Loading…

Statutory Instruments

2026 No. 728

INFRASTRUCTURE PLANNING

The Infrastructure Planning (Timetable for Deciding Request for Direction) Regulations 2026

Made

30th June 2026

Laid before Parliament

3rd July 2026

Coming into force

24th July 2026

The Secretary of State makes these Regulations in exercise of the powers conferred by section 35D of the Planning Act 2008(1).

Citation, commencement, extent and interpretation

1.—(1) These Regulations may be cited as the Infrastructure Planning (Timetable for Deciding Request for Direction) Regulations 2026.

(2) These Regulations come into force on 24th July 2026.

(3) These Regulations extend to England and Wales and (subject to paragraph (4)) to Scotland.

(4) These Regulations extend to Scotland only so far as required for the purpose of the construction (other than by a gas transporter) of an oil or gas cross-country pipe-line(2)—

(a)one end of which is in England or Wales, and

(b)the other end of which is in Scotland.

(5) In these Regulations—

the primary deadline ” means the end of the period of 35 days beginning with the day on which the Secretary of State receives the qualifying request( 3 );

the requestor ” means the person making the qualifying request;

the secondary deadline ” means the end of the period of 21 days beginning with the day on which the requestor is asked to provide the information under regulation 3.

Time limit for decision

2. Subject to regulation 3, where the Secretary of State receives a qualifying request for a direction under section 35B(1) of the Planning Act 2008, the Secretary of State must make a decision on the request before the primary deadline.

Provision of information

3. If, before the primary deadline, the Secretary of State asks the requestor to provide information for the purposes of making a decision on the qualifying request—

(a)any information must be provided to the Secretary of State before the secondary deadline, and

(b)the Secretary of State must make a decision on the request before the end of the period of 35 days beginning with the day after—

(i)the secondary deadline, or

(ii)the day on which the Secretary of State receives any information,

whichever is sooner.

Signed by authority of the Secretary of State for Housing, Communities and Local Government

Matthew Pennycook

Minister of State

Ministry of Housing, Communities and Local Government

30th June 2026

(1)

2008 c. 29. Section 35D is inserted into the Planning Act 2008 by section 4 of the Planning and Infrastructure Act 2025 (c. 34) (“the 2025 Act”). Section 4 of the 2025 Act is brought into force on 24th July 2026 (see the Planning and Infrastructure Act 2025 (Commencement No. 4 and Transitional Provisions) Regulations 2026 (S.I. 2026/641)).

(2)

“Gas transporter” and “cross-country pipe-line” have the meaning given in section 235 of the Planning Act 2008.

(3)

Qualifying request” has the meaning given in section 35D(2) of the Planning Act 2008.

Status: This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
The Infrastructure Planning (Timetable for Deciding Request for Direction) Regulations 2026 (2026/728)
Version from: original only

Displaying information

Status of this instrument

in force Provision is in force
in force* In force only for specified purposes (for detail about the purposes see/hover footnote)
not in force Not in force in England (may be in force in other geographies, see footnotes)
italics Defined term
dfn Defined term (alternative style)
gry bckgrd the in-force status of the provision is complex, check the footnotes

Status of changes to instrument text

The list includes made instruments, both those in force and those yet to come into force. Typically, instruments that are not yet in force (hence their changes are not incorporated into the text above) are indicated by description 'not yet' in the changes made column.