Statutory Instruments
2007 No. 993
ELECTRICITY, ENGLAND AND WALES
The Electricity Act 1989 (Exemption from the Requirement for a Generation Licence) (Burbo Bank) (England and Wales) Order 2007
Made
21st March 2007
Laid before Parliament
26th March 2007
Coming into force
1st May 2007
The Secretary of State makes the following Order in exercise of the powers conferred by section 5 of the Electricity Act 1989( 1 ).
In accordance with section 5(2) of that Act he has given notice of the proposal to make the Order and has considered the representations made in relation to that proposal.
Citation, commencement and extent
1. —(1) This Order may be cited as the Electricity Act 1989 (Exemption from the Requirement for a Generation Licence) (Burbo Bank) (England and Wales) Order 2007 and shall come into force on 1st May 2007.
(2) This Order does not extend to Scotland.
Interpretation
2. In this Order—
“the Act” means the Electricity Act 1989;
“Burbo Bank Wind Farm” means the offshore wind farm known as the Burbo Offshore Wind Farm and located at Ordnance Survey map reference SD 211000 on the west side of the sand bank known as Burbo Bank, which lies off the coast of Cheshire;
“Seascape Energy” means Seascape Energy Limited, registered in England and Wales with number 04129545;
“total system in England and Wales” has the same meaning as it has in the Electricity (Class Exemptions from the Requirement for a Licence) Order 2001( 2 ).
Exemption from section 4(1)(a) of the Act
3. Exemption is granted from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) to Seascape Energy in respect of the Burbo Bank Wind Farm.
Conditions on exemption
4. The exemption granted by article 3 to Seascape Energy is subject to compliance with the following conditions—
(a) that Seascape Energy does not hold a licence under section 6(1)(a) of the Act (licence authorising generation of electricity for supply)( 3 );
(b) that the Burbo Bank Wind Farm is connected to the total system in England and Wales and (except in circumstances outside the reasonable control of Seascape Energy) does not export more than 100 megawatts of electrical power to it at any time.
Truscott
Parliamentary Under Secretary of State for Energy
Department of Trade and Industry
21st March 2007
1989 c.29 ; section 5 was substituted by section 29 of the Utilities Act 2000 (c.27) .
S.I. 2001/3270 ; the definitions of “total system in England and Wales”, “total system in Scotland” and “total system in Great Britain” were substituted for the definition of “total system” by the Electricity (Class Exemption from the Requirement for a Licence) (Amendment) Order 2005 ( S.I. 2005/488 ), article 3.
Section 6 was substituted by section 30 of the Utilities Act 2000.