Statutory Instruments

2002 No. 828

TOWN AND COUNTRY PLANNING, ENGLAND

The Town and Country Planning (General Development Procedure) (Amendment) (England) Order 2002

Made

26th March 2002

Laid before Parliament

28th March 2002

Coming into force

1st July 2002

The Secretary of State for Transport, Local Government and the Regions, in exercise of the powers conferred on him by sections 59, 69 and 333(7) of the Town and Country Planning Act 1990( 1 ) and all other powers enabling him in that behalf, hereby makes the following Order:

Citation, commencement and extent

1. —(1) This Order may be cited as the Town and Country Planning (General Development Procedure) (Amendment) (England) Order 2002 and shall come into force on 1st July 2002.

(2) This Order extends to England only.

Interpretation

2. In this Order—

the 1995 Order” means the Town and Country Planning (General Development Procedure) Order 1995( 2 ).

Changes to article 1: Interpretation

3. In article 1(2) of the 1995 Order

(a) after the definition of “outline planning permission” insert—

“planning obligation” means an obligation entered into by agreement or otherwise by any person interested in land pursuant to section 106 of the Act ( 3 ) ; ; and

(b) after the definition of “reserved matters” insert—

“section 278 agreement” means an agreement entered into pursuant to section 278 of the Highways Act 1980 ( 4 ) ; .

Changes to article 25: Register of applications

4. In article 25 of the 1995 Order

(1) Delete paragraph (3) and substitute the following—

(3) Part I of the register shall contain in respect of each such application and any application for approval of reserved matters made in respect of an outline planning permission granted on such an application, made or sent to the local planning register authority and not finally disposed of—

(a) a copy (which may be photographic) of the application together with any accompanying plans and drawings;

(b) a copy (which may be photographic) of any planning obligation or section 278 agreement proposed or entered into in connection with the application;

(c) a copy (which may be photographic) of any other planning obligation or section 278 agreement entered into in respect of the land the subject of the application which the applicant considers relevant; and

(d) particulars of any modification to any planning obligation or section 278 agreement included in Part I of the register in accordance with sub-paragraphs (b) and (c) above.

(2) After paragraph (4)(e) insert—

(f) a copy (which may be photographic) of any planning obligation or section 278 agreement entered into in connection with any decision of the local planning authority or the Secretary of State in respect of the application;

(g) a copy (which may be photographic) of any other planning obligation or section 278 agreement taken into account by the local planning authority or the Secretary of State when making the decision; and

(h) particulars of any modification to or discharge of any planning obligation or section 278 agreement included in Part II of the register in accordance with sub-paragraphs (f) and (g) above and paragraph (5) below. .

(3) In paragraph (5) after “effect of the Secretary of State’s decision” insert—

Signed by authority of the Secretary of State for Transport, Local Government and the Regions.

Falconer

Minister of State,

Department for Transport, Local Government and the Regions

26th March 2002

( 1 )

1990 c. 8 ; section 69 was amended by paragraph 13 of Schedule 7 to the Planning and Compensation Act 1991 (c. 34) . The functions of the Secretary of State under sections 59, 69 and 333(7) were, so far as exercisable in relation to Wales, transferred to the National Assembly for Wales by article 2 of and Schedule 1 to the National Assembly for Wales (Transfer of Functions) Order 1999, S.I. 1999/672 ; see the entry in Schedule 1 to the Town and Country Planning Act 1990 (c. 8) .

( 2 )

S.I. 1995/419 ; to which there are amendments not relevant to this Order.

( 3 )

Section 106 was substituted by section 12 of the Planning and Compensation Act 1991 (c. 34) .

( 4 )

1980 c. 66 , this section was substituted by section 23 of the New Roads and Street Works Act 1991 (c. 22) , there are other amendments not relevant to this Order.

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Town and Country Planning (General Development Procedure) (Amendment) (England) Order 2002 (2002/828)

Displaying information

Status of this instrument

footnotecommentarytransitional and savingsin force statusrelated provisionsgeo extentinsert/omitsource countin force adj
Defined TermSection/ArticleIDScope of Application
the 1995 Orderart. 2.the_1995_O_rtBrGpi
Changes that affect Made by
Sort descending by Changed Legislation Sort descending by Year and Number Changed Provision Type of effect Sort descending by Affecting Legislation Title Sort descending by Year and Number Affecting Provision Sort descending by Changes made to website text Note
The Town and Country Planning (General Development Procedure) (Amendment) (England) Order 2002 2002 No. 828 rev (with transtl provns and savings) The Town and Country Planning (Development Management Procedure) (England) Order 2010 2010 No. 2184 art 41 sch 9 Not yet

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.