Alstom Transport v Eurostar International Ltd & Anor

[2010] EWHC 2747 (Ch)

Summary

On an application for an interim injunction in a regulated procurement, the court applies the American Cyanamid principles, while taking account of the statutory and public interest in transparent, equal and non-discriminatory competition.

A procurement may proceed on hypothetical assumptions about future regulatory change if bidders are treated equally and the specification is sufficiently clear to permit fair bids and evaluation. Criteria, weightings and material evaluation methodologies must generally be disclosed in advance where they could affect tender preparation or assessment. Serious arguable breaches do not by themselves justify an injunction. The court must assess the adequacy of damages, the balance of uncompensatable disadvantage, the public interest and the claimant’s realistic prospect of obtaining substantive relief.

Treatment over time

Cited in 14 later judgments between 2010 and 2022. Applied, followed or approved 8 times, most recently by the High Court in June 2022.

Most often cited for

  1. Public interest and effects on others inform the balance of convenience in procurement injunctions8 judgments
  2. Reputational and future-market losses from a prestigious contract may make damages inadequate7 judgments

Factual background

ALSTOM, a bidder for Eurostar’s proposed purchase of new high-speed trains, sought an interim injunction preventing Eurostar from contracting with Siemens. It alleged breaches of the Utilities Contracts Regulations 2006, including uncertainty caused by pending safety-rule changes concerning distributed power systems and the late disclosure of criteria, weightings and evaluation methodology.

ALSTOM also relied on Eurostar’s preliminary agreement with Siemens. The application arose after Eurostar notified ALSTOM that Siemens had won the procurement and during the statutory standstill period. The central questions were whether there was a serious issue to be tried, whether damages were adequate, and where the balance of convenience or injustice lay.

Held

  1. Application dismissed. ALSTOM established serious issues to be tried concerning some alleged breaches of the Utilities Contracts Regulations 2006, but the balance of convenience did not favour interim relief.
  2. The court applied the three-stage approach in American Cyanamid v Ethicon [1975] A.C. 396: serious question to be tried, adequacy of damages, and, if necessary, the balance of convenience. The court must avoid conducting a mini-trial. The public interest may, and should, be considered in procurement cases.
  3. It was arguable that the unresolved safety rules made the specification insufficiently precise under regulation 12(7), or rendered the process insufficiently transparent or equal under regulation 4(3) and regulation 30. A utility may procure on hypothetical assumptions about future regulatory change, provided bidders are placed in an equal position and the specification permits fair evaluation.
  4. It was also seriously arguable that Eurostar should have disclosed its NPV-based financial evaluation, its five-point banding system, and the allocation of a material scoring advantage to the lowest bidder. The five-point system appeared inconsistent with the disclosed 100-point system. The complaint that confidence-based scoring was undisclosed was weaker, and the technical evaluation complaint could not be resolved without the evaluation documents.
  5. The preliminary agreement was not obviously outside the Regulations, but no relief was sought in respect of it and no finding on that issue was necessary.
  6. Damages would not adequately compensate ALSTOM for the loss of a prestigious contract and associated reputational and market benefits. Nor would damages adequately compensate Eurostar for the likely delay and disruption to its entire business programme. The balance nevertheless favoured Eurostar. ALSTOM had only a small prospect of showing that the alleged breaches would have changed the result, particularly given the substantial scoring gap and evidence that Siemens had treated the procurement as a higher priority.
  7. The public interest also favoured refusal of the injunction because delay would harm Eurostar’s competitive position and postpone improved competition for Tunnel rail services. The tendering process should not be frozen. ALSTOM’s application was dismissed.

The court’s approach to earlier authorities

Available to signed-in members.

Other judgments in these proceedings

2 judgments in these proceedings, earliest first. Linked by the shared court number HC10C03303, and by appeals.

  1. 29 October 2010Alstom Transport v Eurostar International Ltd & Anor[2010] EWHC 2747 (Ch) · High Court (Chancery Division) · this judgment
  2. 20 January 2012Alstom Transport v Eurostar International Ltd[2012] EWHC 28 (Ch) · High Court (Chancery Division)

Related cases

Not part of these proceedings, but heard together with this judgment or between the same parties.

  1. 13 July 2011Alstom Transport v Eurostar International Ltd & Anor (Rev 1)[2011] EWHC 1828 (Ch) · High Court (Chancery Division) · Same parties

Often cited alongside this case

Of these 8 cases: 5 cited with it on 2 different points; 1 cited alongside it for another point; 2 related in other ways.

Cited together forPublic interest and effects on others inform the balance of convenience in procurement injunctions

  1. Covanta Energy Ltd v Merseyside Waste Disposal Authority[2013] EWHC 2922 (TCC) · High Court (Technology and Construction Court)Also cited together for: Reputational and future-market losses from a prestigious contract may make damages inadequateCited together in 7 later judgments

Cited together forReputational and future-market losses from a prestigious contract may make damages inadequate

  1. NATS (Services) Ltd v Gatwick Airport Ltd & Anor[2014] EWHC 3133 (TCC) · High Court (Technology and Construction Court)Cited together in 6 later judgments

+3 more for signed-in readers

Cited alongside it for other points

  1. Exel Europe Ltd. v University Hospitals Coventry & Anor[2010] EWHC 3332 (TCC) · High Court (Technology and Construction Court)Lifting an automatic procurement suspension requires the ordinary American Cyanamid interim-relief assessmentCited together in 8 later judgments

Other related cases

2 related cases for signed-in readers

Key cases cited

18 authorities cited.

  • American Cyanamid Co v Ethicon Ltd [1975] AC 396
  • The Law Society, R (on the application of) v Legal Services Commission [2007] EWCA Civ 1264
  • Varney and Sons Waste Management Ltd v Hertfordshire County Council [2010] EWHC 1404
  • Lettings International v Newham [2008] EWHC 1583
  • Electronic Data Systems Ltd v Transport Trading Ltd [2008] EWHC 2105
  • Lion Apparel Systems Ltd v Firebuy Ltd [2007] EWHC 2179 (Ch)
  • Partenaire Limited v Department of Finance and Personnel [2007] NIQB 100
  • Uniplex (UK) Ltd v NHS Business Services Authority (Uniplex (UK) Ltd v NHS Business Services Authority.) Case C-406/08
  • Chandler v Camden LBC [2009] 1 CMLR 19
  • National Commercial Bank Jamaica Limited v Olint Corporation Limited 28th April 2009
  • Pressetext Nachrichtenagentur GmbH v Republik Österreich Case C-454/06 Pressetext [2008] ECR I-4401
  • Emm. G. Lianakis v Dimos Alexandroupolis Case C-532/06 Emm. G. Lianakis v Dimos Alexandroupolis [2008] ECR I-0251
  • ATI EAC ATI EAC [2005] ECR I-10109
  • Commission v French Republic Case C-340/02 Commission v French Republic [2004] I-9845
  • Universale-Bau AG v Entsorgungsbetriebe Simmering GmbH Universale-Bau 2002 ECR I-11617
  • Smith v Inner London Education Authority [1978] 1 All ER 411
  • Fellowes & Son v Fisher [1976] QB 122
  • Shepherd Homes Ltd v Sandham [1971] Ch 340

Sign in to see how the court treated each authority. A free account is enough.

Cases citing this case

14 later cases · 8 positive · 3 neutral · 3 caution

Most senior citing decisions:

Sign in for the full treatment table, including the other 4 cases. A free account is enough.