Summary
A company in liquidation retains its statutory and contractual right to refer a dispute arising under a construction contract to adjudication. Insolvency set-off does not extinguish the underlying claims or convert them exclusively into an insolvency dispute.
An adjudicator may determine set-offs and cross-claims raised as defences, although the adjudicator cannot make an affirmative monetary award to the respondent. Adjudication is a useful dispute-resolution process in its own right. Its utility does not depend upon immediate enforcement.
The court should not restrain adjudication merely because insolvency set-off applies or summary enforcement may be unavailable. Any risk to the respondent should ordinarily be addressed at the enforcement stage, through refusal of summary judgment, a stay of execution or suitable safeguards.
Treatment over time
Cited in 17 later judgments between 2020 and 2026, including 1 in the Supreme Court. Applied, followed or approved 7 times, most recently by the High Court in April 2026.
Most often cited for
- The statutory right to adjudicate supports a broad meaning of disputes arising under the contract
- Enforcement safeguards should address insolvency set-off risks without preventing adjudication
- Adjudication jurisdiction includes defences and set-off cross-claims, but not affirmative awards for respondents
Factual background
Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd concerned cross-claims arising from an electrical works sub-sub-contract. Bresco entered creditors’ voluntary liquidation and later referred its claims for unpaid work and damages to adjudication. Lonsdale asserted substantial contractual cross-claims and sought a declaration that the adjudicator lacked jurisdiction and an injunction restraining the adjudication.
Fraser J granted relief on jurisdictional grounds. The Court of Appeal, in [2019] EWCA Civ 27, held that the adjudicator had jurisdiction but continued the injunction because an award in favour of an insolvent company would ordinarily be unenforceable and the adjudication would therefore be futile.
Bresco appealed against the injunction. Lonsdale cross-appealed on jurisdiction. The central issues were whether insolvency set-off extinguished the underlying contractual disputes for adjudication purposes and whether anticipated enforcement difficulties justified restraining the adjudication.
Held
The appeal was allowed and the cross-appeal dismissed. Lord Briggs delivered the judgment, with which Lord Reed, Lord Kitchin, Lord Hamblen and Lord Leggatt agreed. The injunction restraining the adjudication could not stand.
Section 108 of the Housing Grants, Construction and Regeneration Act 1996 gives every party to a construction contract the right to refer a dispute arising under the contract to adjudication at any time. The provision contains no exclusion for a company in liquidation. Its statutory character favours recognition of the right and requires caution before the court interferes by injunction.
Insolvency set-off under rule 14.25 of the Insolvency (England and Wales) Rules 2016 does not cause the underlying claims and cross-claims to disappear for all purposes. Although set-off produces a single net balance, the individual claims must be resolved on their merits before that balance can be calculated. Contractual rights concerning dispute resolution therefore survive. The adjudicator had jurisdiction, and the cross-appeal was dismissed.
A reference of a contractual claim gives the adjudicator jurisdiction to decide every defence to it, including a cross-claim relied upon as a set-off. A clear link exists where the referred claim cannot be determined without deciding the cross-claim. In that situation they may constitute one dispute. The adjudicator may dismiss the company’s claim or declare the value of the cross-claim, but cannot make an affirmative monetary award to the respondent, which must prove for any balance in the liquidation.
Adjudication is not confined to maintaining cash flow through immediate payment. It is a mainstream, speedy and economical form of alternative dispute resolution which frequently achieves the practical final resolution of construction disputes. It may therefore serve a valuable purpose even where its outcome cannot immediately be enforced.
The reasoning in Twintec v Volkerfitzpatrick Ltd [2014] EWHC 10 (TCC) did not justify restraining an adjudication merely because an insolvent company brought it and cross-claims engaged insolvency set-off. Interference with the exercise of a statutory and contractual right requires exceptional justification, which was absent.
Enforcement difficulties should ordinarily be addressed if and when enforcement is sought. Following the approach in Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd, the court may refuse summary judgment, grant judgment with a stay, or consider undertakings which ring-fence the proceeds. Enforcement may nevertheless be proper where the adjudicator determines a net balance for the company and the respondent’s set-off rights are adequately protected.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
- United Kingdom Supreme Court: In Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd [2020] UKSC 25 , unanimously allowed Bresco’s appeal against the injunction and dismissed Lonsdale’s cross-appeal on jurisdiction.
- Court of Appeal: In [2019] EWCA Civ 27 , held that the adjudicator had jurisdiction but continued the injunction because the adjudication was considered futile in view of anticipated enforcement difficulties.
- Technology and Construction Court: Fraser J held that the adjudicator lacked jurisdiction and granted declaratory and injunctive relief restraining the adjudication.
Appeal route
- Appealed from · 24 January 2019Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd[2019] EWCA Civ 27 Court of Appeal (Civil Division)ReversedAppeal allowed; cross-appeal dismissed (unanimously)
- This judgment · 17 June 2020 [2020] UKSC 25 United Kingdom Supreme Court
Other judgments in these proceedings
3 judgments in these proceedings, earliest first. Linked by appeals and by the court numbers the judgments share.
- 31 July 2018Michael J Lonsdale (Electrical) Ltd v Bresco Electrical Services Ltd
- 24 January 2019Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd
- 17 June 2020Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd
Cases on related points
Of these 8 cases: 1 cited with it on one of its points; 3 cited alongside it for other points; 4 related in other ways.
Cited together forEnforcement safeguards should address insolvency set-off risks without preventing adjudication
1 related case for signed-in readers
Cited alongside it for other points
- Pilon Ltd v Breyer Group PlcA deliberate, material failure to consider a referred issue caused by an unduly narrow view of jurisdiction may make the decision unenforceableCited together in 3 later judgments
- Aspect Contracts (Asbestos) Limited v Higgins Construction PlcAdjudication overpayments may be recovered after final determination, potentially with interestCited together in 3 later judgments
+1 more for signed-in readers
Other related cases
- Meadowside Building Developments Ltd v 12-18 Hill Street Management Company LtdCited together in 3 later judgments
+3 more for signed-in readers
5 more related cases for signed-in readers. A free account is enough.
Key cases cited
19 authorities cited.
- The Joint Administrators of LB Holdings Intermediate 2 Limited v The Joint Administrators of Lehman Brothers International (Europe) and others [2017] UKSC 38
- Premium Nafta Products Limited (20th Defendant) and others (Respondents) v. Fili Shipping Company Limited (14th Claimant) and others (Appellants) [2007] UKHL 40
- Wight v Eckhardt Marine GmbH [2003] UKPC 37
- Stein v Blake [1996] AC 243
- Kaupthing Singer and Friedlander Ltd, Re [2010] EWCA Civ 518
- Speymill Contracts Ltd v Baskind [2010] EWCA Civ 120
- Connex South Eastern Ltd v M J Building Services Group Plc [2005] EWCA Civ 193
- Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd [2001] 1 All ER (Comm) 1041
- Meadowside Building Developments Ltd v 12-18 Hill Street Management Company Ltd [2019] EWHC 2651 (TCC)
- J Murphy & Sons Ltd v W Maher and Sons Ltd [2016] EWHC 1148 (TCC)
- Hillcrest Homes Ltd v Beresford and Curbishley Ltd [2014] EWHC 280 (TCC)
- Twintec Ltd v Volkerfitzpatrick Ltd [2014] EWHC 10 (TCC)
- Witney Town Council v Beam Construction (Cheltenham) Ltd [2011] EWHC 2332 (TCC)
- Cosco Bulk Carrier Co Ltd v Armada Shipping SA & Anor [2011] EWHC 216 (Ch)
- PC Harrington Contractors Ltd v Multiplex Constructions (UK) Ltd [2007] EWHC 2833 (TCC)
- In re Pan Atlantic Insurance Co Ltd [2003] EWHC 1696 (Ch)
- In re Bank of Credit and Commerce International SA (No 8) [1996] Ch 245
- MS Fashions Ltd v Bank of Credit and Commerce International SA [1993] Ch 425
- In re Norman Holding Co Ltd [1991] 1 WLR 10
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
17 later cases · 7 positive · 5 neutral · 5 caution
Most senior citing decisions:
- Abbey Healthcare (Mill Hill) Ltd v Augusta 2008 LLP (formerly Simply Construct (UK) LLP) [2024] UKSC 23 mentioned
- Crest Nicholson Regeneration Limited & Ors v Ardmore Construction Limited (in Administration) & Ors [2026] EWHC 789 (TCC) followed
- VMA Services Limited v Project One London Limited [2025] EWHC 1815 (TCC) distinguished
- London Eco Homes Limited v Raise Now Ealing Limited [2025] EWHC 1505 (TCC)
- BDW Trading Limited v Ardmore Construction Limited [2024] EWHC 3235 (TCC)
- Malin Industrial Concrete Floors Limited (in administration) v Volkerfitzpatrick Limited [2024] EWHC 2890 (TCC)
- Henry Construction Projects Limited v Promep Limited [2024] EWHC 1825 (TCC)
- Morganstone Limited v Birkemp Limited [2024] EWHC 933 (TCC)
- David John Frosdick v The Official Receiver [2023] EWHC 1262 (KB)
- JA Ball Limited (in administration) v St Philips Homes (Courthaulds) Ltd [2022] EWHC 3690 (TCC)
Sign in for the full treatment table, including the other 7 cases. A free account is enough.