Derbyshire Dales District Council & Anor v Secretary of State for Communities and Local Government & Anor

[2009] EWHC 1729 (Admin)

Summary

Possible alternative sites are generally a potentially relevant planning consideration. They do not, however, create a legal duty to investigate alternatives merely because a proposed development conflicts with the development plan. Short of irrationality, such a duty arises only where statute or policy expressly or impliedly requires it, including because the matter is obviously material. In the absence of identified alternatives or a policy requirement, the question remains one of planning judgment.

Regional renewable-energy targets must not directly determine an individual planning application. They may nevertheless be material, because targets can be achieved only through the accumulated effect of individual permissions. An inspector may rationally give significant weight to a proposal’s contribution to those targets.

Treatment over time

Cited in 34 later judgments between 2012 and 2026, including 1 in the Supreme Court. Applied, followed or approved 27 times, most recently by the High Court in July 2026.

Most often cited for

  1. Alternative sites are mandatory considerations only where law compels their consideration18 judgments
  2. Potential relevance alone does not make a planning consideration legally mandatory15 judgments

Factual background

Carsington Wind Energy Ltd sought planning permission for four wind turbines and associated works. Derbyshire Dales District Council refused permission. On appeal, an inspector acting for the Secretary of State allowed the appeal and granted permission subject to conditions.

The Council, supported by the Peak District National Park Authority, challenged the decision under section 288 of the 1990 Act. The challenge did not dispute the inspector’s detailed assessment of landscape, National Park and conservation-area effects. It concerned whether he was legally required to investigate alternative sites, and whether regional and national renewable-energy targets could be weighed in deciding the individual application.

Held

  1. The application was dismissed. The inspector made no error of law in granting planning permission. The limited conflict with development-plan policies was a matter for his planning balance.

  2. The court applied the distinction drawn in Trust House Forte Ltd v Secretary of State (1986) 53 P&CR 293. A decision-maker may take account of alternative sites, but a court may only find legal error in failing to do so where a statute or policy imposes that obligation, expressly or by necessary implication. The mere possibility that another site might cause less harm is insufficient.

  3. The exceptional circumstances in Secretary of State v Edwards (1994) 60 P&CR 607 CA were absent. There, competing identified sites were before the Secretary of State for a development for which only a limited number of permissions could be granted. Here, no alternative site had been identified. The statutory provisions and policies protecting the National Park and conservation areas required special regard to their protection, but did not impose a positive duty to investigate alternatives.

  4. R(Bovale Ltd) v Secretary of State [2008] EWHC 2538 (Admin) did not establish the suggested general rule. It concerned whether an inspector could lawfully consider identified alternatives, rather than whether an inspector acted unlawfully by not considering unidentified alternatives. The court also held that the relevant renewable-energy policy did not compel an alternatives review.

  5. The inspector was entitled to reconcile the policies on renewable-energy targets. Strategic targets could not directly dictate the grant or refusal of an individual application. They remained material to the planning balance, since individual permissions collectively determine whether the targets are achieved. His conclusion that the proposal’s contribution merited significant weight was rational.

  6. The authorities were to pay the Secretary of State’s costs. There was no order as to Carsington’s costs.

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

  • High Court (Administrative Court): The court dismissed the authorities’ statutory challenge to the inspector’s decision.
  • Inspector acting for the Secretary of State: Following the Council’s refusal of planning permission, the inspector allowed Carsington’s planning appeal on 27 September 2008 and granted permission subject to conditions.

Often cited alongside this case

Of these 8 cases: 5 cited with it on 2 different points; 3 cited alongside it for other points.

Cited together forAlternative sites are mandatory considerations only where law compels their consideration

  1. Langley Park School for Girls v London Borough of Bromley & Anor[2009] EWCA Civ 734 · Court of Appeal (Civil Division)Cited together in 5 later judgments
  2. Mount Cook Land Ltd & Anor v Westminster City Council[2003] EWCA Civ 1346 · Court of Appeal (Civil Division)Cited together in 8 later judgments

+1 more for signed-in readers

Cited together forPotential relevance alone does not make a planning consideration legally mandatory

  1. R (on the application of Samuel Smith Old Brewery (Tadcaster) and others) v North Yorkshire County Council[2020] UKSC 3 · United Kingdom Supreme CourtCited together in 13 later judgments

+1 more for signed-in readers

Cited alongside it for other points

3 related cases for signed-in readers

Key cases cited

8 authorities cited.

Sign in to see how the court treated each authority. A free account is enough.