Summary
Under the Housing Grants, Construction and Regeneration Act 1996, exclusions from construction operations are construed narrowly and applied to the specified operations. In section 105(2)(c)(ii), “erection” of steelwork ordinarily covers lifting and connecting steelwork on site. It does not include fabrication drawings, off-site fabrication or delivery to site.
Where an agreement contains both construction operations and excluded operations, adjudication applies only to the former. An adjudicator may decide the referable part of a dispute, but a single decision covering both referable and non-referable parts is invalid and unenforceable. The court cannot reconstruct or sever that decision in enforcement proceedings.
Factual background
Cleveland Bridge sought summary judgment to enforce an adjudicator’s decision requiring the Joint Venture to pay £317,500 plus VAT under an agreed final account for works at an LNG terminal.
The subcontract covered fabrication, delivery and erection of structural steelwork, construction and cladding of buildings, and painting. The Joint Venture argued that the subcontract was not, or was only partly, a construction contract because steelwork supporting or providing access to plant or machinery was excluded by section 105(2)(c)(ii) of the Housing Grants, Construction and Regeneration Act 1996.
The issues were the scope of the exclusion, the adjudicator’s jurisdiction over a mixed contract and dispute, and whether the adjudicator’s single decision could be severed for enforcement.
Held
- Classification of the works. The subcontract comprised both construction operations under section 105(1) and excluded operations under section 105(2)(c)(ii). The steelwork for the piperacks and pipebridges was significant and substantial steelwork supporting or providing access to plant or machinery at a site whose primary activity was the production, transmission, processing or bulk storage of gas.
- Meaning of “erection”. The exclusions in section 105(2) required a narrow construction. “Erection” of steelwork meant essentially lifting the steelwork into position and connecting it together. It did not include fabrication drawings, connection design, off-site fabrication, painting or delivery to site. Those activities remained construction operations under section 105(1).
- Mixed agreements and jurisdiction. Section 104(5) contemplated agreements relating to construction operations and other matters. The Act’s adjudication provisions applied only so far as the agreement related to construction operations. The adjudicator therefore had jurisdiction over the referable part of the dispute, although the whole dispute could not be referred to adjudication.
- Severability. The referral concerned one dispute about payment of the final account, not separate disputes. The adjudicator decided the whole dispute and did not issue an alternative decision limited to the construction operations. Her decision therefore included matters outside her jurisdiction and was not valid or enforceable.
- The implied term in paragraph 23(2) of Part I of the Scheme required compliance with a valid adjudicator’s decision. It did not make individual findings leading to a single decision separately binding. The court could not divide the sum, revise the decision or create a partly court-made decision. Cleveland Bridge’s Part 24 application was dismissed.
The court’s approach to earlier authorities
Available to signed-in members.
Key cases cited
10 authorities cited.
- Attorney General of Belize v Belize Telecom Ltd [2009] UKPC 10
- Investors Compensation Scheme Ltd v West Bromwich Building Society (Investors Compensation Scheme Ltd v Hopkins & Sons) [1997] UKHL 28
- Pepper v Hart [1993] AC 593
- North Midland Construction Plc v A E & E Lentjes UK Ltd [2009] EWHC 1371 (TCC)
- Cantillon Ltd v Urvasco Ltd [2008] EWHC 282 (TCC)
- Rsl (South West) Ltd. v Stansell Ltd. [2003] EWHC 1390 (TCC)
- KNS Industrial Services (Birmingham) Ltd v Sindall Ltd (2001) 75 Con LR 71
- Fence Gate Ltd v James R Knowles Ltd (2002) 84 Con LR 206
- Griffin v Midas Homes Ltd (2001) 78 Con LR 152
- Farebrother Building Services Ltd v Frogmore Investments Ltd [2001] CILL 1589
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
6 later cases · 5 positive · 1 caution
Most senior citing decisions:
- C Spencer Ltd v M W High Tech Projects UK Limited [2020] EWCA Civ 331 applied
- C Spencer Ltd v MW High Tech Projects UK Ltd [2021] EWHC 1284 (TCC) followed
- Engie Fabricom (UK) Ltd v MW High Tech Projects UK Ltd [2020] EWHC 1626 (TCC) followed
- C Spencer Ltd v MW High Tech Projects UK Ltd [2019] EWHC 2547 (TCC)
- Equitix ESI CHP (Wrexham) Ltd v Bester Generacion UK Ltd [2018] EWHC 177 (TCC)
- Severfield (UK) Ltd v Duro Felguera UK Ltd [2015] EWHC 3352 (TCC)
Sign in for the full treatment table. A free account is enough.