Cadogan Petroleum Holdings Ltd v Global Process Systems LLC

[2013] EWHC 214 (Comm)

Case details

Case citations
[2013] EWHC 214 (Comm) · [2013] CN 252 · [2013] 2 Ll Rep 26
Court
High Court (Commercial Court)
Judgment date
15 February 2013
Judgment text

This feature is available to zoomLaw Pro members.

Subjects
Contract Equity and trusts Penalties and relief against forfeiture
Keywords
termination for breach accrued contractual rights instalment payments failure of consideration penalty clauses relief against forfeiture unjust enrichment commercial contracts gas plants damages adjourned
Outcome
issues determined (contractual payments retained and accrued instalments recoverable; relief against forfeiture granted on secured terms; damages claim adjourned)
Judicial consideration

This feature is available to zoomLaw Pro members.

Summary

Contractual provisions governing accrued payment rights on termination should be construed according to their language and commercial context. Where a contract preserves accrued rights, termination does not ordinarily extinguish sums already paid or due. A restitutionary claim based on failure of consideration cannot displace express contractual arrangements governing the parties’ benefits. The penalty doctrine applies to provisions taking effect on breach; it does not apply to payment obligations which arise independently of breach. Relief against forfeiture is distinct from the penalty doctrine and depends on equitable considerations existing when relief is sought. In a commercial contract, the court may preserve the contractual scheme while securing sums which may ultimately exceed the innocent party’s loss.

Factual background

Cadogan and Global Process Systems LLC entered into a settlement agreement under which GPS agreed to purchase two gas plants from Cadogan. GPS paid approximately US$7.5 million, but failed to pay later instalments. Cadogan terminated the sale agreement under clause 22, which preserved accrued rights. The plants remained unsold.

The court determined whether Cadogan could retain the sums paid, recover approximately US$20 million in accrued instalments as a debt, and whether GPS was entitled to restitution, relief against forfeiture or relief under the law of penalties. The claim for damages was adjourned.

Held

  1. Construction. Clause 22.2 preserved rights accrued before termination. Those rights included Cadogan’s right to recover unpaid instalments and, by agreement, to retain instalments already paid. Clause 22’s express cessation of clause 13, together with the continuing operation of clause 21, supported that construction. The commercial structure also contemplated that the plants might remain unsold.

  2. Failure of consideration. The contractual allocation of benefits governed the parties’ rights. Since the agreement expressly provided that accrued rights were unaffected by termination, there was no room for a restitutionary claim based on total failure of consideration. Cadogan was therefore prima facie entitled to retain approximately US$7.5 million and recover approximately US$20 million as a debt.

  3. Penalties. The instalments were payable by reference to specified events and not because of breach. They were independent of any breach and therefore could not constitute penalties. The penalty doctrine and relief against forfeiture are distinct: the former is assessed by construction at the date of contract, whereas the latter involves equitable jurisdiction exercised in light of circumstances existing when relief is sought. The court did not need to decide whether the instalments would otherwise have had a compensatory or deterrent character.

  4. Relief against forfeiture. Proceeding on the accepted basis that relief was available, justice did not require repayment of the sums paid or refusal of the debt claim. The plants had not been sold and their value was uncertain. The contractual scheme was maintained, but further net sale proceeds up to US$10 million, plus applicable interest, were to be paid to Cadogan, with any balance secured or paid into court pending further order or agreement. The damages claim was adjourned and both parties were given liberty to apply.

The court’s approach to earlier authorities

This feature is available to zoomLaw Pro members.

Key cases cited

This feature is available to zoomLaw Pro members.

Cases citing this case

This feature is available to zoomLaw Pro members.