Valeo Materiaux De Frictions v VTL Automotive Ltd.

[2005] EWHC 1855 (TCC)

Case details

Case citations
[2005] EWHC 1855 (TCC)
Court
High Court (Technology and Construction Court)
Judgment date
17 August 2005
Judgment text

This feature is available to zoomLaw Pro members.

Subjects
Contract Contractual construction Set-off and total failure of consideration
Keywords
summary judgment commercial contract construction licence agreement supply obligation condition precedent contractual set-off exclusion repudiatory breach total failure of consideration
Outcome
judgment for the claimant; restitutionary counterclaim dismissed
Judicial consideration

This feature is available to zoomLaw Pro members.

Summary

On a summary judgment application under CPR Part 24, the court must determine whether the opposing case has a real, rather than fanciful, prospect of success and whether any other compelling reason requires a trial.

Contractual obligations must be construed in their commercial and factual context. A contractual obligation to supply a defined product may include the characteristics used to identify that product. Payment obligations for licences and associated services are not necessarily conditional upon separate supply obligations. Clear wording requiring payment without deductions may exclude set-off. A complete contractual termination code may supersede common-law rights to accept repudiatory breach. A total failure of consideration is not established where substantial contractual benefits have been provided.

Factual background

Valeo Materiaux De Frictions v VTL Automotive Ltd. concerned two summary judgment applications arising from a Cooperation and Licence Agreement concerning the manufacture, licensing and supply of W2 friction material.

Valeo claimed £200,000, representing the unpaid balance of the final contractual instalment. VTL alleged that the supplied material was not optimised and stabilised in accordance with the W248 formula. It advanced contractual, set-off, repudiation and restitutionary arguments, including a claim for return of £800,000 on the basis of total failure of consideration.

The issues were the scope of Valeo’s supply obligations, whether payment was conditional upon compliant supply, whether VTL could terminate or set off damages, and whether there had been a total failure of consideration.

Held

  1. Summary judgment. The applications were governed by CPR Part 24. Applying Swain v Hillman [2001] 1 All ER 91, VTL had to show more than an arguable case. Its case had to have a realistic prospect of success, and there had to be no other compelling reason for a trial. For present purposes, the court accepted the correctness of VTL’s factual allegations about the shortcomings of the material.
  2. Supply obligation. Construed against the parties’ common factual background, the Cooperation and Licence Agreement required Valeo to manufacture and supply such quantities of W2 material as VTL reasonably ordered. The material had to be W2 in an optimised and stabilised form based on the W248 formula. This requirement arose from the contractual description of the material and clauses 8.1 and 8.2, rather than from a warranty under the licensing provisions.
  3. Instalment payments. The £1 million consideration under clause 3.1.1 was payable for the licence, training, intellectual property and associated services. Valeo’s separate manufacturing and supply obligations under clause 8 were not a condition precedent to VTL’s obligation to pay the instalments. The contractual structure also treated non-conforming material through the royalty provisions, rather than by suspending the lump-sum payments.
  4. Set-off and termination. Clause 12.8 required all sums to be paid in full without deductions. In context, that wording clearly excluded set-off against the licence consideration, including a claim arising from separate supply obligations. Clause 10 was a complete contractual code for termination and superseded the common-law right to accept a repudiatory breach. In any event, VTL had not sufficiently particularised its alleged breaches, loss or causation and appeared to have affirmed any possible repudiation.
  5. Total failure of consideration. VTL had no arguable restitutionary claim. Valeo had provided substantial licences, training and other services, and VTL had made substantial payments after receiving irreversible benefits. The supply obligations and the clause 3 licence obligations were separate.
  6. Valeo was therefore entitled to summary judgment for £200,000 plus appropriate interest, and to judgment dismissing VTL’s £800,000 restitutionary counterclaim.

The court’s approach to earlier authorities

This feature is available to zoomLaw Pro members.

Key cases cited

This feature is available to zoomLaw Pro members.

Cases citing this case

This feature is available to zoomLaw Pro members.