πŸ”† πŸ“– βž• πŸ‘€

Statutory Instruments

2005 No. 1646

ELECTRICITY

GAS

The Electricity and Gas Appeals (Designation and Exclusion) Order 2005

Made

18th June 2005

Laid before Parliament

22nd June 2005

Coming into force

14th July 2005

The Secretary of State, in exercise of the powers conferred on him by section 173 of the Energy Act 2004( 1 ), and having consulted the Gas and Electricity Markets Authority and such other persons as he considers appropriate, hereby makes the following Order:β€”

Citation, commencement and extent

1. β€”(1) This Order may be cited as the Electricity and Gas Appeals (Designation and Exclusion) Order 2005 and shall come into force on 14th July 2005.

(2) This Order does not extend to Northern Ireland.

Interpretation

2. In this Orderβ€”

β€œthe Act” means the Energy Act 2004;

β€œtransmission licence” has the same meaning as in section 6 of the Electricity Act 1989( 2 ); and

β€œtransportation licence” means a licence granted under section 7(2) of the Gas Act 1986( 3 ).

Designation of documents

3. For the purposes of section 173(2)(b) of the Act, the following documents are designatedβ€”

(a) the Balancing and Settlement Code, being the document of that title required to be prepared pursuant to Standard Condition C3 of transmission licences;

(b) the Connection and Use of System Code, being the document of that title required to be prepared pursuant to Standard Condition C10 of transmission licences;

(c) a Network Code, being a document of that title required to be prepared pursuant to the conditions of a transportation licence to which Standard Special Condition A11 (Network and Uniform Network Code) applies;

(d) the Supply Point Administration Agreement, being the document of that title required to be entered into pursuant to Standard Condition 34A of supply licences granted under section 7A of the Gas Act 1986( 4 );

(e) the Master Registration Agreement, being the document of that title required to be entered into pursuant to Standard Condition 37 of supply licences granted under section 6 of the Electricity Act 1989; and

(f) the Uniform Network Code, being the document of that title required to be prepared pursuant to Standard Special Condition A11 of transportation licences.

Exclusion of decisions

4. β€”(1) No appeal shall lie to the Competition Commission under section 173 of the Act from a decision made by GEMA on or after the date on which this Order comes into force, which consists in the giving or refusal of a consent by virtue of which a document designated in article 3 has effect or would have had effect as mentioned in section 173(2)(c) of the Act, if the relevant condition is satisfied in respect of that decision.

(2) For the purpose of paragraph (1), the relevant condition isβ€”

(a) in the case of a decision in relation to the Balancing and Settlement Code, the condition in article 5(1);

(b) in the case of a decision in relation to the Connection and Use of System Code, the condition in article 6(1);

(c) in the case of a decision in relation to a Network Code, the condition in article 7(1);

(d) in the case of a decision in relation to the Supply Point Administration Agreement, the condition in article 8(1);

(e) in the case of a decision in relation to the Master Registration Agreement, the condition in article 9(1); and

(f) in the case of a decision in relation to the Uniform Network Code, the condition in article 10(1).

5. β€”(1) The condition referred to in article 4(2)(a) is that the decision consists in the giving of a consent to a majority recommendation made by the Panel in the Modification Report.

(2) In this article, the words β€œPanel” and β€œModification Report” have the same meanings as in the Balancing and Settlement Code.

6. β€”(1) The condition referred to in article 4(2)(b) is that the decision consists in the giving of a consent to a majority recommendation of Panel Members in the Amendment Report.

(2) In this articleβ€”

(a) β€œmajority recommendation” means a recommendation that is supported by the majority of those views of Panel Members which, in the reasonable opinion of GEMA, are clearly expressed in the Amendment Report; and

(b) the words β€œPanel Members” and β€œAmendment Report” have the same meanings as in the Connection and Use of System Code.

7. β€”(1) The condition referred to in article 4(2)(c) is that the decision accords with a majority recommendation made by the Modification Panel in the Modification Report.

(2) In this article, the words β€œModification Panel” and β€œModification Report” have the same meanings as in the Uniform Network Code.

8. β€”(1) The condition referred to in article 4(2)(d) is that the decision consists in the giving of a consent to a Change Proposal.

(2) In this article, the expression β€œChange Proposal” has the same meaning as in the Supply Point Administration Agreement.

9. β€”(1) The condition referred to in article 4(2)(e) is that the decision consists in the giving of a consent to a resolution of the MEC arising from the Change Procedures.

(2) In this article, the words β€œMEC” and β€œChange Procedures” have the same meanings as in the Master Registration Agreement.

10. β€”(1) The condition referred to in article 4(2)(f) is that the decision consists in the giving of a consent to a majority recommendation made by the Modification Panel in the Modification Report.

(2) In this article, the words β€œModification Panel” and β€œModification Report” have the same meanings as in the Uniform Network Code.

11. When, on or after the date on which this Order comes into force, a decision in relation to a document designated in article 3 is made by GEMA, whichβ€”

(a) is not excluded under article 4 from the right of appeal which would otherwise be conferred by section 173 of the Act; and

(b) consists in the giving or refusal of a consent by virtue of which that document has effect or would have had effect as mentioned in section 173(2)(c) of the Act,

GEMA shall at the same time or as soon as reasonably practicable thereafterβ€”

(i) decide whether to exclude that decision under article 12; and

(ii) give notice of the decision taken under paragraph (i) in such manner as it considers appropriate for the purpose of bringing the matters to which the notice relates to the attention of persons likely to be interested.

12. GEMA may exclude a decision referred to in article 11(a) and (b) from the right of appeal conferred by section 173 of the Act if the delay caused by the holding of the appeal against that decision is likely to have a material adverse effect on the availability of electricity or gas for meeting the reasonable demands of consumers in Great Britain.

13. Where GEMA excludes a decision under article 12, it shall, as soon as reasonably practicable after the exclusion of that decision, publish a notice stating the reasons for its having exercised its power to exclude in such manner as it considers appropriate for the purpose of bringing the matters to which the notice relates to the attention of persons likely to be interested.

Malcolm Wicks

Minister of State for Energy,

Department of Trade and Industry

18th June 2005

( 1 )

2004 c. 20 .

( 2 )

1989 c. 29 ; section 6 was substituted for the original by the Utilities Act 2000 (c. 27) , section 30.

( 3 )

1986 c. 44 ; section 7(2) was amended by the Utilities Act 2000 (c. 27) , sections 3, 76 and 108, and Schedule 6, Part I, paragraphs 1 to 4.

( 4 )

1986 c. 44 . Section 7A was inserted by the Gas Act 1995 (c. 45) , section 6(1).

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Electricity and Gas Appeals (Designation and Exclusion) Order 2005 (2005/1646)

Displaying information

Status of this instrument

footnotecommentarytransitional and savingsin force statusrelated provisionsgeo extentinsert/omitsource countin force adj
Defined TermSection/ArticleIDScope of Application
Amendment Reportart. 4.Amendment__rt1QtG5
Change Proceduresart. 4.Change_Pro_rtupM8R
Change Proposalart. 4.Change_Pro_rtDBE0p
majority recommendationart. 4.majority_r_rtQ8pb3
MECart. 4.MEC_rtY4eWo
Modification Panelart. 4.Modificati_rtndTXp
Modification Panelart. 4.Modificati_rtg3awh
Modification Reportart. 4.Modificati_rtD3Wo6
Modification Reportart. 4.Modificati_rtF3Lhc
Modification Reportart. 4.Modificati_rt3qTo9
Panelart. 4.Panel_rtaPrRt
Panel Membersart. 4.Panel_Memb_rt996Mx
the Actart. 2.the_Act_rt4wC1p
transmission licenceart. 2.transmissi_rtOYAVm
transportation licenceart. 2.transporta_rtnCTus
This instrument is derived from the version at www.legislation.gov.uk. To see a list of all amendments (including any to be made) check the resources page for this instrument on their website. Note, the status of this instrument is given above.
This instrument is derived from the version at www.legislation.gov.uk. To see original commencement information, check the resources page associated with this instrument. n.b. commencement information for marked amendments is embedded in the relevant footnote.

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.