πŸ”† πŸ“– βž• πŸ‘€

Statutory Instruments

2022 No. 702

ELECTRICITY , SCOTLAND

The Electricity (Individual Exemptions from the Requirement for a Generation Licence) (Scotland) Order 2022

Made

24th June 2022

Laid before Parliament

27th June 2022

Coming into force

19th July 2022

The Secretary of State makes the following Order in exercise of the powers conferred by section 5(1) of the Electricity Act 1989( 1 ).

The Secretary of State has given notice of the proposal to make this Order in accordance with section 5(2) and (3) of that Act, and consulted with the Scottish Ministers( 2 ). No representations in respect of the proposal have been made.

Citation, commencement and extent

1. β€”(1) This Order may be cited as the Electricity (Individual Exemptions from the Requirement for a Generation Licence) (Scotland) Order 2022 and comes into force on 19th July 2022.

(2) This Order extends to England and Wales and Scotland.

Interpretation

2. In this Order β€”

β€œ the Act ” means the Electricity Act 1989;

β€œ Creag Riabhach Wind Farm ” means the electricity generating station known as Creag Riabhach Wind Farm, located north of Lairg, and south of Altnaharra, Scotland, incorporating a substation whose entrance is situated at Ordnance Survey map reference NC529273;

β€œ Creag Riabhach Wind Farm Limited ” means the company of that name registered in Scotland with company number SC424471;

β€œ licensed generator ” means the holder of a licence under section 6(1)(a) of the Act;

β€œ Sandy Knowe Wind Farm ” means the electricity generating station known as Sandy Knowe Wind Farm, located south-west of Kirkconnel and Kelloholm, Scotland, incorporating a substation whose entrance is situated at Ordnance Survey map reference NS710100;

β€œ Sandy Knowe Wind Farm Limited ” means the company of that name registered in England and Wales with company number 06850950;

β€œ the total system ” means all transmission systems and distribution systems, located in Great Britain, of holders of licences under section 6(1)(b) and (c) of the Act( 3 ).

Exemption from prohibition of unlicensed generation of electricity for supply

3. Exemption is granted from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) toβ€”

(a) Creag Riabhach Wind Farm Limited in respect of Creag Riabhach Wind Farm; and

(b) Sandy Knowe Wind Farm Limited in respect of Sandy Knowe Wind Farm.

Conditions on exemption granted by article 3(a)

4. The exemption granted by article 3 (a) of this Order is subject to compliance with the following conditionsβ€”

(a) Creag Riabhach Wind Farm is connected to the total system;

(b) Creag Riabhach Wind Farm does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of Creag Riabhach Wind Farm Limited; and

(c) Creag Riabhach Wind Farm Limited is not a licensed generator in respect of Creag Riabhach Wind Farm.

Conditions on exemption granted by article 3(b)

5. The exemption granted by article 3 (b) of this Order is subject to compliance with the following conditionsβ€”

(a) Sandy Knowe Wind Farm is connected to the total system;

(b) Sandy Knowe Wind Farm does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of Sandy Knowe Wind Farm Limited; and

(c) Sandy Knowe Wind Farm Limited is not a licensed generator in respect of Sandy Knowe Wind Farm.

Greg Hands

Minister of State for Energy, Clean Growth and Climate Change

Department for Business, Energy & Industrial Strategy

24th June 2022

( 1 )

1989 c. 29 ; section 5 was substituted by section 29 of the Utilities Act 2000 (c. 27) .

( 2 )

Under article 4 of, and Schedule 3 to, the Scotland Act 1998 (Transfer of Functions to the Scottish Ministers etc.) Order 1999 ( S.I. 1999/1750 ), functions under section 5(1) of the Electricity Act 1989 are, in so far as they are exercisable in or as regards Scotland, only exercisable after consultation with the Scottish Ministers.

( 3 )

Section 6 was substituted by section 30 of the Utilities Act 2000 (c. 27) and section 6(1)(b) was further substituted by section 136(1) of the Energy Act 2004 (c. 20) .

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Electricity (Individual Exemptions from the Requirement for a Generation Licence) (Scotland) Order 2022 (2022/702)

Displaying information

Status of this instrument

footnotecommentarytransitional and savingsin force statusrelated provisionsgeo extentinsert/omitsource countin force adj
Defined TermSection/ArticleIDScope of Application
Creag Riabhach Wind Farmart. 2.legTerm6DUE3IkO
Creag Riabhach Wind Farm Limitedart. 2.legTerm4cTlasEa
licensed generatorart. 2.legTerm7RKFcdvF
Sandy Knowe Wind Farmart. 2.legTermXtKHe6Fj
Sandy Knowe Wind Farm Limitedart. 2.legTermbcR2WYvU
the Actart. 2.legTermHGjNXSQd
the total systemart. 2.legTerm27AuNOOy

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.