is made of every test carried out pursuant to regulations 8(5) and 10(6) in relation to gas he conveys and keep that record or a copy thereof at that address.

(2) Each report and record required to be kept by paragraph (1) shall be kept for a period of 3 years after it has been made, and the safety case and revision shall be kept for so long as it is current.

(3) It shall be sufficient compliance with paragraph (1) for the information in the documents to be kept at the address notified on film or by electronic means provided that the information is capable of being reproduced as a written copy at that address and it is secure from loss or unauthorised interference.

(4) Where a person has notified an address pursuant to sub-paragraph (a) of paragraph (1), he may notify to the Executive a different address in Great Britain for the purposes of the provisions referred to in that sub-paragraph, and where he does so references in those provisions and in paragraph (3) where applicable to the address notified shall be construed as the address in the last notification made under this paragraph.

(5) In this regulation β€œaudit report” means a report made pursuant to the arrangements referred to in paragraph 11 of Schedule 1 or paragraph 4 of Schedule 2 (to the extent that the later mentioned paragraph relates to arrangements for audit).

[F39Pipes used to convey biogas or gas made from biogas: transitional provisions

10.β€”(1)A BPF pipe transporter (β€œB”) may continue to convey gas in a BPF pipe on and after 6th April 2023 despite the fact that B does not have a safety case prepared pursuant to regulation 3(1)(a) which has been accepted by the Executive.

(2)But paragraph (1) ceases to apply to Bβ€”

(a)on 6th October 2024, if B has not prepared a safety case pursuant to regulation 3(1)(a) and sent it to the Executive before that date;

(b)if the Executive rejects the safety case prepared by B pursuant to regulation 3(1)(a), on the date on which the Executive rejects B’s safety case (whether this date is [F40before, on or after 6th October 2024F40]).

(3)In this regulationβ€”

β€œBPF pipe transporter” means a person who, immediately before 6th April 2023β€”

(a)

is conveying gas in a BPF pipe; and

(b)

is not conveying gas in any part of any existing network to which the BPF pipe is connected;

β€œBPF pipe” means a pipe conveying gas from a biomethane production facility which, immediately before 6th April 2023β€”

(a)

is connected to an existing network; but

(b)

is not treated as part of that network for the purposes of these Regulations;

β€œexisting network” means a network within the meaning of these Regulations as they had effect immediately before 6th April 2023.F39]

[F39Transitional provisions: emergency reporting service provider safety case

10A.β€”(1)This regulation applies where, immediately before 6th April 2023, a person (β€œP”) has an accepted EHP safety case.

(2)P’s accepted EHP safety case is to be treated, on and after 6th April 2023, as if it had been prepared pursuant to, and accepted by the Executive under, regulation 3(3A).

(3)Accordingly, on 6th April 2023, P becomes the emergency reporting service provider for each network.

(4)Regulation 4 applies in relation to P as if the requirement in paragraph (3) of that regulation to make a thorough review of the contents of its accepted EHP safety case every three years were a requirement toβ€”

(a)make a thorough review of the accepted EHP safety case by the end of the period of three years beginning with the day on which P last reviewed that safety case, and

(b)at least every three years thereafter.

(5)Nothing in this regulation prevents P from giving written notice for the purposes of regulation 3(3B) on or after 6th April 2023 in relation to any or all of the networks.

(6)In this regulation β€œaccepted EHP safety case” means a safety case prepared pursuant to, and accepted by the Executive under, paragraph 3 of exemption No. 8 of 2016 granted by the Executive in pursuance of its powers under regulation 11(1) of these Regulations on 5th September 2016 to National Grid Gas Distribution Limited, a company registered in England and Wales with the company number 10080864.F39]

ExemptionsI10

11.β€”(1) Subject to paragraph (2), the Executive may, by a certificate in writing, exempt any person or class of persons from any requirement or prohibition imposed by these Regulations, and any such exemption may be granted subject to conditions and to a limit of time and may be revoked at any time by a certificate in writing.

(2) The Executive shall not grant any such exemption unless, having regard to the circumstances of the case and in particular toβ€”

(a)the conditions, if any, which it proposes to attach to the exemption; and

(b)any other requirements imposed by or under any enactment which apply to the case;

it is satisfied that the health and safety of persons likely to be affected by the exemption, will not be prejudiced in consequence of it.

Repeals, revocations and amendment

F4112. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

[F42Review of these Regulations

13.β€”(1)The Secretary of State must from time to timeβ€”

(a)carry out a review of the regulatory provisions contained in these Regulations, as amended by the Gas Safety (Management) (Amendment) Regulations 2023;

(b)set out the conclusions of the review in a report; and

(c)publish the report.

(2)Section 30(4) of the Small Business, Enterprise and Employment Act 2015(5) requires that a report must in particularβ€”

(a)set out the objectives intended to be achieved by the regulatory regime established by the regulatory provisions referred to in paragraph (1)(a),

(b)assess the extent to which the objectives are achieved, and

(c)assess whether those objectives remain appropriate, and if so, the extent to which they could be achieved by a system which imposes less onerous regulatory provision.

(3)The first report must be published before the end of the period of five years beginning with 6th April 2023.

(4)Subsequent reports must be published under this regulation at intervals not exceeding five years.

(5)In this regulation β€œregulatory provision” has the same meaning as in sections 28 to 32 of the Small Business, Enterprise and Employment Act 2015 (see section 32 of that Act).F42]

Signed by authority of the Secretary of State

Paul Beresford

Parliamentary Under Secretary of State,

Department of the Environment

4th March 1996

Regulation 3(1)

SCHEDULE 1PARTICULARS TO BE INCLUDED IN SAFETY CASE OF A PERSON CONVEYING GAS

GeneralI11,I12,I13,I14

1. Name and address of the person preparing the safety case (in this Schedule referred to as β€œthe duty holder”).

2. A description of the operation intended to be undertaken by the duty holder.

3. A general description of the plant and premises the duty holder intends to use in connection with the operation including, in particular, the geographical location where any pipes he uses joins pipes used by other persons for conveying gas.

4. Particulars of anyβ€”

(a)technical specifications;

(b)procedures or arrangements relating to operation and maintenance,

which the duty holder intends to follow in connection with the operation he intends to undertake insofar as they affect the health and safety of persons.

Safety managementI15,I16,I17,I18,I19,I20,I21

5. A statement of the significant findings of the risk assessment he has made pursuant to [F43regulation 3 of the Management of Health and Safety at Work Regulations 1999, and particulars of the arrangements he has made in accordance with regulation 5(1) thereof.F43]

6. Particulars to demonstrate that the management system of the duty holder is adequate to ensure that the relevant statutory provisions will (in respect of matters within his control) be complied with in relation to the operation he intends to undertake.

7. Particulars to demonstrate that the duty holder has established adequate arrangements for ensuring the competence of his employees in health and safety matters.

8. Particulars to demonstrate that the duty holder has established adequate arrangements for managing work carried out by persons who are not his employees on or in relation to plant or premises which he owns or controls.

9. Particulars to demonstrate that the duty holder has established adequate arrangements for passing information relevant to health and safety to persons within his undertaking.

10. Particulars to demonstrate that the duty holder has established adequate arrangements for passing and receiving information relevant to health and safety to and from other persons who have duties under these Regulations.

11. Particulars to demonstrate that the duty holder has established adequate arrangements for audit and the making of any necessary reports.

Co-operationI22

12. Particulars of the arrangements the duty holder has established to enable him to comply with regulation 6 (co-operation) including (except where he is the network emergency co-ordinator[F44or the emergency reporting service provider for the networkF44] ) particulars of the arrangements he has established to ensure that any directions given to him by the network emergency co-ordinator[F44or the emergency reporting service provider for the networkF44] are followed.

Gas escapes and investigationsI23,I24

13. Particulars of the arrangementsβ€”

(a)the duty holder and any emergency service provider appointed by him have established to enable him or the provider, as the case may be, to comply with regulation 7(4) to (6);

(b)the duty holder has established to appoint emergency service providers.

14. Particulars to demonstrate that the duty holder has established adequate arrangements to enable him to comply with paragraphs (12), (13), (15) and (16) of regulation 7, for co-ordinating the investigations he causes to be carried out pursuant to that regulation with other investigations carried out pursuant thereto, and for participating in such other investigations.

Content and other characteristics of gasI25

15. Particulars to demonstrate that the duty holder has established adequate arrangements to ensure that all gas he conveys complies with regulation 8.

Continuity of supplyI26,I27

16. Particulars to demonstrate that the duty holder has established adequate arrangements to minimise the risk of a supply emergency.

17. Particulars to demonstrate that the duty holder has established adequate arrangements to ensure that the gas he conveys will be at an adequate pressure when it leaves the part of the network used by him.

Supply emergenciesI28,I29,I30,I31

18. Particulars to demonstrate that the duty holder has established adequate arrangements for dealing with supply emergencies or other incidents which could endanger persons.

19. Where the duty holder is the only person conveying gas in a network, particulars to demonstrate that he has established adequate arrangements to decide when and for how long gas not conforming with the requirements of regulation 8(1) should be conveyed in the network pursuant to regulation 8(4).

20. Without prejudice to paragraph 18 above, particulars of the procedures that the duty holder has established to discontinue safely supply to consumers, when it is known there is insufficient gas to satisfy demand.

21. Particulars of the procedures that the duty holder has established to restore safely the gas supply to consumers, following an interruption in supply.

InterpretationI32

22. In this Scheduleβ€”

(a)β€œaudit” means systematic assessment of the adequacy of the management system to achieve the purpose referred to in paragraph 6 carried out by persons who are sufficiently independent of the system (but who may be employed by the duty holder) to ensure that such assessment is objective;

(b);β€œmanagement system” means the organisation and arrangements established by the duty holder for managing his undertaking;

(c)any reference to an operation intended to be undertaken by the duty holder is a reference to his intended operation of conveying gas in a network.

Regulation 3(2)

SCHEDULE 2PARTICULARS TO BE INCLUDED IN SAFETY CASE OF A NETWORK EMERGENCY CO-ORDINATORI33,I34,I35,I36

1. Name and address of the person preparing the safety case (in this Schedule referred to as β€œthe duty holder”).

2. A general description of the network to which the safety case relates, including the geographical location of where pipes used by different persons conveying gas in the network join.

3. Particulars to demonstrate that the duty holder has established adequate arrangements for co-ordinating the actions to be taken to prevent a supply emergency includingβ€”

(a)particulars to demonstrate that the duty holder has established adequate arrangements to monitor gas flow within the network in order to identify a forthcoming supply emergency;

(b)in cases where it is not possible to obtain sufficient gas, particulars of the procedures and arrangements that the duty holder has established to direct persons conveying gas to secure a reduction in consumption and to verify that such directions have been followed;

(c)particulars of the procedures that the duty holder has established to monitor the situation throughout a supply emergency, and details of the procedures established to restore safely the gas supply to consumers, once the emergency is over;

(d)particulars to demonstrate that the duty holder has established adequate arrangements to decide when and for how long gas not conforming with the requirements of regulation 8(1) should be conveyed in the network pursuant to regulation 8(2);

(e)particulars to demonstrate that the duty holder has established adequate arrangements for rehearsing and testing the actions to be taken in the case of a supply emergency;

(f)a general description of the plant and premises the duty holder intends to use in connection with the arrangements and procedures described in his safety case pursuant to this paragraph.

4. The same particulars as are referred to in paragraphs 4 to 11 of Schedule 1 as if any reference in paragraphs 4 and 6 thereof to the operation intended to be undertaken were a reference to the network emergency co-ordinator’s functions under the arrangements and procedures described in his safety case.

Regulation 8

SCHEDULE 3CONTENT AND OTHER CHARACTERISTICS OF GAS

PART IREQUIREMENTS UNDER NORMAL CONDITIONSI37,I38,I39,I40

1. The content and characteristics of the gas shall be in accordance with the values specified in the following table.

Content or characteristicValue
hydrogen sulphide content≀5 mg/m3;
total sulphur content (including H2S)≀50 mg/m3;
hydrogen content≀0.1% (molar);
oxygen content[F45≀1.0% (molar), where the gas is conveyed in a pipe operated at a pressure of ≀38 barg, and ≀0.2% molar, where the gas is conveyed in a pipe operated at a pressure of >38 bargF45] ;
impuritiesshall not contain solid or liquid material which may interfere with the integrity or operation of pipes or any gas appliance (within the meaning of regulation 2(1) of [F46the 1998 RegulationsF46] ) which a consumer could reasonably be expected to operate;
hydrocarbon dewpoint and water dewpointshall be at such levels that they do not interfere with the integrity or operation of pipes or any gas appliance (within the meaning of regulation 2(1) of [F47the 1998 RegulationsF47] ) which a consumer could reasonably be expected to operate;
[F48RD ≀0.700F48]
WN

(i) ≀51.41 MJ/m3, and

(ii) [F49β‰₯46.50 MJ/m3F49];

F50...F50...
F51...F51...

2. The gas shall have been treated with a suitable stenching agent to ensure that it has a distinctive and characteristic odour which shall remain distinctive and characteristic when the gas is mixed with gas which has not been so treated, except that this paragraph shall not apply where the gas is at a pressure of above 7 barg.

3. The gas shall be at a suitable pressure to ensure the safe operation of any gas appliance (within the meaning of regulation 2(1) of [F52the 1998 RegulationsF52] ) which a consumer could reasonably be expected to operate.

4.β€”(1) Expressions and the abbreviations used in this Part shall have the meanings assigned to them in Part III of this Schedule.

F53(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART IIREQUIREMENTS FOR GAS CONVEYED TO PREVENT A SUPPLY EMERGENCYI41,I42

1. The requirements of the gas referred to in regulation 8(2) and (4) areβ€”

(a)WNβ€”

(i)≀52.85 MJ/m3, and

(ii)β‰₯46.50 MJ/m3; and

F54(b). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

and in all other respects the gas shall conform to the requirements specified in Part I of this Schedule, as if those requirements were repeated herein.

2.β€”(1) Expressions and abbreviations used in this Part shall have the meanings assigned to them in Part III of this Schedule.

F55(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART IIIINTERPRETATIONI43,I44

1. In this Scheduleβ€”

β€œbar” means bars (absolute);

β€œbarg” means bars (gauge);

β€œC” means degrees Celsius;

F56...

F57...

F58...

[F59β€œgross calorific value” means the gross calorific value, expressed in MJ/ m3, of a dry gas determined on the basis that the water produced by combustion is assumed to be condensed;F59]

β€œmg/m3” means milligrams per cubic metre [F60under the reference conditionsF60] ;

[F61β€œMJ/m3” means megajoules per cubic metre under the reference conditions;F61]

F62...

F63...

[F64β€œrelative density” (β€œRD”) means the ratio of VG to VA (expressed in the same units) whereβ€”

F65...

[F66β€œWN” means the Wobbe Number of the gas, which is calculated in accordance with the following formulaβ€”F66]

F67...

[F681A.In this Schedule, the reference conditions are 15C and 1.01325 bar.F68]

F692. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(1)

1974 c. 37; section 1(1) was extended by section 2(1) of the Offshore Safety Act 1992 (c. 15), and sections 15 and 50 were amended by the Employment Protection Act 1975 (c. 71), Schedule 15, paragraphs 6 and 16 respectively.

(2)

1986 c. 44; section 7A was inserted by section 6 of the Gas Act 1995.

(3)

Section 6A of the Gas Act 1986 was inserted by section 4 of the Gas Act 1995.

Status: There are currently no known outstanding effects for the Gas Safety (Management) Regulations 1996.
Gas Safety (Management) Regulations 1996 (1996/551)

Displaying information

Status of this instrument

footnotecommentarytransitional and savingsin force statusrelated provisionsgeo extentinsert/omitsource countin force adj
F1Words in reg. 2(1) omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 3(2)(a)omitted
F2Words in reg. 2(1) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 3(2)(b)inserted
F3Words in reg. 2(1) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 3(2)(c)substituted
F4Words in reg. 2(1) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 3(2)(d)inserted
F5Words in reg. 2(1) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 3(2)(e)inserted
F6Words in reg. 2(2) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 3(3)inserted
F7Words in reg. 2(4) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 3(4)(a)inserted
F8Words in reg. 2(4) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 3(4)(b)inserted
F9Words in reg. 2(4) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 3(4)(c)substituted
F10Reg. 2(10A) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 3(5)inserted
F11Word in reg. 3(1) omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 4(2)(a)omitted
F12Reg. 3(1)(aa) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 4(2)(b)inserted
F13Reg. 3(3A)-(3C) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 4(3)inserted
F14Words in reg. 3(4) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 4(4)inserted
F15Words in reg. 5(1) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 5inserted
F16Words in reg. 6(1) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 6(2)substituted
F17Words in reg. 6(2)(c) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 6(3)(a)inserted
F18Reg. 6(2)(ca) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 6(3)(b)inserted
F19Words in reg. 6(2)(h) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 6(3)(c)(i)inserted
F20Words in reg. 6(2)(h) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 6(3)(c)(ii)inserted
F21Reg. 7(1)-(1C) substituted for reg. 7(1) (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(2)substituted
F22Words in reg. 7(2) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(3)substituted
F23Words in reg. 7(3) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(4)substituted
F24Reg. 7(3A) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(5)inserted
F25Words in reg. 7(8) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(6)substituted
F26Reg. 7(8A) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(7)inserted
F27Word in reg. 7(11) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(8)(a)(i)inserted
F28Words in reg. 7(11) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(8)(a)(ii)substituted
F29Words in reg. 7(11) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(8)(a)(iii)substituted
F30Word in reg. 7(11)(a) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(8)(b)(i)substituted
F31Words in reg. 7(11)(a) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(8)(b)(ii)substituted
F32Word in reg. 7(11)(b) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(8)(c)substituted
F33Reg. 7(11A) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(9)inserted
F34Words in reg. 7(14) substituted (1.10.2013) by The Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013 (S.I. 2013/1471), reg. 1(2)(3), Sch. 4 Table 2 (with reg. 19)this amendment (text substituted) should be read in conjunction with other related provisions, see the commentary.substituted
F35Words in reg. 7(17)(a) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 7(10)substituted
F36Words in reg. 8(1) substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 8(2)substituted
F37Reg. 8(1A)(1B) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 8(3)inserted
F38Reg. 8(6) inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 8(4)inserted
F39Regs. 10, 10A substituted for reg. 10 (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 9substituted
F39Regs. 10, 10A substituted for reg. 10 (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 9substituted
F40Words in reg. 10(2)(b) substituted (1.4.2024) by The Health and Safety and Nuclear (Fees) (Amendment) and Gas Safety (Miscellaneous Amendment) Regulations 2024 (S.I. 2024/322), regs. 1(1), 17 (with reg. 1(3))this amendment (text substituted) should be read in conjunction with other related provisions, see the commentary.substituted
F41Reg. 12 omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 10omitted
F42Reg. 13 inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 11inserted
F43Words in Sch. 1 para. 5 substituted (29.12.1999) by The Management of Health and Safety at Work Regulations 1999 (S.I. 1999/3242), reg. 1(1), Sch. 2 (with regs. 2(1), 30)this amendment (text substituted) should be read in conjunction with other related provisions, see the commentary.substituted
F44Words in Sch. 1 para. 12 inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 12inserted
F45Words in Sch. 3 Pt. 1 table substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(2)(a)(i)substituted
F46Words in Sch. 3 Pt. 1 table substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(2)(a)(ii)substituted
F47Words in Sch. 3 Pt. 1 table substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(2)(a)(iii)substituted
F48Words in Sch. 3 Pt. 1 table inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(2)(a)(iv)inserted
F49Words in Sch. 3 Pt. 1 table substituted (6.4.2025) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(2), 14(2)(a)(v) (as amended by S.I. 2023/320, regs. 1, 2)substituted
F50Words in Sch. 3 Pt. 1 table omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(2)(a)(vi)omitted
F51Words in Sch. 3 Pt. 1 table omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(2)(a)(vii)omitted
F52Words in Sch. 3 Pt. 1 para. 3 substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(2)(b)substituted
F53Sch. 3 Pt. 1 para. 4(2) omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(2)(c)omitted
F54Sch. 3 Pt. 2 para. 1(b) omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(3)(a)(i)omitted
F55Sch. 3 Pt. 2 para. 2(2) omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(3)(b)omitted
F56Words in Sch. 3 Pt. 3 para. 1 omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(i)omitted
F57Words in Sch. 3 Pt. 3 para. 1 omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(ii)omitted
F58Words in Sch. 3 Pt. 3 para. 1 omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(iii)omitted
F59Words in Sch. 3 Pt. 3 para. 1 inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(iv)inserted
F60Words in Sch. 3 Pt. 3 para. 1 substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(v)substituted
F61Words in Sch. 3 Pt. 3 para. 1 substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(vi)substituted
F62Words in Sch. 3 Pt. 3 para. 1 omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(vii)omitted
F63Words in Sch. 3 Pt. 3 para. 1 omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(viii)omitted
F64Words in Sch. 3 Pt. 3 para. 1 substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(ix)substituted
F65Words in Sch. 3 Pt. 3 para. 1 omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(x)omitted
F66Words in Sch. 3 Pt. 3 para. 1 substituted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(xi)substituted
F67Words in Sch. 3 Pt. 3 para. 1 omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(a)(xii)omitted
F68Sch. 3 Pt. 3 para. 1A inserted (6.4.2023) by The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(b)inserted
F69Sch. 3 Pt. 3 para. 2 omitted (6.4.2023) by virtue of The Gas Safety (Management) (Amendment) Regulations 2023 (S.I. 2023/284), regs. 1(3), 14(4)(c)omitted
I1Reg. 1 in force at 1.4.1996, see reg. 1
I2Reg. 2 in force at 1.4.1996, see reg. 1
I3Reg. 3 in force at 1.4.1996, see reg. 1
I4Reg. 4 in force at 1.4.1996, see reg. 1
I5Reg. 5 in force at 1.4.1996, see reg. 1
I6Reg. 6 in force at 1.4.1996, see reg. 1
I7Reg. 7 in force at 1.4.1996, see reg. 1
I8Reg. 8 in force at 31.10.1996, see reg. 1
I9Reg. 9 in force at 1.4.1996, see reg. 1
I10Reg. 11 in force at 1.4.1996, see reg. 1
I11Sch. 1 para. 1 in force at 1.4.1996, see reg. 1
I12Sch. 1 para. 2 in force at 1.4.1996, see reg. 1
I13Sch. 1 para. 3 in force at 1.4.1996, see reg. 1
I14Sch. 1 para. 4 in force at 1.4.1996, see reg. 1
I15Sch. 1 para. 5 in force at 1.4.1996, see reg. 1
I16Sch. 1 para. 6 in force at 1.4.1996, see reg. 1
I17Sch. 1 para. 7 in force at 1.4.1996, see reg. 1
I18Sch. 1 para. 8 in force at 1.4.1996, see reg. 1
I19Sch. 1 para. 9 in force at 1.4.1996, see reg. 1
I20Sch. 1 para. 10 in force at 1.4.1996, see reg. 1
I21Sch. 1 para. 11 in force at 1.4.1996, see reg. 1
I22Sch. 1 para. 12 in force at 1.4.1996, see reg. 1
I23Sch. 1 para. 13 in force at 1.4.1996, see reg. 1
I24Sch. 1 para. 14 in force at 1.4.1996, see reg. 1
I25Sch. 1 para. 15 in force at 1.4.1996, see reg. 1
I26Sch. 1 para. 16 in force at 1.4.1996, see reg. 1
I27Sch. 1 para. 17 in force at 1.4.1996, see reg. 1
I28Sch. 1 para. 18 in force at 1.4.1996, see reg. 1
I29Sch. 1 para. 19 in force at 1.4.1996, see reg. 1
I30Sch. 1 para. 20 in force at 1.4.1996, see reg. 1
I31Sch. 1 para. 21 in force at 1.4.1996, see reg. 1
I32Sch. 1 para. 22 in force at 1.4.1996, see reg. 1
I33Sch. 2 para. 1 in force at 1.4.1996, see reg. 1
I34Sch. 2 para. 2 in force at 1.4.1996, see reg. 1
I35Sch. 2 para. 3 in force at 1.4.1996, see reg. 1
I36Sch. 2 para. 4 in force at 1.4.1996, see reg. 1
I37Sch. 3 Pt. I para. 1 in force at 1.4.1996, see reg. 1
I38Sch. 3 Pt. I para. 2 in force at 1.4.1996, see reg. 1
I39Sch. 3 Pt. I para. 3 in force at 1.4.1996, see reg. 1
I40Sch. 3 Pt. I para. 4 in force at 1.4.1996, see reg. 1
I41Sch. 3 Pt. II para. 1 in force at 1.4.1996, see reg. 1
I42Sch. 3 Pt. II para. 2 in force at 1.4.1996, see reg. 1
I43Sch. 3 Pt. III para. 1 in force at 1.4.1996, see reg. 1
I44Sch. 3 Pt. III para. 2 in force at 1.4.1996, see reg. 1
Defined TermSection/ArticleIDScope of Application
accepted EHP safety casereg. 10A.accepted_E_lgMZ1Vc
auditpara 22. of SCHEDULE 1audit_rtlEE5C
audit reportreg. 9.audit_repo_rtmgYlH
barpara PART III of SCHEDULE 3bar_rtxQIrg
bargpara PART III of SCHEDULE 3barg_rt2b27t
biogasreg. 2.biogas_lgYlY2Z
biomethanereg. 2.biomethane_lgImR9d
biomethane production facilityreg. 2.biomethane_lgqRjQJ
BPF pipereg. 10.BPF_pipe_lgedCJQ
BPF pipe transporterreg. 10.BPF_pipe_t_lgRtUjA
distribution mainreg. 2.distributi_rtkJasl
electricity generating stationreg. 2.electricit_rt9gX0X
emergency controlreg. 2.emergency__rtPZSTd
emergency reporting service providerreg. 2.emergency__lgyZIyq
emergency reporting service providerreg. 3.emergency__rtwfkdK
emergency service providerreg. 2.emergency__rtszYZn
existing networkreg. 10.existing_n_lg63Rhi
gasreg. 2.gas_rttklYk
gas fittingsreg. 2.gas_fittin_rtUqCIo
gas processing facilityreg. 2.gas_proces_rty0rJs
gas production facilityreg. 2.gas_produc_rtOiWw5
gross calorific valuepara PART III of SCHEDULE 3gross_calo_lgPrlzY
installation pipeworkreg. 2.installati_rtsFC7k
interconnectorreg. 2.interconne_rtiv8Gd
LNG facilityreg. 2.LNG_facili_lglORZe
management systempara 22. of SCHEDULE 1management_rtgOMcB
networkreg. 2.network_rtXKH1k
network emergency co-ordinatorreg. 2.network_em_rtNLLYI
out of specification biogasreg. 8.out_of_spe_lgDTgtW
pipereg. 2.pipe_rt6SZaa
RDpara PART III of SCHEDULE 3RD_lgIsq0I
regulatory provisionreg. 13.regulatory_lgaIcBD
relative densitypara PART III of SCHEDULE 3relative_d_lgsIRRB
relevant facilityreg. 8.relevant_f_lgRtCEV
relevant networkreg. 7.relevant_n_lgOuh3p
relevant pipereg. 8.relevant_p_lgKNBZL
relevant service providerreg. 7.relevant_s_rtMDBm8
safety casereg. 2.safety_cas_rttsQ2a
service pipereg. 2.service_pi_rtUfdPG
supply emergencyreg. 2.supply_eme_rty8LCC
the 1974 ActUnknown(β€œ_prnPBosu
the 1998 Regulationsreg. 2.the_1998_R_lg70vjr
the duty holderpara 1. of SCHEDULE 1the_duty_h_rtfXPUo
the duty holderpara SCHEDULE 2the_duty_h_rtUXNOD
the Executivereg. 2.the_Execut_rteeWVv
the relevant datereg. 3.the_releva_lgksak5
the responsible personreg. 7.the_respon_rt9ppjB
WNpara PART III of SCHEDULE 3WN_lg9yCfB
This instrument is derived from the version at www.legislation.gov.uk. To see a list of all amendments (including any to be made) check the resources page for this instrument on their website. Note, the status of this instrument is given above.
This instrument is derived from the version at www.legislation.gov.uk. To see original commencement information, check the resources page associated with this instrument. n.b. commencement information for marked amendments is embedded in the relevant footnote.

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.