2026 No. 1151

ENERGY

The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2026

Made

2nd November 2026

Laid before Parliament

3rd November 2026

Coming into force

24th November 2026

The Secretary of State makes these Regulations in exercise of the powers conferred by section 27(2)(b) of the Energy Prices Act 2022(1).

Citation, commencement and extent

1.—(1) These Regulations may be cited as the Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2026 and come into force on 24th November 2026.

(2) These Regulations extend to England and Wales, Scotland and Northern Ireland.

Amendment of the Contracts for Difference (Electricity Supplier Obligations) Regulations 2014

2. The Contracts for Difference (Electricity Supplier Obligations) Regulations 2014(2) are amended as follows.

Amendment to regulation 2 (interpretation)

3. In regulation 2, in paragraph (1), in the definition of “SoS funds”, omit “(under section 154(2)(b) of the Act)”.

Amendment to regulation 5 (CFD quarterly contribution)

4. In regulation 5, for the definition of “SoS repayment” substitute—

“SoS repayment is the total amount of SoS funds that the CFD counterparty was required to repay during that period;”.

Amendment to regulation 7 (estimated cost, income & electricity supply)

5. In regulation 7—

(a)in paragraph (1), for “any SoS repayment and the CFD counterparty’s estimates of TGPR and NDSR” substitute “the CFD counterparty’s estimates of any SoS repayment, TGPR and NDSR”;

(b)in paragraph (2), before sub-paragraph (a) insert—

“(za)the terms on which any SoS funds have been or are expected to be provided to the CFD counterparty;”.

Polly Billington

Minister of State

Department for Energy Security and Net Zero

2nd November 2026

(2)

S.I. 2014/2014; relevant amending instruments are S.I. 2016/363, 2020/709 and 2024/1159.

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2026 (2026/1151)
Version from: original only

Details appear here

Hover a defined term or a footnote marker in the text, or select a case si note chip beside a section.

In-force status is shown at the top of the page. Upcoming changes are listed under the Future changes tab.

in force Provision is in force
in force* In force only for specified purposes (for detail about the purposes see/hover footnote)
not in force Not in force in England (may be in force in other geographies, see footnotes)
italics Defined term
dfn Defined term (alternative style)
gry bckgrd the in-force status of the provision is complex, check the footnotes

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.