Statutory Instruments

2002 No. 93

ELECTRICITY

The Electricity (Connection Charges) Regulations 2002

Made

17th January 2002

Laid before Parliament

21st January 2002

Coming into force

11th February 2002

M1,M2,M3 The Secretary of State in Exercise of the powers conferred on her by sections 19(2) and (3) , 60 and 64(1) of the Electricity Act 1989 and after consultation with the Gas and Electricity Markets Authority , hereby makes the following Regulations:—

Citation and commencement

1. These Regulations may be cited as the Electricity (Connection Charges) Regulations 2002 and shall come into force on 11th February 2002.

[F1 Application

1A. —(1) These Regulations do not apply in cases where a first connection is made on or after 6th April 2017.

(2) In paragraph (1), “first connection” has the meaning given in paragraph 1 of Schedule 5B to the 1989 Act. F1]

Interpretation

2. —(1) In these Regulations—

(2) In these Regulations—

(a) any reference to a numbered section is a reference to the section bearing that number in the Electricity Act 1989;

(b) any reference to a numbered regulation is a reference to the regulation bearing that number in these Regulations; and

(c) except where otherwise provided, any reference to a numbered paragraph is a reference to the paragraph bearing that number in the regulation in which the reference occurs.

Meaning of “eligible person”

3. —(1) In these Regulations—

eligible person” means any person who at the relevant time owns or occupies the relevant premises, and is—

(a)

an initial contributor;

(b)

a person who has been required to make a contribution to an electricity distributor or a public electricity supplier in accordance with these Regulations or the Old Regulations; or

(c)

a person to whom any right to receive a payment in accordance with these Regulations or the Old Regulations has been legally assigned.

F3 (2) In paragraph (1) “relevant premises” means the ... premises owned or occupied by a person at the time when he became either—

(a) an initial contributor; or

(b) a person required to make a contribution to an electricity distributor or a public electricity supplier in accordance with these Regulations or the Old Regulations,

in respect of the connection to those premises.

Prescribed period

4. The prescribed period for the purposes of these Regulations is five years after the provision of any electric line or electrical plant for the purpose of making a connection to the premises or distribution system of an initial contributor.

Entitlement to recover amount in respect of expenses

5. Subject to regulation 6, an electricity distributor may require a person requiring a connection under section 16(1) at any time after the coming into force of these Regulations to pay to the electricity distributor such an amount in respect of the relevant expenses as may be reasonable in all the circumstances if—

(a) the connection is required within the prescribed period;

(b) an initial contributor has made a payment to the electricity distributor or a public electricity supplier in respect of the relevant expenses;

(c) the electricity distributor or the public electricity supplier as the case may be has not recovered the relevant expenses in full; and

(d) the electricity distributor has made available to the person requesting the connection such information (if any) as may have been reasonably requested by that person for the purpose of ascertaining—

(i) the amount of the relevant expenses;

(ii) the date of the first provision of the electric line or electrical plant; and

(iii) the amounts paid in respect of the relevant expenses by the initial contributor or by persons previously required to make a payment under these Regulations or the Old Regulations.

Obligation to recover amount in respect of expenses

6. —(1) Subject to paragraphs (2) to [F4 (5) F4] , an electricity distributor shall exercise his rights under regulation 5 if within the prescribed period

(a) F5,F5 any electric line or electrical plant first provided for the purpose of making a connection to ... premises is subsequently used for the purpose of making a further connection to ... premises; and

(b) the relevant expenses have been wholly or mainly defrayed by the initial contributor or by that contributor and any other person previously required to make a payment in accordance with these Regulations or the Old Regulations.

(2) Subject to paragraphs (3) and (4), the electricity distributor shall exercise his rights under regulation 5 in the manner which he considers is best calculated to secure the recovery of an amount which is not more than the proportion of the relevant expenses which is appropriate having regard to the maximum [F6 capacity F6] required by the person requiring the further connection.

(3) Where the electricity distributor exercises his rights under regulation 5 in discharge of the obligation imposed on him by this regulation, regulation 5 shall be read and construed as if sub-paragraph (c) thereof had been omitted.

(4) The obligation imposed by this regulation shall not apply in any case where—

(a) the amount which would be applied in making payments to eligible persons in accordance with regulation 7, after deduction in accordance with that regulation of the administrative expenses of the electricity distributor, is insufficient to provide a payment of [F7 £300 F7] or more to at least one eligible person; or

(b) at the relevant time there are no eligible persons.

[F8 (5) The obligation imposed by this regulation shall not apply in the case of any electric line or electrical plant which was provided before 1st June 2003 for the purpose of making a connection to the premises of an initial contributor where those premises were not used wholly or mainly for domestic purposes. F8]

Payments to eligible persons

7. —(1) Where an electricity distributor has in discharge of the obligation imposed on him by regulation 6 recovered an amount, that amount shall, subject to paragraphs (2) to (4), be applied in making payments to eligible persons.

(2) The electricity distributor may deduct his administrative expenses from the amount mentioned in paragraph (1) before he makes any payments to eligible persons.

(3) Where payments fall to be made to two or more eligible persons in respect of the same relevant expenses in accordance with paragraph (1), each of those payments shall bear the same proportion to the aggregate of those payments as the proportion which each payment made by or in relation to each such eligible person bears to the aggregate of the payments made by or in respect of those eligible persons.

(4) The electricity distributor shall not be required by this regulation to make a payment to an eligible person if the amount of that payment would, but for this paragraph, be less than [F9 £300 F9] .

(5) Payments to eligible persons in accordance with this regulation shall be made as soon as practicable after the electricity distributor has recovered the amount out of which those payments are to be made.

Provision of information to eligible persons

8. Whenever an electricity distributor intends to use any electric line or electrical plant for the purpose of making a further connection in any circumstances where regulation 6 applies, he shall inform any eligible persons of that fact and shall also give them the following information—

(a) the amount which the electricity distributor calculates would be recoverable in accordance with that regulation; and

(b) the estimated amount of his administrative expenses.

[F10 Maintenance of records

8A. An electricity distributor shall maintain in relation to the provision of any electric line or electrical plant made on or after 1st June 2003 such records as are necessary to enable him to discharge the obligations imposed on him by these Regulations. F10]

Revocation

9. The Old Regulations are revoked.

Brian Wilson

Minister of State for Industry and Energy

Department of Trade and Industry

Status: There are currently no known outstanding effects for the The Electricity (Connection Charges) Regulations 2002.
The Electricity (Connection Charges) Regulations 2002 (2002/93)
Version from: 6 April 2017

Displaying information

Status of this instrument

in force Provision is in force
in force* In force only for specified purposes (see footnote)
not in force Not in force in England (may be in force in other geographies, see footnotes)
defined term Defined term
dfn Defined term (alternative style)
footnote commentary transitional and savings in force status related provisions geo extent insert/omit source count in force adj
F1 Reg. 1A inserted (6.4.2017) by The Electricity (Connection Charges) Regulations 2017 (S.I. 2017/106) , regs. 1 , 13 inserted
F2 Words in reg. 2(1) revoked (1.6.2003) by The Electricity (Connection Charges) (Amendment) Regulations 2002 (S.I. 2002/3232) , regs. 1 , 3(2)
F3 Word in reg. 3(2) revoked (1.6.2003) by The Electricity (Connection Charges) (Amendment) Regulations 2002 (S.I. 2002/3232) , regs. 1 , 3(3)
F4 Word in reg. 6(1) substituted (1.6.2003) by The Electricity (Connection Charges) (Amendment) Regulations 2002 (S.I. 2002/3232) , regs. 1 , 3(4) substituted
F5 Word in reg. 6(1) revoked (1.6.2003) by The Electricity (Connection Charges) (Amendment) Regulations 2002 (S.I. 2002/3232) , regs. 1 , 3(3)
F6 Word in reg. 6(2) substituted (1.6.2003) by The Electricity (Connection Charges) (Amendment) Regulations 2002 (S.I. 2002/3232) , regs. 1 , 3(5) substituted
F7 Sum in reg. 6(4)(a) substituted (1.6.2003) by The Electricity (Connection Charges) (Amendment) Regulations 2002 (S.I. 2002/3232) , regs. 1 , 3(6) substituted
F8 Reg. 6(5) added (1.6.2003) by The Electricity (Connection Charges) (Amendment) Regulations 2002 (S.I. 2002/3232) , regs. 1 , 3(7) added
F9 Sum in reg. 7(4) substituted (1.6.2003) by The Electricity (Connection Charges) (Amendment) Regulations 2002 (S.I. 2002/3232) , regs. 1 , 3(6) substituted
F10 Reg. 8A added (1.6.2003) by The Electricity (Connection Charges) (Amendment) Regulations 2002 (S.I. 2002/3232) , regs. 1 , 3(8) added
M1 Section 19 of the Electricity Act 1989 (c. 29) was amended by section 46 of the Utilities Act 2000 (c. 27) .
M2 See the definition of “prescribed”. The definition was amended by section 108 of and paragraphs 24, 38(1) and (6) of Schedule 6 to the Utilities Act 2000.
M3 The Gas and Electricity Markets Authority was established under section 1(1) of the Utilities Act 2000.
M4 S.I. 1990/527 .
M5 Section 6 was substituted by section 30 of the Utilities Act 2000 on 1st October 2001.
M6 Section 16(1) was substituted by section 44 of the Utilities Act 2000.
Defined Term Section/Article ID Scope of Application
administrative expenses reg. 2. def_46b2b623a6
eligible person reg. 2. def_cf0a87548e
eligible person reg. 3. def_ce50f58a75
first connection reg. 1A. def_e6af2bc3d1
initial contributor reg. 2. def_75c2014783
Old Regulations reg. 2. def_aa2306a7d2
prescribed period reg. 2. def_fa2a9d7586
public electricity supplier reg. 2. def_245086cb5b
relevant expenses reg. 2. def_b9bc0c0406
relevant premises reg. 3. def_ba58c07a25
relevant time reg. 2. def_80fe1006bf

Status of changes to instrument text