Case details
Summary
Summary judgment should be refused where the defendant shows a real, rather than fanciful, prospect of defending the claim on assumed facts. A court should not finally resolve difficult issues of contractual construction where the relevant factual background remains to be tested, particularly where rectification is advanced in the alternative.
In construing a commercial agreement, the court may consider its objective purpose and the commercial consequences of competing interpretations. Language may, where justified, be read so as to avoid commercial absurdity. Whether a partial substitution of parties terminates a wider contract is context-dependent and cannot be answered by a single universal rule.
Factual background
Langston held fixed-rate unsecured loan notes issued by Cardiff City Football Club Ltd. It sought summary judgment under CPR Part 24 for more than £30 million, contending that a 2006 Agreement varying the loan terms had never become unconditional.
The Club relied on the 2006 Agreement, whose operative provisions were conditional on the satisfaction or waiver of conditions in a development agreement by 31 May 2007. It also relied alternatively on rectification of the variation deed. The issues concerned whether a subsequent variation of the development agreement terminated it, whether its conditions had been satisfied or waived, and whether the variation deed should be rectified.
Held
- Application dismissed. The Club had a real prospect of successfully defending the claim. The court therefore declined to determine the disputed issues finally on assumed facts.
- The substitution of Devco for the Club as obligor in respect of many, but not all, obligations under the development agreement did not necessarily terminate the whole agreement. Whether partial substitution operates as termination or variation is purpose-dependent. The parties’ manifested intention and the purpose for which the question arises are material. The drafting expressly described the document as a variation and preserved the agreement’s continuing effect. The court considered this approach consistently with Saunders v Ralph [1993] 2 EGLR 1 and Morris v Baron & Co [1918] AC 1.
- The 2006 Agreement was to be construed by reference to its commercial purpose. Its objective was to reduce and postpone the loan in order to enable the stadium project to proceed. Treating the development agreement’s variation as a termination, or treating waiver as sufficient for the write-down but insufficient for postponement, could produce commercial absurdity. The court applied the principles expressed in Prenn v Simmonds [1971] 1 WLR 1381 and The Antaios [1985] AC 191.
- Although the evidence did not establish written consent under the development agreement’s waiver procedure, the assumed facts gave the Club a real prospect of proving an effective waiver by conduct and agreement. The court adopted the conclusion in World Online Telecom Ltd v I-Way Ltd [2002] EWCA Civ 413 that the legal issue was sufficiently unsettled to be unsuitable for summary determination.
- There was also a sufficient evidential basis for the alternative rectification claim. The evidence could support a common intention that the agreement should become unconditional when the development agreement became unconditional, and that the omission of “waived” from the variation deed resulted from drafting rather than an intended exclusion.
The court’s approach to earlier authorities
This feature is available to zoomLaw Pro members.
Key cases cited
This feature is available to zoomLaw Pro members.
Cases citing this case
This feature is available to zoomLaw Pro members.