Stephen Donald Architects Ltd. v King

[2003] EWHC 1867 (TCC)

Case details

Case citations
[2003] EWHC 1867 (TCC)
Court
High Court (Technology and Construction Court)
Judgment date
30 July 2003
Judgment text

This feature is available to zoomLaw Pro members.

Subjects
Contract Restitution Professional negligence
Keywords
architectural fees quantum meruit unjust enrichment concluded contract repudiatory breach dishonoured cheque professional negligence value engineering
Outcome
claim and counterclaim dismissed
Judicial consideration

This feature is available to zoomLaw Pro members.

Summary

A professional services claim may fail where the parties never reached a concluded agreement on remuneration. Where services are undertaken as part of a joint venture, with payment intended only upon successful completion, the claimant assumes the risk that the venture will fail and may consequently have no restitutionary claim. A quantum meruit is a restitutionary claim: enrichment must be at the claimant’s expense and unjust, after considering any applicable defences and the parties’ intentions. An architect’s response to an unaffordable design may properly include value engineering with the contractor and professional team, followed by seeking alternative tenders. A client may terminate an uncompleted, non-contractual relationship without liability for repudiatory breach.

Factual background

The claimant architect had undertaken design, planning and project-management work for the defendant’s proposed redevelopment of his property. The parties had been friends and had discussed payment by a flat or by fees, but their arrangements remained informal. The claimant later sought agreement to a cash fee of £125,000 plus VAT and interim payments. The defendant did not accept those terms and terminated the claimant’s involvement.

The claimant claimed contractual fees, a quantum meruit, damages for wrongful repudiation and payment of a dishonoured cheque. The defendant counterclaimed for negligence, breach of duty and consequential losses. The principal issues were whether a binding contract existed, whether restitution was available, whether the cheque created liability, and whether the claimant’s design and subsequent conduct fell below the required standard.

Held

The claims and counterclaim were dismissed.

  1. No concluded contract. The parties’ early discussions focused on the possibility of remunerating the claimant with an interest in a flat after successful completion. The later correspondence did not establish agreement to a fee payable by reference to work stages or to interim payments. The defendant’s letter of 16 July 2002 was an offer to pay £125,000 plus VAT on completion, which the claimant did not accept. The contractual fee claim therefore failed. Since there was no contract, the defendant was entitled to end the relationship without liability for repudiatory breach.
  2. Quantum meruit. A quantum meruit is a restitutionary claim. The relevant questions are whether the defendant was enriched, whether the enrichment was at the claimant’s expense, whether it was unjust, and whether any defence applied. Although the defendant may have obtained some benefit from the planning work, the claimant had consciously undertaken the risk that funding might fail or that the defendant might decide not to proceed. Retaining that benefit without further payment was therefore not unjust. The alternative claim failed.
  3. Cheque. The £47,000 cheque was intended as a loan or gesture of friendship and was unsupported by consideration. In any event, it was subject to the collateral condition that it would not be presented until AIB consented. Presentation before that consent was a breach of the collateral contract and prevented recovery on the cheque.
  4. Counterclaim. Although the court proceeded on the basis that the admitted duties of care existed, the design was not one which no reasonably competent architect could have produced for the unusual brief. Once affordability became doubtful, the claimant undertook value engineering with the professional team and sought an alternative contractor. That was a reasonable response. The negligence counterclaim consequently failed.
  5. If negligence had been established, certain AIB-related expenses might have been recoverable, but that issue did not affect the result.

The court’s approach to earlier authorities

This feature is available to zoomLaw Pro members.

Key cases cited

This feature is available to zoomLaw Pro members.

Cases citing this case

This feature is available to zoomLaw Pro members.