The Gas and Electricity Markets Authority( 1 ), in exercise of the powers conferred by sections 7B(1), (2) and (11) and 47 of the Gas Act 1986( 2 ) makes the following Regulations:

Citation, commencement and revocation I1

1. β€”(1) These Regulations may be cited as the Gas (Applications for Licences and Extensions and Restrictions of Licences) Regulations 2019 and come into force on 5th July 2019.

(2)The Gas (Applications for Licences and Extensions and Restrictions of Licences) Regulations 2010( 3 ) (β€œthe 2010 Regulations”) are revoked.

Transitional provisions I2

2. β€”(1) Where an application has been made under the 2010 Regulations but at the date upon which these Regulations come into force the application has neither been granted nor refused, the application shall be treated thereafter as having been made under these Regulations.

(2) In relation to an application to which paragraph (1) applies, the Authority, where necessary, will require applicants to supplement their application with additional information to meet the requirements of these Regulations.

(3) Where, in relation to an application to which paragraph (1) applies, the applicant, before the coming into force of these Regulations, published a notice of the application in accordance with the 2010 Regulations, the requirements of these Regulations as regards publication shall be taken to have been met.

Interpretation I3

3. β€”(1) In these Regulationsβ€”

β€œthe 2000 Act” means the Utilities Act 2000( 4 )

β€œthe 2004 Act” means the Energy Act 2004( 5 );

β€œthe Act” means the Gas Act 1986;

β€œapplication” means an application for a licence, an application for an extension of a licence or an application for a restriction of a licence under the Act and references to an application in respect of a licence shall be construed accordingly;

β€œthe Authority” means the Gas and Electricity Markets Authority established by section 1 of the 2000 Act;

β€œdomestic premises” means premises used wholly or mainly for domestic purposes;

β€œextension”, in relation to a transporter licence, means an extension of the licence under section 7(4) of the Act( 6 ) and, in relation to a supplier licence or a shipper licence, means an extension of the licence under section 7A(4) of the Act( 7 );

β€œinterconnector licence” means a licence granted or to be granted under section 7ZA(1) of the Act( 8 );

β€œprincipal undertaking” means an undertaking within the meaning of section 1161 of the Companies Act 2006( 9 );)

β€œrelated person” means

(a)

in relation to an applicant who is the principal undertaking, a parent or subsidiary undertaking of the principal undertaking or a subsidiary undertaking of the parent undertaking of the principal undertaking, in each case within the meaning of section 1162 and Schedule 7 of the Companies Act 2006; and

(b)

in relation to any applicant (including such an undertaking), a connected person of the applicant within the meaning of section 286 of the Taxation of Chargeable Gains Act 1992( 10 );

β€œrestriction”, in relation to a transporter licence, means a restriction of the licence under section 7(4A) of the Act( 11 ) and, in relation to a supplier licence or a shipper licence, means a restriction of the licence under section 7A(6) of the Act;

β€œshares”, in relation to an applicant with share capital, means allotted shares; in relation to an applicant with capital but no share capital, means rights to share in the capital of the applicant; and in relation to an applicant without share capital, means interests (i) conferring any right to share in the profits or liability to contribute to the losses of the applicant; and (ii) giving rise to an obligation to contribute to the debts or expenses of the applicant in the event of winding up;

β€œshipper licence” means a licence granted or to be granted under section 7A(2) of the Act;

β€œsigned” includes signed in a manner which would for the purposes of section 7 of the Electronic Communications Act 2000( 12 ) be an electronic signature;

β€œsignificant managerial responsibility or influence” means where a person plays a role inβ€”

(a)

the making of decisions about how the whole or a substantial part of an undertaking’s activities are to be managed or organised, or

(b)

the actual managing or organising of the whole or a substantial part of those activities;

β€œsupplier licence” means a licence granted or to be granted under section 7A(1) of the Act;

β€œSupplier of Last Resort event” means when a direction is issued by the Authority pursuant to standard condition 8 of either a gas supply licence granted under section 7A(1) of the Act or an electricity supply licence granted under section 6(1)(d) of the Electricity Act 1989( 13 );

β€œtransporter licence” means a licence granted or to be granted under section 7 of the Act; and

β€œultimate holding company” means a holding company (within the meaning of sections 1159 and 1160 of the Companies Act 2006( 14 )) of the applicant which is not itself a subsidiary of another company, which is in the position to control, or exercise significant influence over, a policy of the applicant by virtue of rights under contractual arrangements or rights of ownership which are held by the company or of which the company is a beneficiary.

(2) In these Regulations, unless the context otherwise requires, a reference to a standard condition is a reference, β€”

(a) in relation to a shipper licence, a supplier licence or a transporter licence, to a standard condition which is determined under section 81(2) of the 2000 Act( 15 ); or

(b) in relation to an interconnector licence, to a standard condition which is determined under section 150(1) of the 2004 Act,

subject to any modifications of the standard conditions made under Part I of the Act, the 2000 Act, or the 2004 Act, after the determination under those sections.

(3) In these Regulations β€”

(a) any reference to the Schedule is a reference to the Schedule of these Regulations; and

(b) any reference to a numbered paragraph is a reference to the paragraph bearing that number in the regulation in which the reference occurs.

[F1 (4) These Regulations do not apply to applications in respect ofβ€”

(a) a β€œ smart meter communication licence ” as defined in section 7AB(1) of the Act; or

(b) a β€œ code manager licence ” as defined in section 7AC(1) of the Act. F1]

Manner of Application I4

4. An application shall be:

(a) made in writing, addressed to the Authority and delivered or sent by prepaid post to the Authority at its principal address or sent by electronic mail to an address specified by the Authority;

(b) signed and dated by or on behalf of the applicant, stating, where signed on behalf of the applicant, the capacity of the signatory; and

(c) accompanied by the prescribed fee referred to in regulation 7 of these Regulations.

Form of application I5

5. β€”(1) An application shall be made by completing in full the form shown in the Schedule.

(2) The application may not be considered by the Authority unless it is made in accordance with this regulation 5.

(3) The Authority may make further enquiries of the applicant about any matter connected with the application and may request additional information or documentation as set out in the form in the Schedule.

Additional information and documents to accompany application I6

6. β€”(1) Subject to paragraphs (2), (3) and (4)β€”

(a) an application in respect of a supplier licence shall be accompanied by the information and documents specified for that licence in the form in the Schedule;

(b) an application in respect of a shipper licence shall be accompanied by the information and documents specified for that licence in the form in the Schedule;

(c) an application in respect of a transporter licence shall be accompanied by the information and documents specified for that licence in the form in the Schedule; and

(d) an application in respect of an interconnector licence shall be accompanied by the information and documents specified for that licence in the form in the Schedule.

(2) The obligation imposed by paragraph (1) shall, to the extent that information and documents are specified in the Schedule by reference to, or in relation to, a standard condition, applyβ€”

(a) subject to paragraph (3), in the case of an application for a licence, other than for a supplier licence of the type described in section 8(2) of the Act( 16 ), as if the standard condition in question were to be included and have effect in any licence granted as a result of the application; and

(b) in the case of an application for an extension or restriction of a licence, in relation to such of the standard conditions in question as have been included and have effect in that licence.

(3) Where a modification to any standard condition is requested in an application made in accordance with these Regulations, the obligation imposed by paragraph (2)(a) shall be modified accordingly.

(4) The obligation imposed by paragraph (1)(a), (b) and (c) in relation to an application for an extension or restriction of a licence shall only apply to the extent that the information and documents differ from or add to the most recent information and documents provided in relation to an application made in accordance with these Regulations or in pursuance of a condition of the applicant’s licence.

Application Fees I7

7. β€”(1) Subject to paragraph (2), the prescribed fee in relation to an application of the description specified in the first column of the Table in the form in the Schedule shall be the corresponding fee specified in the second column of that Table.

(2) Where more than one fee would, but for this paragraph, be payable in respect of a particular application, the prescribed fee shall be the higher or highest such fee.

Publication of notice of application I8

8. β€”(1) The period prescribed for the purpose of section 7B(2) of the Act( 17 ) (notice of applications) is ten working days from the date the applicant is notified by the Authority that the application is duly made (β€œthe prescribed period”).

(2) The prescribed manner of publication for that purpose shall be either byβ€”

(a) requesting the Authority to place the notice on the website address of the Authority (at β€œwww.ofgem.gov.uk” or such other website address as may be notified to the applicant by the Authority in writing); or

(b) publishing the notice on the website address of the applicant and requesting the Authority to place a link to the applicant’s website address on the website address of the Authority (at β€œwww.ofgem.gov.uk” or such other website address as may be notified to the applicant by the Authority in writing).

(3) Where an application is for the restriction of a licence, the applicant shall also ensure that notice of application is published within the prescribed period in such newspapers as are calculated to ensure that the notice is circulated throughout the area to which the proposed restriction relates.

The seal of the Gas and Electricity Markets Authority here affixed is authenticated by the signature of

Legal seal

Mary Starks

A member of the Authority

For and by The Gas and Electricity Markets Authority

13th June 2019

Regulation 5

SCHEDULE I9

( 1 )

The Gas and Electricity Markets Authority was established under section 1(1) of the Utilities Act 2000 (c.27) .

( 2 )

1986 c.44 : section 7B of the Gas Act was inserted by section 74(7) of the Utilities Act 2000.

( 4 )

2000 c.27 .

( 5 )

2004 c.20 .

( 6 )

section 7 was substituted by section 5 of the Gas Act 1995 (c.45) .

( 7 )

section 7A was inserted by section 6 of the Gas Act 1995.

( 8 )

section 7ZA was inserted by section 149 of the Energy Act 2004.

( 9 )

2006 c.46 .

( 11 )

section 7(4A) was inserted by section 76(4) of the Utilities Act 2000.

( 12 )

2000 c.7 .

( 13 )

1989 c.29 .

( 14 )

2006 c.46 .

( 15 )

section 81(2) was amended by section 168(10) of the Energy Act 2004.

( 16 )

section 8(2) was amended by paragraph 2 of schedule 6 of the Utilities Act 2000

( 17 )

section 7B was inserted by section 7 of the Gas Act 1995.

Status: There are currently no known outstanding effects for the The Gas (Applications for Licences and Extensions and Restrictions of Licences) Regulations 2019.
The Gas (Applications for Licences and Extensions and Restrictions of Licences) Regulations 2019 (2019/1024)

Displaying information

Status of this instrument

footnotecommentarytransitional and savingsin force statusrelated provisionsgeo extentinsert/omitsource countin force adj
F1Reg. 3(4) substituted (25.5.2024) by The Energy Act 2023 (Consequential Amendments) Regulations 2024 (S.I. 2024/706) , regs. 1(2) , 35substituted
I1Reg. 1 in force at 5.7.2019, see reg. 1(1)
I2Reg. 2 in force at 5.7.2019, see reg. 1(1)
I3Reg. 3 in force at 5.7.2019, see reg. 1(1)
I4Reg. 4 in force at 5.7.2019, see reg. 1(1)
I5Reg. 5 in force at 5.7.2019, see reg. 1(1)
I6Reg. 6 in force at 5.7.2019, see reg. 1(1)
I7Reg. 7 in force at 5.7.2019, see reg. 1(1)
I8Reg. 8 in force at 5.7.2019, see reg. 1(1)
I9Sch. in force at 5.7.2019, see reg. 1(1)
Defined TermSection/ArticleIDScope of Application
applicationreg. 3.applicatio_rty8Vtb
code manager licencereg. 3.legTermbxDHUwdF
domestic premisesreg. 3.domestic_p_rtCKbTy
extensionreg. 3.extension_rt4wjOe
interconnector licencereg. 3.interconne_rtucv54
principal undertakingreg. 3.principal__rtgiWKE
related personreg. 3.related_pe_rtb3Ko7
restrictionreg. 3.restrictio_rtF5RfH
sharesreg. 3.shares_rtD3vd2
shipper licencereg. 3.shipper_li_rtb5ZB5
signedreg. 3.signed_rtQQ6YV
significant managerial responsibility or influencereg. 3.significan_rtyOE0e
smart meter communication licencereg. 3.legTerm1l0xxMFP
supplier licencereg. 3.supplier_l_rt7r1Nb
Supplier of Last Resort eventreg. 3.Supplier_o_rtTSaz4
the 2000 Actreg. 3.the_2000_A_rtiFMeg
the 2004 Actreg. 3.the_2004_A_rtB28Rl
the 2010 Regulationsreg. 1.(β€œ_prnbRqse
the Actreg. 3.the_Act_rtvkDmC
the Authorityreg. 3.the_Author_rtlPK65
the prescribed periodreg. 8.(β€œ_prngeDgB
transporter licencereg. 3.transporte_rtl6fyo
ultimate holding companyreg. 3.ultimate_h_rtlTbp7
This instrument is derived from the version at www.legislation.gov.uk. To see a list of all amendments (including any to be made) check the resources page for this instrument on their website. Note, the status of this instrument is given above.
This instrument is derived from the version at www.legislation.gov.uk. To see original commencement information, check the resources page associated with this instrument. n.b. commencement information for marked amendments is embedded in the relevant footnote.

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.