Statutory Instruments
2017 No. 184
Transport
The High Speed Rail (London – West Midlands) (Nomination) Order 2017
Made
23rd February 2017
Coming into force
24th February 2017
The Secretary of State for Transport, in exercise of the powers conferred by section 45(1) of the High Speed Rail (London – West Midlands) Act 2017( 1 ), makes the following Order:
Citation and commencement
1. This Order may be cited as the High Speed Rail (London – West Midlands) (Nomination) Order 2017 and comes into force on 24th February 2017.
Appointment of nominated undertaker
2. —(1) High Speed Two (HS2) Ltd is be the nominated undertaker for—
(a) all purposes of the scheduled works; and
(b) subject to paragraph (2), the purposes of any other provision of the High Speed Rail (London – West Midlands) Act 2017 so far as connected with or in any way related to those works or otherwise for Phase One purposes.
(2) The purposes referred to in paragraph (1)(b) do not include the demolition of the Vezey Wing (and link bridge) of the former National Temperance Hospital at 110-112 Hampstead Road, London NW1 2LS.
Signed by authority of the Secretary of State
Andrew Jones
Parliamentary Under Secretary of State
Department for Transport
23rd February 2017