Summary
An arbitration agreement governed by English law is construed separately from the underlying contract. A wide clause referring disputes arising out of or relating to the contract to arbitration is not displaced merely because the contract is governed by foreign law or because foreign legislation assigns functions to a statutory body. Any contractual or statutory approval relevant to the merits may be considered by the arbitrators without affecting their jurisdiction, unless the contract clearly creates an exclusive alternative jurisdiction. Changes in the substantive law governing the underlying contract may affect the parties’ rights, but do not alter the scope of a separately governed arbitration agreement. An estoppel by convention requires a shared assumption, reliance and sufficient unfairness in allowing departure from it.
Factual background
ST-CMS commenced ICC arbitration concerning the actual capital cost of a power plant and the resulting tariff payable under a long-term power purchase agreement with TNEB. TNEB applied under section 72 of the Arbitration Act 1996 for declarations that the claims were outside the arbitration agreement and for injunctions restraining the arbitration.
TNEB argued that Indian electricity legislation required the actual capital cost and tariff to be determined exclusively by the Central Electricity Authority or the Tamil Nadu Electricity Regulatory Commission. It relied alternatively on private international law, public policy and estoppel by convention. The central issue was whether those matters affected the arbitrators’ jurisdiction.
Held
- Construction of the arbitration agreement. The arbitration agreement was a separate agreement under section 7 of the Arbitration Act 1996, governed by English law. Article 15.2(a) was deliberately broad, covering disputes arising out of or relating to the PPA, subject only to matters expressly provided for elsewhere as being finally and exclusively determined by another person.
- The PPA’s provisions concerning tariff compliance, capital cost and CEA approval dealt with substantive matters. They did not expressly or impliedly create an exception to the arbitrators’ jurisdiction. CEA approval, if required, was a matter for the arbitrators to take into account when determining the parties’ rights and appropriate relief.
- Private international law and public policy. Indian law, as the proper law of the PPA, governed substantive disputes under it. It did not govern the scope of the separate English-law arbitration agreement. Article 3.3 of the Rome Convention did not apply to arbitration agreements, and no fundamental English public policy principle required the arbitration clause to be disapplied. The Ralli Bros principle was inapplicable because performance of the arbitration agreement was to occur in London and no contractual obligation required performance in India.
- Indian electricity legislation. Under the 1948 regime, CEA’s approval was required only for excess costs over the relevant approved or contractual ceiling. There was no general requirement for CEA to determine the whole actual capital cost. Under the 2003 Act and the 2005 Tamil Nadu Regulations, an existing PPA continued to govern tariff and operating norms. The TNERC therefore had no exclusive jurisdiction to redetermine the tariff under this PPA.
- The reasoning in Small Hydro Powers Developers Association v APERC was compelling and supported the distinction between regulation of electricity purchase under section 86(1)(b) and general tariff determination under section 86(1)(a). The contrary approach in GVK Industries v CEA was rejected insofar as it misconstrued CEA’s former statutory role.
- Estoppel. The correspondence did not establish a shared assumption that CEA had exclusive jurisdiction to determine actual capital cost. TNEB’s work was required under the PPA in any event, and no sufficient detriment or unconscionability was shown. The estoppel case therefore failed.
- TNEB’s applications for declarations and injunctions were dismissed. ST-CMS was entitled to the declarations sought. Costs were to follow the event, subject to consequential submissions.
The court’s approach to earlier authorities
Available to signed-in members.
Key cases cited
21 authorities cited.
- Associated Electric and Gas Insurance Services Ltd v European Reinsurance Co of Zurich [2003] UKPC 11
- Fiona Trust & Holding Corporation & Ors v Yuri Privalov & Ors [2007] EWCA Civ 20
- C v D [2007] EWHC 1541 (Civ)
- Centrica plc v British Gas Trading Ltd [2006] EWHC 3068 (Civ)
- GVK Industries v CEA [2006] 111 AD Delhi 523
- OT Africa Lyon Ltd v Magic Sportswear [2005] 2 LLR 170
- BSES v Tata Power Co Limited 2004 1 SCC 195
- West Bengal Electricity Regulatory Commission v CESC Limited (2002) 8 SCC 715
- Svenska Handelsbanken v M/sIndian Charge Chrome Limited (1994) 2 SCC 155
- Renusagar Power Company Ltd v General Electric Co AIR 1994 SC 860
- Lemenda Trading Co Ltd v African Middle East Petroleum Co Ltd [1988] QB 448
- Akai v Peoples Insurance Co [1988] 1 LLR 90
- The Vistafjord [1988] 2 LLR 343
- Amalgamated Investment & Property Co Ltd v Texas Commerce International Bank Ltd [1982] QB 84
- Murlidhar Aggarval v State of Uttar Pradesh (1974) 2 SCC 472
- Regazzoni v K C Sethia (1944) Ltd [1956] 2 QB 490
- Kahler v Midland Bank Ltd [1950] AC 24
- R v International Trustee for the Protection of Bondholders Aktiengesellschaft [1937] AC 500
- Ralli Bros v Cia Naviera Sota y Aznar [1920] 2 KB 287
- Dabhol Power Company v Maharashtra State Electricity Board
- Small Hydro Powers Developers Association v APERC
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
8 later cases · 5 positive · 3 caution
Most senior citing decisions:
- FS Cairo (Nile Plaza) LLC v Lady Brownlie [2021] UKSC 45 explained
- FS Cairo (Nile Plaza) LLC v Brownlie [2020] EWCA Civ 996 explained
- AIG Financial Products Corp & Ors v Gruber & Ors [2020] EWCA Civ 31 applied
- Renaissance Securities (Cyprus) Limited v Chlodwig Enterprises Limited & Ors [2023] EWHC 2816 (Comm)
- Kazakhstan Kagazy Plc & Ors v Baglan Abdullayevich Zhunus & Ors [2018] EWHC 369 (Comm)
- Beijing Jianlong Heavy Industry Group v Golden Ocean Group Ltd & Ors [2013] EWHC 1063 (Comm)
- Abuja International Hotels Ltd. v Meridien Sas [2012] EWHC 87 (Comm)
- AES Ust-Kamenogorsk Hydropower Plant LLP v Ust-Kamenogorsk Hydropower Plant JSC [2010] EWHC 772 (Comm)
Sign in for the full treatment table. A free account is enough.