MM Packaging (UK) Ltd v Philip Potter & Ors
[2017] EWCA Civ 1471
Case details
Case summary
This appeal concerned the construction of a settlement agreement clause which provided for payment of "90 days of gross pay" to former employees. The central legal question was whether that phrase required calculation on a per diem basis (average daily pay multiplied by 90) or on a calendar basis (including non-working days) consistent with the statutory scheme for a protective award under the Trade Union and Labour Relations (Consolidation) Act 1992 (sections 188–190). The Court of Appeal held that the phrase should be read in its contractual context and, in particular, against the known fact that the agreement was compromising a union claim under section 189 for a protective award of up to 90 days. On that holistic reading the payment was to be calculated in the same way as a statutory protective award (calendar basis under section 190(2)).
The court rejected the narrower literal approach adopted by the trial judge and emphasised that pre-contractual negotiation evidence need not be admitted to obtain the correct contextual meaning where the objective matrix is clear. Because the correct construction favoured the defendant company, there was no need to decide the alternative counterclaim for rectification.
Case abstract
The appellant company closed its Bootle factory and entered into a comprehensive settlement agreement with its former employees and their trade union. Clause 1.2(ii) of the agreement provided for payment of "90 days of gross pay" to employees. The parties disputed whether that phrase required a per diem calculation (average daily pay times 90) or a calendar calculation consistent with statutory protective awards under section 189 of the Trade Union and Labour Relations (Consolidation) Act 1992 and the calculation method in section 190(2). The company paid on the calendar basis; some employees sued for declarations that the per diem approach applied. The company counterclaimed for rectification if the court preferred the claimants' construction.
The trial before HH Judge Graham Wood QC heard evidence about the negotiation process and adopted a construction favouring the per diem approach. On appeal to the Court of Appeal the principal issues were (i) the proper approach to construction of the written settlement clause and the admissibility and weight of evidence of pre-contractual negotiations, (ii) whether the clause should be read in its commercial and statutory context, and (iii) whether rectification would be required if the clause were construed for the claimants.
The Court of Appeal rejected the trial judge's isolated literal approach and his reliance on detailed negotiation evidence. The court applied a holistic objective approach to construction, placing decisive weight on the fact that the agreement explicitly compromised the union's section 189 claim for a protective award of up to 90 days and that the statutory scheme, via section 190(2), calculates remuneration on a calendar/week's pay basis. The court concluded that an objective reader would understand "90 days of gross pay" as referring to the claimed statutory entitlement and therefore to the calendar method of calculation. The appeal was allowed and the claim dismissed; the rectification issue did not require determination.
Held
Appellate history
Legislation cited
- Employment Rights Act 1996: Part XIV
- Trade Union and Labour Relations (Consolidation) Act 1992: Section 188
- Trade Union and Labour Relations (Consolidation) Act 1992: Section 189
- Trade Union and Labour Relations (Consolidation) Act 1992: Section 190
- Trade Union and Labour Relations (Consolidation) Act 1992: Section 192
- Transfer of Undertakings (Protection of Employment) Regulations 2006: Regulation 15
- Transfer of Undertakings (Protection of Employment) Regulations 2006: regulation 16(3)