Summary
A contractual close-out mechanism is not penal merely because it determines the amount payable by applying a valuation method rather than a fixed sum, or because the amount varies with market conditions. The question is whether the provision requires payment of an extravagant or unconscionable sum in comparison with the loss resulting from the breach.
Where commercial parties agree that persistent non-payment permits termination of all related transactions and payment representing the value of the unperformed bargain, the payment may properly compensate loss of bargain rather than impose a penalty. A clause may make timely payment a condition by specifying termination and compensatory consequences, even without using the words condition or repudiatory breach. The court should give effect to carefully drafted commercial arrangements, particularly in complex financial transactions.
Factual background
BNP Paribas claimed an Early Termination Amount under an ISDA Master Agreement after Wockhardt failed to make payments due under several foreign exchange transactions. The sum comprised unpaid amounts already due and a Close-out Amount calculated by reference to the value of the outstanding transactions.
Wockhardt argued that the Close-out provisions were unenforceable penalties because the same termination mechanism applied to defaults of differing seriousness and because the amount payable depended on market movements. BNP applied for summary judgment or strike-out. The central issues were whether the Close-out Amount was commercially reasonable and whether the contractual termination provisions engaged the doctrine of penalties.
Held
- Commercial reasonableness. The evidence established that BNP had calculated the Close-out Amount using its standard internal pricing model, applied in the ordinary course of its business to similar transactions. In the absence of any substantive challenge, BNP had shown that it had acted by commercially reasonable procedures to produce a commercially reasonable result.
- Unpaid amounts. Requiring the defaulting party to pay sums which had already fallen due under individual transactions was not penal. Those sums were accrued contractual debts and did not represent a sanction for default.
- Close-out Amount. The contractual method did not prescribe an extravagant or unconscionable measure. It calculated the cost of replacing the terminated transactions, or their economic equivalent, and therefore sought to place BNP in the position it would have occupied had the uncompleted transactions proceeded.
- Condition and termination. Although the agreement did not use the expressions “condition” or “repudiatory breach”, it provided that failure to pay continuing after notice entitled BNP to designate an Early Termination Date. It then substituted an obligation to pay the value of the terminated transactions for the parties’ future payment and delivery obligations. The parties had therefore agreed consequences equivalent to those following breach of condition.
- The fluctuating value of the Close-out Amount was not extraneous to the breach. Market movements were necessarily relevant to valuing the unperformed bargain. The fact that the calculation could produce a payment in either direction, with credit for any net value favouring the defaulting party, also negated any suggestion of a windfall.
- The provisions were not rendered penal merely because one termination mechanism applied to defaults of differing seriousness, or because the amount was determined by the non-defaulting party, subject to good faith and commercially reasonable procedures. There was no realistic prospect of establishing that the Early Termination provisions were penalties.
- Paragraphs 19 and 20 of the existing Defence, concerning penalties, were to be struck out. The issue of summary judgment or interim payment was deferred pending determination of Wockhardt’s proposed amendment.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
First instance decision. No earlier appellate decision is stated in the judgment.
Key cases cited
19 authorities cited.
- Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd [1915] AC 79
- Perpetual Trustee Company Ltd & Anor v BNY Corporate Trustee Services Ltd & Ors [2009] EWCA Civ 1160
- AWB (Geneva) SA & Anor v North America Steamships Ltd & Anor [2007] EWCA Civ 739
- Murray v Leisureplay Plc [2005] EWCA Civ 963
- Cine Bes Filmcilik Ve Yapimcilik & Anor v United International Pictures & Ors [2003] EWCA Civ 1669
- Lombard North Central Plc v Butterworth [1987] QB 527
- Hongkong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd (The Hongkong Fir) [1962] 2 QB 26
- Perpetual Trustee Co Ltd v BNY Corporate Trustee Services Ltd & Anor [2009] EWHC 1912 (Ch)
- Dalkia Utilities Services Plc v Celtech International Ltd [2006] EWHC 63 (Comm)
- Protector Endowment Loan Co v Grice (1880) 5 QBD 592
- Rice v Great Yarmouth BC [2001] 3 LGLR 4
- Antaios Cia Naviera SA v Salen Rederierna AB (The Antaios) (Salen Rederierna AB v Antaios Cia Naviera SA) [1985] AC 191
- Elsey v J.G. Collins Insurance Agencies Ltd [1978] 83 DLR 1
- Cehave NV v Bremer Handelgesellschaft mbH (Hansa Nord, The) [1976] QB 44
- Robophone Facilities Ltd v Blank [1966] 1 WLR 1428
- Comr of Public Works v Hills [1906] AC 368
- Parkin v Thorold [1852] 16 Beav 59
- The Angelic Star
- Drexel Burnham Lambert Products Corporation v Midland Bank PLC 92 Civ 3098 (MP)
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
3 later cases · 2 positive · 1 neutral
Most senior citing decisions:
- Videocon Global Ltd & Anor v Goldman Sachs International [2016] EWCA Civ 130 applied
- ALEXEY SAMARENKO v DAWN HILL HOUSE LIMITED [2011] EWCA Civ 1445 considered
- Goldman Sachs International v Videocon Global Ltd & Anor [2014] EWHC 4267 (Comm) applied
Sign in for the full treatment table. A free account is enough.