Albion Energy Ltd v Energy Investments Global BRL
[2020] EWHC 301 (Comm)
Case details
Case summary
The claimant, Albion, sought summary judgment for the final instalment of the purchase price ($13.3m) under a sale and purchase agreement dated 31 January 2018. The defendant, EIGL, relied on an arbitration clause in a later escrow agreement and asserted an equitable set-off based on an intended unfair prejudice petition in Jersey arising from alleged improper payments identified by an Alvarez & Marsal review.
The court held that the escrow agreement's ICC arbitration clause was confined to disputes arising out of that escrow letter and did not displace the English jurisdiction clause in the SpA for Albion's debt claim. The court interpreted the SpA releases and a specific carve-out for matters reported by Alvarez as preserving EIGL's substantive claims but rejected EIGL's contention that those claims could provide a realistic equitable set-off to defeat Albion's summary judgment application.
On the merits the court concluded there was no real prospect that an unfair prejudice petition would produce an order requiring Albion to pay EIGL such that an equitable set-off could be established. Accordingly the court refused the s.9 Arbitration Act 1996 stay and granted summary judgment for Albion for the balance and interest.
Case abstract
Background and nature of the application. Albion sold its remaining 20% interest in Heritage to EIGL under a sale and purchase agreement (SpA) for $100m. Two initial instalments were paid; the final instalment became the subject of dispute after allegations arising from an Alvarez & Marsal review of Heritage’s payments. The parties entered into an escrow agreement for part of the outstanding sum. Albion applied for summary judgment for the escrowed balance of $13.3m. EIGL applied for a stay under s.9 of the Arbitration Act 1996 relying on the escrow agreement arbitration clause, alternatively for leave to defend and for a stay pending proposed Jersey proceedings for unfair prejudice.
Issues framed by the court. The court first addressed whether the arbitration clause in the escrow agreement compelled a mandatory stay under s.9. If not, the court considered whether Albion was entitled to summary judgment or whether EIGL had a realistic defence by way of equitable set-off founded on a prospective unfair prejudice petition in Jersey. The court also considered whether the SpA releases precluded EIGL’s claims and whether a right of set-off was excluded by the SpA.
Facts and documentary background. The SpA contained a general English jurisdiction clause. The escrow agreement (entered subsequently by three of the six SpA parties) contained an ICC arbitration clause limited to disputes "arising out of or in connection with this letter". The SpA contained termination and release clauses (clauses 7 and 8) and a specific carve‑out preserving claims "which relate to any matter reported by Alvarez and Marsal". The Alvarez review identified a number of payments and expense items (Nigerian consultancy payments, payments to a Turkish company, director expenses, and jet costs) which EIGL characterised as the "Disputed Payments".
Reasoning on the arbitration stay. Applying authorities on overlapping dispute resolution clauses and a commercial, purposive construction (including BNP Paribas v Trattamento and related authorities), the court concluded the arbitration clause in the escrow agreement was focused on obligations created by that agreement, not on the separate debt claim under the SpA. The court relied on the wording of the arbitration clause, the preservation clause in the escrow agreement, the fact that only three SpA parties were signatories to the escrow agreement, and the commercial implausibility of supplanting the SpA forum for the debt claim. Accordingly the s.9 stay was refused.
Reasoning on the summary judgment and equitable set-off. The court applied the established summary judgment test and analysed the legal basis for EIGL's proposed equitable set-off. The court accepted for present purposes that the Disputed Payments raised serious factual issues to be tried, but rejected EIGL's attempt to re-package Heritage's claims as the basis for an equitable set-off against Albion's debt. Key reasons were (i) EIGL was in control of Heritage throughout the relevant period and could have caused Heritage to pursue the claims, (ii) the essence of EIGL's complaint was misconduct simpliciter rather than ongoing unfair management of the company’s affairs such that relief against Albion personally was unlikely, (iii) EIGL had substantial knowledge of the matters before the SpA and had preserved such claims by carve-out in the SpA, and (iv) EIGL did not demonstrate a realistic basis to quantify any compensation exceeding Albion's claim. The court therefore found no realistic prospect of succeeding with the set-off defence and allowed Albion's summary judgment claim.
Procedural and wider observations. The court noted authorities dealing with the allocation of dispute resolution clauses between principal and ancillary/security documents and observed that different forums for principal and security matters are common and commercially explicable.
Held
Cited cases
- In the matter of the Nortel Companies, [2013] UKSC 52 positive
- Aectra Refining & Marketing Inc v Exmar NV, [1994] 1 WLR 1634 positive
- Connaught Restaurants Ltd v Indoor Leisure Ltd, [1994] 1 WLR 592 positive
- Manzanilla Ltd v Corton Property and Investments Ltd, [1996] EWCA Civ 942 neutral
- Re Legal Costs Negotiators Ltd, [1999] BCC 547 positive
- Al-Naimi (t/a Buildmaster Construction Services) v Islamic Press, [2000] CLC 647 positive
- Swain v Hillman, [2001] 1 All ER 91 positive
- ED & F Man Liquid Products v Patel, [2003] EWCA Civ 472 positive
- Re Chime Corp Ltd; Kung v Kou, [2004] HKCFA 73 positive
- ICI Chemicals & Polymers Ltd v TTE Training Ltd, [2007] EWCA Civ 725 positive
- Doncaster Pharmaceuticals Group Ltd v Bolton Pharmaceutical Co 100 Ltd, [2007] FSR 63 neutral
- Gamlestaden Fastigheter AB v Baltic Partners Ltd, [2007] UKPC 26 positive
- Satyam Computer Services Ltd v Upaid Systems Ltd, [2008] EWCA Civ 487 neutral
- UBS AG v HSH Nordbank AG, [2009] EWCA Civ 585 positive
- Deutsche Bank AG v Sebastian Holdings Inc, [2010] EWCA Civ 998 positive
- Geldof Metaalconstructive NV v Simon Carves Ltd, [2011] 1 Lloyd's Rep 517 positive
- PT Thiess Contractors Indonesia v PT Kaltim Prima Coal, [2011] EWHC 1842 (Comm) positive
- Transocean Offshore International Ventures Ltd v Burgundy Global Exploration Corp, [2012] 2 SLR 821 positive
- Cool Seas (Seafoods) Limited v Interfish Limited, [2018] 2038 (Ch) positive
- BNP Paribas v Trattamento Rifiuti Metropolitani SpA, [2019] EWCA Civ 768 positive
Legislation cited
- Arbitration Act 1996: Section 9
- Companies (Jersey) Law 1991: Article 74(1)
- Companies Act 2006: Section 994
- Companies Act 2006: Section 996(1)
- Insolvency Rules 1986: Rule 6.96