Statutory Instruments

2020 No. 650

Energy

The Domestic Renewable Heat Incentive Scheme and Renewable Heat Incentive Scheme (Amendment) Regulations 2020

Made

26th June 2020

Laid before Parliament

29th June 2020

Coming into force

20th July 2020

The Secretary of State, in exercise of the powers conferred by sections 100(1), (2)(a) and (b) and 104(2) of the Energy Act 2008( 1 ), makes the following Regulations.

In accordance with section 100(7) of that Act, the Secretary of State has obtained the consent of the Scottish Ministers to the making of these Regulations.

Citation and commencement

1. These Regulations may be cited as the Domestic Renewable Heat Incentive Scheme and Renewable Heat Incentive Scheme (Amendment) Regulations 2020 and come into force on 20th July 2020.

Amendment of the Domestic Renewable Heat Incentive Scheme Regulations 2014

2. —(1)Schedule 6 to the Domestic Renewable Heat Incentive Scheme Regulations 2014( 2 ) (expenditure for individual technologies) is amended as follows.

(2) In Part 1 (biomass plants), for Table 1 substitute—

Table 1

Assessment date Expenditure threshold Growth threshold Super expenditure threshold Super growth threshold
31st July 2020 £49.70m £0.76m £54.14m £1.04m
31st October 2020 £50.47m £0.77m £55.18m £1.04m
31st January 2021 £51.24m £0.77m £56.23m £1.05m
30th April 2021 £52.01m £0.77m £57.28m £1.05m
31st July 2021 £52.78m £0.77m £58.33m £1.05m
31st October 2021 £53.55m £0.77m £59.38m £1.05m
Any date after 30th January 2022 £54.32m £0.77m £60.43m £1.05m

(3) In Part 2 (air source heat pumps), for Table 2 substitute—

Table 2

Assessment date Expenditure threshold Growth threshold Super expenditure threshold Super growth threshold
31st July 2020 £51.00m £3.50m £68.10m £5.00m
31st October 2020 £54.50m £3.50m £73.10m £5.00m
31st January 2021 £58.00m £3.50m £78.10m £5.00m
30th April 2021 £61.50m £3.50m £83.10m £5.00m
31st July 2021 £65.00m £3.50m £88.10m £5.00m
31st October 2021 £68.50m £3.50m £93.10m £5.00m
Any date after 30th January 2022 £72.00m £3.50m £98.10m £5.00m

(4) In Part 3 (ground source heat pumps), for Table 3 substitute—

Table 3

Assessment date Expenditure threshold Growth threshold Super expenditure threshold Super growth threshold
31st July 2020 £38.14m £1.66m £52.12m £2.53m
31st October 2020 £39.80m £1.66m £54.66m £2.54m
31st January 2021 £41.48m £1.68m £57.21m £2.55m
30th April 2021 £43.16m £1.68m £59.76m £2.55m
31st July 2021 £44.84m £1.68m £62.31m £2.55m
31st October 2021 £46.52m £1.68m £64.86m £2.55m
Any date after 30th January 2022 £48.20m £1.68m £67.41m £2.55m

(5) In Part 4 (solar thermal plants), for Table 4 substitute—

Table 4

Assessment date Expenditure threshold Growth threshold Super expenditure threshold Super growth threshold
31st July 2020 £1.92m £0.07m £2.75m £0.12m
31st October 2020 £1.99m £0.07m £2.87m £0.12m
31st January 2021 £2.06m £0.07m £2.99m £0.12m
30th April 2021 £2.13m £0.07m £3.11m £0.12m
31st July 2021 £2.20m £0.07m £3.23m £0.12m
31st October 2021 £2.27m £0.07m £3.35m £0.12m
Any date after 30th January 2022 £2.34m £0.07m £3.47m £0.12m

Amendment of the Renewable Heat Incentive Scheme Regulations 2018

3. —(1)The Renewable Heat Incentive Scheme Regulations 2018( 3 ) are amended as follows.

(2) In regulation 35 (tariff guarantees)

(a) in paragraph (6), for paragraph (c) substitute—

(c) the date by which such evidence must be provided, which must be no later than—

(i) 3 weeks from the date on which the provisional tariff guarantee notice is issued; or

(ii) 31st March 2021,

whichever is the earlier. ;

(b) after paragraph (7) insert—

(7A) Where the Authority has issued a notice under paragraph (7) before 20th July 2020 for an application made on or after 17th July 2019 and before 29th June 2020, the Authority may re-issue the notice substituting a date no later than 31st March 2022 as the date by which, for the purposes of the tariff guarantee, the plant must be commissioned or the injection of biomethane must commence. ;

(c) after paragraph (8) insert—

(8A) Where the Authority has revoked a tariff guarantee before 20th July 2020 for an application made on or after 17th July 2019 and before 29th June 2020 because the applicant failed to meet the condition imposed in accordance with paragraph (7)(b), the Authority may reissue a notice under paragraph (7) substituting a date no later than 31st March 2022 as the date by which, for the purposes of the tariff guarantee, the plant must be commissioned or the injection of biomethane must commence. ;

(d) in paragraph (11A), for “17th July 2019” substitute “29th June 2020 and before 20th July 2020”;

(e) after paragraph (11A) insert—

(11B) In relation to tariff guarantee applications made on or after 17th July 2019 and before 29th June 2020 or on or after 20th July 2020, the guaranteed tariff does not apply where—

(a) the tariff start date in relation to an accredited RHI installation is earlier than the date given under paragraph (4)(b) or the tariff start date for a producer of biomethane for injection is earlier than the date given in accordance with paragraph (5)(a);

(b) the tariff guarantee has been revoked and a notice under paragraph (7) has not been reissued under paragraph (8A); or

(c) the tariff start date in relation to an accredited RHI installation or producer of biomethane for injection is after 31st March 2022. ;

(f) in paragraph (14)—

(i) in sub-paragraph (a), for “and 2020/2021” substitute “, 2020/2021, 2021/2022 and 2022/2023”;

(ii) at the end insert—

(e) may determine and publish that part of the budget allocation which will be allocated to a particular technology or group of technologies. .

(3) In regulation 59 (calculation and payment of periodic support payments to participants)

(a) in paragraph (1), after “Subject to” insert “paragraph (1A) and”;

(b) after paragraph (1) insert—

(1A) For an accredited RHI installation or producer of biomethane for injection with a tariff start date after 31st March 2021, periodic support payments are payable for the period beginning on the tariff start date and ending on 31st March 2041. .

Kwasi Kwarteng

Parliamentary Under Secretary of State

Department for Business, Energy and Industrial Strategy

26th June 2020

( 1 )

2008 c. 32 . Section 100 is amended by section 51 of the Infrastructure Act 2015 (c. 7) and S.I. 2011/2195 . Section 51 also amended section 105 of the Energy Act 2008 (parliamentary control of subordinate legislation) and inserted subsections (3A) to (3I) concerning provisions which require the affirmative resolution procedure. By virtue of section 105(3A) to (3I), these Regulations do not attract the affirmative procedure.

( 2 )

S.I. 2014/928 , amended by S.I. 2016/257 and S.I. 2019/1052 . There are other amending instruments but none is relevant.

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Domestic Renewable Heat Incentive Scheme and Renewable Heat Incentive Scheme (Amendment) Regulations 2020 (2020/650)

Displaying information

Status of this instrument

footnotecommentarytransitional and savingsin force statusrelated provisionsgeo extentinsert/omitsource countin force adj
Defined TermSection/ArticleIDScope of Application

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.