Loading…eh

🔆 📖 👤

Statutory Instruments

2019 No. 930

Electricity

The Electricity (Individual Exemptions from the Requirement for a Generation Licence) Order 2019

Made

13th May 2019

Laid before Parliament

15th May 2019

Coming into force

6th June 2019

The Secretary of State makes the following Order in exercise of the powers conferred by section 5 of the Electricity Act 1989( 1 ).

The Secretary of State has given notice of the proposal to make this Order in accordance with sections 5(2) and 5(3) of that Act, and consulted with the Scottish Ministers( 2 ). No representations in respect of the proposal have been made.

Citation and commencement

1. This Order may be cited as the Electricity (Individual Exemptions from the Requirement for a Generation Licence) Order 2019 and comes into force on 6th June 2019.

Interpretation

2. In this Order—

the Act” means the Electricity Act 1989 ;

Blackcraig Wind Farm” means the electricity generating station known as Blackcraig Wind Farm in Dumfries and Galloway, Scotland, whose entrance is situated at Ordnance Survey map reference NX718808;

Blackcraig Wind Farm (Scotland) Limited” means the company of that name registered in Scotland with number SC493311;

Clocaenog Forest Wind Farm” means the electricity generating station known as Clocaenog Forest Wind Farm which is in Clocaenog Forest in Conwy County Borough and in the County of Denbighshire, Wales, incorporating a substation which is situated at Ordnance Survey map reference SJ014588;

Innogy Renewables UK Limited” means the company of that name registered in England and Wales with number 02550622;

licensed generator” means the holder of a licence under section 6(1)(a) of the Act;

the total system” means all transmission systems and distribution systems, located in Great Britain, of holders of licenses under section 6(1)(b) and (c) of the Act( 3 ).

Exemptions from prohibition of unlicensed generation of electricity for supply

3. Exemption is granted from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) to—

(a) Blackcraig Wind Farm (Scotland) Limited in respect of Blackcraig Wind Farm; and

(b) Innogy Renewables UK Limited in respect of Clocaenog Forest Wind Farm.

Conditions on exemptions

4. The exemption granted by article 3(a) of this Order is subject to compliance with the following conditions—

(a) Blackcraig Wind Farm is connected to the total system;

(b) Blackcraig Wind Farm does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of Blackcraig Wind Farm (Scotland) Limited; and

(c) Blackcraig Wind Farm (Scotland) Limited is not a licensed generator in respect of Blackcraig Wind Farm.

5. The exemption granted by article 3(b) of this Order is subject to compliance with the following conditions—

(a) Clocaenog Forest Wind Farm is connected to the total system;

(b) Clocaenog Forest Wind Farm does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of Innogy Renewables UK Limited; and

(c) Innogy Renewables UK Limited is not a licensed generator in respect of Clocaenog Forest Wind Farm.

Kelly Tolhurst

Minister for Small Business, Consumer and Corporate Responsibility

Department for Business, Energy and Industrial Strategy

13th May 2019

( 1 )

1989 c. 29 ; section 5 was substituted by section 29 of the Utilities Act 2000 (c. 27) .

( 2 )

Under article 4 of, and Schedule 3 to, the Scotland Act 1998 (Transfer of Functions to the Scottish Ministers etc. ) Order 1999 ( S.I. 1999/1750 ), functions under section 5(1) of the Electricity Act 1989 are, in so far as they are exercisable in or as regards Scotland, only exercisable after consultation with the Scottish Ministers.

( 3 )

Section 6 was substituted by section 30 of the Utilities Act 2000 and section 6(1)(b) was further substituted by section 136(1) of the Energy Act 2004 (c. 20) .

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Electricity (Individual Exemptions from the Requirement for a Generation Licence) Order 2019 (2019/930)
Version from: original only

Displaying information

Status of this instrument

in force Provision is in force
in force* In force only for specified purposes (see footnote)
not in force Not in force in England (may be in force in other geographies, see footnotes)
defined term Defined term
dfn Defined term (alternative style)
footnote commentary transitional and savings in force status related provisions geo extent insert/omit source count in force adj
Defined Term Section/Article ID Scope of Application
Blackcraig Wind Farm art. 2. def_05b500665c
Blackcraig Wind Farm (Scotland) Limited art. 2. def_242ae400bd
Clocaenog Forest Wind Farm art. 2. def_165ef60d4e
Innogy Renewables UK Limited art. 2. def_86985104d6
licensed generator art. 2. def_0ecb7f984f
the Act art. 2. def_bad05ff2d4
the total system art. 2. def_e7cb3eb4c3

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.

Contains public sector information licensed under the Open Government Licence v3.0.