Summary
Construction adjudication is an interim process. An adjudicator’s decision remains binding and enforceable despite errors of fact, law or procedure, provided the adjudicator answered the dispute referred. Enforcement may be refused where the adjudicator exceeded jurisdiction or committed a serious breach of natural justice. Courts should examine technical challenges sceptically, bearing in mind the statutory purpose of speedy payment. An adjudicator need not put provisional conclusions to the parties except in an exceptional case. Where reasons are requested, a brief statement is sufficient if it identifies the issues decided and the conclusions reached. Paragraph 20(c) of the Scheme for Construction Contracts gives the adjudicator a freestanding power to award interest, subject to any contractual term relating to interest.
Factual background
Carillion and Devonport Royal Dockyard were parties to construction and alliance agreements concerning works at Devonport dockyard. An adjudicator awarded Carillion further sums, including amounts for the target cost, defects, a bonus, a fee and interest.
Devonport commenced proceedings challenging the adjudicator’s jurisdiction, the fairness of the target-cost and defects decisions, the adequacy of the reasons, and the power to award interest. Carillion sought enforcement of the adjudicator’s decision. The central issues were whether the adjudicator had answered the dispute referred, whether any procedural defects were sufficiently serious to prevent enforcement, and whether paragraph 20(c) of the Scheme authorised an award of interest.
Held
- Enforcement framework. The statutory adjudication scheme determines who should hold disputed funds provisionally pending final resolution. The decision must generally be enforced even if it contains errors of fact, law or procedure. The critical distinction is between answering the right question wrongly and answering a question which was not referred. The former remains binding; the latter is outside jurisdiction. Serious breaches of natural justice may also prevent enforcement.
- Target cost. The adjudicator was entitled to assess the target cost at £113,953,000. The notice of adjudication and referral required him to determine the primary sum due, which necessarily involved assessing the target cost. Both parties had addressed the issue with extensive evidence. Any error in the assessment was an error within jurisdiction and did not invalidate the decision.
- Natural justice and evidence. The adjudicator was entitled to conclude that negotiations between Devonport and the Ministry of Defence were legally irrelevant, and therefore to disregard them. He was also entitled not to adopt an alternative expert calculation which he rejected. There was no obligation to address every argument expressly where the decision showed which arguments were accepted and how the figures were calculated. It was not necessary to invite further submissions on the adjudicator’s modest reduction of the defects allowance, which was an evaluative assessment of the expert evidence and materially different from the exceptional circumstances in Balfour Beatty Construction Ltd v Lambeth LBC [2002] BLR 288.
- Reasons. The reasons on defects were adequate. They explained why the expanded claim was rejected and why a reduction was made to the original claim. Only absent or unintelligible reasons causing substantial prejudice would justify refusing enforcement.
- Interest. Paragraph 20(c) of the Scheme conferred a freestanding power to award interest. The reference to having regard to any contractual term meant that an express contractual provision had to be respected, not that the power existed only where the contract separately provided for interest.
- All four challenges failed. Judgment was entered for Carillion in both actions, and the adjudicator’s decision was ordered to be enforced.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
Not stated in the judgment. The decision was a first-instance determination of two linked enforcement proceedings in the Technology and Construction Court.
Appeal route
- This judgment [2005] EWHC 778 (TCC) High Court (Technology and Construction Court)
- Appealed to[2005] EWCA Civ 1358Outcomepermission to appeal refused except on interest; appeal on interest dismissed.
Key cases cited
13 authorities cited.
- South Bucks District Council and another (Respondents) v. Porter (FC) (Appellant) [2004] UKHL 33
- Amec Capital Projects Ltd v Whitefriars City Estates Ltd [2004] EWCA Civ 1418
- Pegram Shopfitters Ltd. v Tally Weijl (UK) Ltd. [2003] EWCA Civ 1750
- Ferson Contractors Ltd. v Levolux A.T. Ltd. [2003] EWCA Civ 11
- RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) Ltd [2002] EWCA Civ 270
- Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd [2000] EWCA Civ 507
- Macob Civil Engineering Limited v Morrison Construction Limited [1999] CLC 739
- Glencot Development and Design Co Ltd v Ben Barrett & Son (Contractors) Ltd [2001] 80 Construction Law Reports 14
- Save Britain’s Heritage v Number 1 Poultry Ltd (Save Britain's Heritage v Secretary of State for the Environment) [1991] 1 WLR 153
- K/S A/S BILL BIAKH AND K/S A/S BILL BIALI v. HYUNDAI CORPORATION [1988] 1 Lloyd's Rep 187
- Northern Developments (Cumbria) Ltd v J&J Nichols
- Sherwood v Casson
- Discain Project Services Ltd v Opecprime Development Ltd 80 Construction Law Reports 95
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
8 later cases · 8 positive
Most senior citing decisions:
- Coventry & Warwickshire Development Partnership LLP v Avison Young (UK) Limited [2026] EWHC 2319 (TCC) applied
- Westgreen Construction Limited v Irina Kiryukhina [2026] EWHC 2189 (TCC) applied
- Clegg Food Projects Limited v Prestige Car Direct Properties Limited [2025] EWHC 2173 (TCC) followed
- Andrew Bellis v Sky House Construction Ltd [2023] EWHC 1473 (TCC)
- BEXHEAT LIMITED v ESSEX SERVICES GROUP LIMITED [2022] EWHC 936 (TCC)
- Global Switch Estates 1 Ltd v Sudlows Ltd [2020] EWHC 3314 (TCC)
- Vinci Construction UK Ltd v Beumer Group UK Ltd [2018] EWHC 1874 (TCC)
- Jacques & Anor (t/a C&E Jacques Partnership) v Ensign Contractors Ltd [2009] EWHC 3383 (TCC)
Sign in for the full treatment table. A free account is enough.