ELECTRICITY, ENGLAND

The Electricity (Individual Exemption from the Requirement for a Generation Licence) (Slough Multifuel) (England) Order 2024

Made

22nd February 2024

Laid before Parliament

26th February 2024

Coming into force

29th March 2024

The Secretary of State makes this Order in exercise of the powers conferred by section 5(1) of the Electricity Act 1989( 1 ).

The Secretary of State has given notice of the proposal to make this Order in accordance with sections 5(2) and 5(3) of that Act. No representations in respect of the proposal have been made.

Citation, commencement, extent and application

1. β€”(1) This Order may be cited as the Electricity (Individual Exemption from the Requirement for a Generation Licence) (Slough Multifuel) (England) Order 2024 and comes into force on 29th March 2024.

(2) This Order extends to England and Wales and Scotland.

(3) This Order applies in relation to England only.

Interpretation

2. In this Orderβ€”

β€œ the Act ” means the Electricity Act 1989;

β€œ Slough Multifuel generating station ” means the electricity generating station known as Slough Multi-fuel generating station located in Slough, Berkshire, England, whose entrance is situated at Ordnance Survey map reference SU952815( 2 );

β€œ SSE Slough Multifuel Limited ” means the company of that name registered in England and Wales with company number 11271136;

β€œ the total system ” means all transmission systems and distribution systems, located in Great Britain, of holders of licenses under section 6(1)(b) and (c) of the Act( 3 ).

Exemption from prohibition of unlicensed generation of electricity for supply

3. Exemption is granted from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) to SSE Slough Multifuel Limited in respect of Slough Multifuel generating station.

Conditions on exemption

4. The exemption granted by article 3 of this Order is subject to compliance with the following conditionsβ€”

(a) Slough Multifuel generating station is connected to the total system;

(b) Slough Multifuel generating station does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of SSE Slough Multifuel Limited; and

(c) SSE Slough Multifuel Limited does not hold a licence under section 6(1)(a) of the Act in relation to Slough Multifuel generating station.

Claire Coutinho

Secretary of State for Energy Security and Net Zero

Department for Energy Security and Net Zero

22nd February 2024

( 1 )

1989 c. 29 ; section 5 was substituted by section 29 of the Utilities Act 2000 (c. 27) .

( 2 )

The Ordnance Survey map reference system is used to identify the position of a feature on Ordnance Maps (as defined in section 5 and Schedule 1 to the Interpretation Act 1978 (c.30) ).

( 3 )

Section 6 was substituted by section 30 of the Utilities Act 2000 and section 6(1)(b) was further substituted by section 136(1) of the Energy Act 2004 (c. 20) .

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Electricity (Individual Exemption from the Requirement for a Generation Licence) (Slough Multifuel) (England) Order 2024 (2024/195)

Displaying information

Status of this instrument

footnotecommentarytransitional and savingsin force statusrelated provisionsgeo extentinsert/omitsource countin force adj
Defined TermSection/ArticleIDScope of Application
Slough Multifuel generating stationart. 2.legTermv0SW56Cr
SSE Slough Multifuel Limitedart. 2.legTerm15P7KeoW
the Actart. 2.legTermmJhzaNXK
the total systemart. 2.legTermVvJHVI4J

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.