Abbey Healthcare (Mill Hill) Ltd v Augusta 2008 LLP (Court of Appeal judgment)
[2022] EWCA Civ 823
Case details
Case summary
The Court of Appeal held that a collateral warranty can, depending on its terms, amount to a "construction contract" within the meaning of s.104(1) of the Housing Grants (Construction & Regeneration) Act 1996. The relevant statutory test is whether the agreement is "for" the carrying out (or arranging the carrying out) of construction operations; that requires construction of the warranty's operative words and the contractual context rather than reliance on labels.
Applying that approach, the majority (Coulson LJ and Peter Jackson LJ) concluded that the Abbey Collateral Warranty contained both past and future-facing obligations (it warranted that Simply Construct "has performed and will continue to perform" its obligations under the building contract and warranted skill and care), and that the warranty was retrospective in effect. The date of execution therefore was not determinative: because the warranty created actionable obligations coterminous with the underlying building contract, it was a construction contract for the purposes of s.104(1), the Scheme was implied under s.108(5) and the adjudicator had jurisdiction.
The judge at first instance was therefore wrong to refuse summary judgment on the ground that the warranty was merely a product‑style guarantee because it was executed after practical completion. The Respondent’s Notice advancing alternative submissions was dismissed. Stuart‑Smith LJ dissented, concluding on his construction of the warranty that the document was in substance a warranty (a promise about the contractor's past and future performance under the primary contract) rather than an undertaking by the contractor to carry out works for the beneficiary and so did not constitute a construction contract.
Case abstract
Background and procedural posture. Abbey Healthcare (Mill Hill) Limited (tenant/beneficiary) sought summary judgment to enforce an adjudicator's decision awarding £908,495.98 against Simply Construct (contractor) following an adjudication under a collateral warranty executed after practical completion of the works. At first instance the deputy High Court judge ([2021] EWHC 2110 (TCC)) refused summary judgment, concluding the collateral warranty was not a "construction contract" under s.104(1) of the Housing Grants (Construction & Regeneration) Act 1996 because it was executed years after the construction operations had been completed. Permission to appeal was granted and this appeal followed.
Nature of the claim and relief sought. Abbey sought summary judgment to enforce an adjudicator's decision made under the implied Scheme of Construction Contracts; Simply Construct resisted on the basis that the collateral warranty was not a construction contract under s.104(1) and therefore the adjudicator lacked jurisdiction.
Issues framed by the Court of Appeal. The court identified three issues: (1) whether a collateral warranty can ever be a construction contract under s.104(1); (2) if so, whether the terms of the Abbey Collateral Warranty made it a construction contract; and (3) whether the date of execution of the collateral warranty affected that conclusion.
Facts in brief. Simply Construct entered a JCT Design and Build contract with Sapphire to build a care home; the contract required the contractor to execute collateral warranties in the form set out in Schedule 5 if requested. Works began in May 2015 and practical completion occurred in October 2016. After defects and remedial works, Simply Construct did not execute the collateral warranty in favour of Abbey until September 2020. Toppan (employer) and Abbey each pursued adjudications. The same adjudicator decided both disputes on 30 April 2021; Simply Construct refused payment and resisted enforcement by arguing lack of jurisdiction.
Court’s reasoning and conclusion. The majority held (i) a collateral warranty can be a construction contract if, on its wording and context, it is an agreement "for" the carrying out of construction operations; (ii) the Abbey Collateral Warranty warranted that Simply Construct "has performed and will continue to perform" its obligations under the building contract and warranted skill and care, thereby creating obligations that were prospective and so capable of being characterised as an agreement for the carrying out of construction operations; (iii) the warranty was retrospective in effect (it made the contractor’s liability coterminous with its liability under the building contract), so the late execution did not prevent it being a construction contract; and (iv) Parkwood Leisure v Laing O'Rourke was persuasive authority that comparable collateral warranties can be construction contracts. Accordingly the Scheme was implied and the adjudicator had jurisdiction; the appeal was allowed and the respondent’s alternative submissions dismissed. Stuart‑Smith LJ dissented on construction of the warranty, concluding the document was properly read as a promise about the contractor’s performance under the building contract (a warranty) which did not create a direct obligation to carry out works for the beneficiary and thus did not fall within s.104(1).
Subsidiary findings and implications. The court emphasised that whether any given collateral warranty is a construction contract depends on its precise terms and factual matrix; labels are not determinative. The decision confirms that timing of execution is not decisive where the warranty is expressed (or intended) to be retrospective.
Held
Appellate history
Cited cases
- Northern & Shell Plc v John Laing Construction Ltd., [2003] EWCA Civ 1035 positive
- Jeune v Queen's Cross Properties Ltd, [1972] Ch 97 neutral
- Modern Engineering (Bristol) Ltd v Gilbert-Ash (Northern) Ltd, [1974] AC 689 neutral
- Price v Strange, [1978] Ch 337 neutral
- Murphy v. Brentwood District Council, [1991] 1 AC 398 neutral
- Fencegate Ltd v James R Knowles Ltd, [2001] CILL 1757-1759 neutral
- Gillies Ramsay Diamond v PJW Enterprise Limited, [2002] CILL 1901/1903 positive
- Parkwood Leisure Ltd v Laing O'Rourke Wales and West Ltd, [2013] EWHC 2665 (TCC) positive
- Hurley Palmer Flatt Ltd v Barclays Bank PLC, [2014] EWHC 3042 (TCC) unclear
- Swansea Stadium Management Limited v City & County of Swansea, [2018] EWHC 2192 (TCC) positive
- C Spencer Ltd v M W High Tech Projects UK Ltd, [2020] EWCA Civ 331 positive
Legislation cited
- Housing Grants (Construction & Regeneration) Act 1996: Part II
- Housing Grants (Construction & Regeneration) Act 1996: Section 104(1) – s.104(1)
- Housing Grants (Construction & Regeneration) Act 1996: Section 105 – s.105
- Housing Grants (Construction & Regeneration) Act 1996: Section 108(5) – s.108(5)
- Housing Grants (Construction & Regeneration) Act 1996: Section 109 – s.109
- Scheme of Construction Contracts (England and Wales) Regulations 1998 (the Scheme): Regulation Scheme