Loading…eh

🔆 📖 👤

Statutory Instruments

2009 No. 2344

Electricity, England And Wales

The Electricity (Exemption from the Requirement for a Generation Licence) (Lynn and Inner Dowsing) (England and Wales) Order 2009

Made

28th August 2009

Laid before Parliament

3rd September 2009

Coming into force

25th September 2009

The Secretary of State makes the following Order in exercise of the powers conferred by section 5 of the Electricity Act 1989( 1 ).

In accordance with section 5(2) of that Act the Secretary of State has given notice of the proposal to make the Order. No representations in respect of the proposal have been made.

Citation, commencement and extent

1. —(1) This Order may be cited as the Electricity (Exemption from the Requirement for a Generation Licence) (Lynn and Inner Dowsing) (England and Wales) Order 2009 and shall come into force on 25th September 2009.

(2) This Order does not extend to Scotland.

Interpretation

2. In this Order—

the Act” means the Electricity Act 1989 ;

Centrica (IDW) Limited” means the company of that name registered in Scotland with number SC213642;

Centrica (LW) Limited” means the company of that name registered in England and Wales with number 04155137;

Inner Dowsing Wind Farm” means the offshore wind farm known as Inner Dowsing Wind Farm located at Ordnance Survey map reference TF635688, approximately 5 kilometres off the coast of Skegness in Lincolnshire, and approximately 2 kilometres north of Lynn Wind Farm;

Lynn Wind Farm” means the offshore wind farm known as Lynn Wind Farm located at Ordnance Survey map reference TF645627, approximately 5 kilometres off the coast of Skegness in Lincolnshire, and approximately 2 kilometres south of Inner Dowsing Wind Farm; and

total system in England and Wales” has the same meaning as it has in the Electricity (Class Exemptions from the Requirement for a Licence) Order 2001 ( 2 ).

Exemption from section 4(1)(a) of the Act

3. Exemption is granted from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) to—

(a) Centrica (IDW) Limited in respect of Inner Dowsing Wind Farm; and

(b) Centrica (LW) Limited in respect of Lynn Wind Farm.

Conditions on exemption

4. The exemption granted by article 3(a) to Centrica (IDW) Limited is subject to compliance with the following conditions—

(a) that Centrica (IDW) Limited does not hold a licence under section 6(1)(a) of the Act( 3 ) (a generation licence);

(b) that Inner Dowsing Wind Farm is connected to the total system in England and Wales; and

(c) that, except in circumstances outside the reasonable control of Centrica (IDW) Limited, Inner Dowsing Wind Farm does not export more than 100 megawatts of electrical power to the total system in England and Wales.

5. The exemption granted by article 3(b) to Centrica (LW) Limited is subject to compliance with the following conditions—

(a) that Centrica (LW) Limited does not hold a licence under section 6(1)(a) of the Act;

(b) that Lynn Wind Farm is connected to the total system in England and Wales; and

(c) that, except in circumstances outside the reasonable control of Centrica (LW) Limited, Lynn Wind Farm does not export more than 100 megawatts of electrical power to the total system in England and Wales.

David Kidney

Parliamentary Under Secretary of State,

Department of Energy and Climate Change

28th August 2009

( 1 )

1989 c.29 ; section 5 was substituted by section 29 of the Utilities Act 2000 (c.27) .

( 2 )

S.I. 2001/3270 ; the definitions of “total system in England and Wales”, “total system in Scotland” and “total system in Great Britain” were substituted for the definition of “total system” by the Electricity (Class Exemption from the Requirement for a Licence) (Amendment) Order 2005 ( S.I. 2005/488 ), article 3.

( 3 )

Section 6 was substituted by section 30 of the Utilities Act 2000.

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Electricity (Exemption from the Requirement for a Generation Licence) (Lynn and Inner Dowsing) (England and Wales) Order 2009 (2009/2344)
Version from: original only

Displaying information

Status of this instrument

in force Provision is in force
in force* In force only for specified purposes (see footnote)
not in force Not in force in England (may be in force in other geographies, see footnotes)
defined term Defined term
dfn Defined term (alternative style)
footnote commentary transitional and savings in force status related provisions geo extent insert/omit source count in force adj
Defined Term Section/Article ID Scope of Application
Centrica (IDW) Limited art. 2. def_29a86bd61d
Centrica (LW) Limited art. 2. def_29ed8e266c
Inner Dowsing Wind Farm art. 2. def_0ff4f76a9c
Lynn Wind Farm art. 2. def_cb1f23be2c
the Act art. 2. def_e18f27b361
total system in England and Wales art. 2. def_f1298dd52f

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.

Contains public sector information licensed under the Open Government Licence v3.0.