Statutory Instruments

2015 No. 1406

Offshore Installations

The Offshore Installations (Safety Zones) (No. 2) Order 2015

Made

23rd June 2015

Coming into force in accordance with article 1(2)

The Secretary of State makes this Order—

(a)

in exercise of the powers conferred by section 22 of the Petroleum Act 1987( 1 ); and

(b)

for the purpose of giving effect to proposals submitted to him by the Health and Safety Executive under section 24(2A)( 2 ) of that Act.

Citation and commencement

1. —(1) This Order may be cited as the Offshore Installations (Safety Zones) (No. 2) Order 2015.

(2) This Order comes into force on 14th July 2015 except for article 2(1) which comes into force as provided in article 2(2).

Establishment of safety zones

2. —(1) A safety zone is established around each installation specified in column 1 of the Schedule (being an installation to be stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the Schedule.

(2) Paragraph (1) comes into force, as respects each installation specified in column 1 of the Schedule—

(a) on 14th July 2015, where the installation arrives at its station before that date; and

(b) when the installation arrives at its station, in any other case.

Amendment of the Offshore Installations (Safety Zones) Order 2015

3. In the Offshore Installations (Safety Zones) Order 2015( 3 ), in the Schedule, in the entry relating to Cladhan Field Development Project, for “61°08.89′ North” substitute “61°08.86′ North” and for “00°47.27′ East” substitute “00°47.17′ East”.

Signed by authority of the Secretary of State for Work and Pensions

Justin Tomlinson

Parliamentary Under Secretary of State,

Department for Work and Pensions

23rd June 2015

Article 2

SCHEDULE INSTALLATIONS

(1)

Name or other designation of the offshore installation

(2)

Latitude

(3)

Longitude

Alder Subsea Tie-back, Block 15/29a, Alder Field

58°06′04.977″ North

00°41′35.670″ East

Edradour Manifold, Block 206/4a, Edradour Field

60°56.04′ North

02°14.01′ West

Glenlivet Manifold, Block 214/30a, Glenlivet Field

61°04.60′ North

02°05.42′ West

Mariner Floating Storage Unit Subsea Installation, Block 9/11a, Mariner Field

59°36.50′ North

01°04.58′ East

( 1 )

1987 c. 12 .

( 2 )

Section 24(2A) was inserted by S.I. 1993/1823 and amended by S.I. 2008/960 .

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Offshore Installations (Safety Zones) (No. 2) Order 2015 (2015/1406)

Displaying information

Status of this instrument

footnotecommentarytransitional and savingsin force statusrelated provisionsgeo extentinsert/omitsource countin force adj
Defined TermSection/ArticleIDScope of Application

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.