Loading…eh

🔆 📖 👤

Statutory Instruments

2024 No. 168

ELECTRICITY

The Electricity (Criteria for Relevant Electricity Projects) (Transmission) Regulations 2024

Made

at 9.34 a.m. on 20th February 2024

Laid before Parliament

at 3.00 p.m. on 20th February 2024

Coming into force

12th March 2024

The Secretary of State makes these Regulations in exercise of the powers conferred by section 6BA(1)(b) and (5) of the Electricity Act 1989( 1 ).

In accordance with section 6BA(6) of that Act, the Secretary of State has consulted the Authority, such holders of relevant licences as the Secretary of State considers appropriate, and such other persons as the Secretary of State considers appropriate.

Citation, commencement and extent

1. —(1) These Regulations may be cited as the Electricity (Criteria for Relevant Electricity Projects) (Transmission) Regulations 2024 and come into force on 12th March 2024.

(2) These Regulations extend to England and Wales and Scotland.

Interpretation

2. In these Regulations—

the Act ” means the Electricity Act 1989 ;

early-model tender exercise ” means a tender exercise which relates to a project before the completion of preliminary works;

electricity solution ” means an asset or service delivered by a project;

late-model tender exercise ” means a tender exercise which relates to a project after the completion of preliminary works;

network need ” means a constraint on, or a requirement of, a transmission system( 2 );

preliminary works ” means—

(a)

in respect of a project’s electricity solution which principally comprises an asset—

(i)

the completion of the detailed design of the asset, and

(ii)

the acquisition of all necessary planning consents and property rights for its construction and maintenance; or

(b)

in respect of a project’s electricity solution which is a service—

(i)

the completion of the detailed design of the service, and

(ii)

where relevant, the acquisition of any necessary property rights for maintenance of any assets associated with the service;

tender exercise ” has the meaning given in section 6CD(3) of the Act( 3 ).

Criteria for projects

3. —(1) Subject to paragraphs (2) to (4), the criteria in regulations 4 to 8 are specified in respect of a project that relates to a transmission system, for the purposes of section 6BA(1)(b) of the Act.

(2) These Regulations do not apply to a project or any part of a project which is or may be subject to determination on a competitive basis of the person to whom an offshore transmission licence( 4 ) is to be granted under the Electricity (Competitive Tenders for Offshore Transmission Licences) Regulations 2015( 5 ).

(3) The criterion in regulation 7 applies only to early-model tender exercises.

(4) The criterion in regulation 8 applies only to late-model tender exercises.

Network Need criterion

4. A project’s electricity solution must be capable, with reasonable certainty, of addressing a network need.

Novelty criterion

5. —(1) A project’s electricity solution must, in respect of the transmission system and network need to which it relates, be wholly new.

(2) In this regulation “wholly new”, in respect of an asset, includes the entire replacement of an asset which forms part of a transmission system.

Separability criterion

6. —(1) A project’s electricity solution must be capable of being clearly distinguishable from any other part of the transmission system to which it relates and from any other electricity solution related to that transmission system.

(2) In respect of an early-model tender exercise, the ownership and control of a project’s electricity solution (including relevant planning consents and property rights) must be capable of being separable from the ownership and control of any part of the transmission system to which it relates and any other electricity solution which relates to that transmission system.

(3) In respect of a late-model tender exercise, the ownership and control of a project’s electricity solution (including relevant planning consents and property rights) must be separable from the ownership and control of any part of the transmission system to which it relates and any other electricity solution which relates to that transmission system.

Consumer benefit criterion in respect of an early-model tender exercise

7. —(1) A cost-benefit analysis in respect of a project must demonstrate that the non-tendered consumer impact does not outweigh the tendered consumer impact.

(2) In this regulation—

cost-benefit analysis ” means—

(a)

an analysis of the costs and of the benefits to consumers; and

(b)

a reasonable estimate of those costs and of those benefits;

non-tendered consumer impact ” means the estimated overall impact of a network need being addressed otherwise than through a tender exercise;

tendered consumer impact ” means the estimated overall impact of a network need being addressed by a project through a tender exercise.

High value criterion in respect of a late-model tender exercise

8. —(1) A project must have an estimated capital expenditure equal to or greater than £100,000,000.

(2) In this regulation “ estimated capital expenditure ” means an estimate of the total costs of a project, calculated by reference to one or more of the following—

(a) any costs relating to the purchase of component parts;

(b) construction costs;

(c) the costs of the acquisition of land on which it is to be situated;

(d) the costs of compliance with the conditions attached to planning consents and property rights;

(e) the costs of third-party works upon which a project’s electricity solution’s operation depends;

(f) project management costs;

(g) itemised risk and contingency allowances;

(h) costs relating to the procurement of itemised goods, services and works;

(i) any other costs that are reasonably integral or relevant to the arrangement, construction, commissioning, procurement, operation or function of the project’s electricity solution.

Graham Stuart

Minister of State for Energy Security and Net Zero

Department for Energy Security and Net Zero

at 9.34 a.m. on 20th February 2024

( 1 )

1989 c. 29 . Section 6BA was inserted by section 203 of, and paragraph 2 of Schedule 15 to, the Energy Act 2023 (c. 52) .

( 2 )

“Transmission system” is defined in section 64(1) of the Act (c. 29).

( 3 )

1989 c. 29 . Section 6CD was inserted by section 203 of, and paragraph 3 of Schedule 15 to, the Energy Act 2023 (c. 52) .

( 4 )

“Offshore transmission licence” is defined in section 64(1) of the Act (c. 29).

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Electricity (Criteria for Relevant Electricity Projects) (Transmission) Regulations 2024 (2024/168)
Version from: original only

Displaying information

Status of this instrument

in force Provision is in force
in force* In force only for specified purposes (see footnote)
not in force Not in force in England (may be in force in other geographies, see footnotes)
defined term Defined term
dfn Defined term (alternative style)
footnote commentary transitional and savings in force status related provisions geo extent insert/omit source count in force adj
Defined Term Section/Article ID Scope of Application
cost-benefit analysis reg. 7. def_1739944e22
early-model tender exercise reg. 2. def_85ede83f93
electricity solution reg. 2. def_38da0b83b7
estimated capital expenditure reg. 8. def_b6f0a7c125
late-model tender exercise reg. 2. def_8a503e836e
network need reg. 2. def_f8910c676b
non-tendered consumer impact reg. 7. def_14c9b0b86a
preliminary works reg. 2. def_3519314d22
tender exercise reg. 2. def_b5ee132a82
tendered consumer impact reg. 7. def_bbca96dffc
the Act reg. 2. def_c68e2fb4ae
wholly new reg. 5. def_b25b7e1916

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.

Contains public sector information licensed under the Open Government Licence v3.0.