Summary
In a medical negligence claim, the Bolam standard remains subject to the court’s assessment of whether the supporting professional opinion has a logical basis. Causation may be established by proving that negligent conduct made a material contribution to injury, including where several negligent and non-negligent factors operate successively or cumulatively. The material-contribution approach is not confined to single-agency cases. Where medical evidence makes it impossible, rather than merely difficult, to attribute particular loss to particular causes, damages should not be apportioned between those causes. The claimant may recover for the entirety of the injury once material contribution is established.
Factual background
The claimant, a general practitioner, suffered a serious head injury after falling down stairs. He alleged that the defendant hospital negligently delayed a CT brain scan and later delayed arranging an ambulance transfer to a neurosurgical hospital. He sustained permanent cognitive and neuropsychological impairment. The defendant disputed breach, causation and the extent of recoverable damages, relying on the initial trauma and a later post-operative infection as non-tortious causes.
The central issues were whether the hospital was negligent, whether the claimant suffered damaging raised intracranial pressure during the relevant delays, whether that pressure materially contributed to his injury, and whether damages should be apportioned.
Held
- Breach of duty. The applicable standard was that in Bolam, qualified by the requirement in Bolitho that professional opinion must withstand logical analysis. The defendant was negligent in failing to ensure that the CT brain scan was performed by about 10.00 am. It was also negligent in failing to request a second ambulance soon after the claimant had been stabilised and was ready for transfer.
- Raised intracranial pressure. On the balance of probabilities, the claimant was suffering damaging raised intracranial pressure from at least about 12.15 pm, and in any event from the time of his seizure. The operative findings and evidence of the neurosurgeon who saw the claimant’s brain were preferred to the limited indications on the earlier CT scan.
- Factual causation. Without the CT delay, the claimant would probably have been transferred and operated upon before his seizure, avoiding several hours of damaging pressure. The ambulance delay would separately have postponed surgery by about one hour.
- Legal causation. The material-contribution approach applied even though the initial trauma and later infection were additional causes. The authorities did not confine that approach to single-agency cases. The negligent pressure made an unquantifiable but more than negligible contribution to the claimant’s cognitive and neuropsychological impairment.
- Apportionment. Apportionment was inappropriate because the evidence made it impossible, rather than merely difficult, to attribute particular loss to particular causes. The claimant was therefore entitled to recover without deduction.
- Disposition. Judgment was entered for the claimant in the total sum of £454,858.65, inclusive of interest.
The court’s approach to earlier authorities
Available to signed-in members.
Key cases cited
15 authorities cited.
- Williams v The Bermuda Hospitals Board [2016] UKPC 4
- Fairchild v Glenhaven Funeral Services Ltd (Babcock International Ltd v National Grid Co plc, Dyson v Leeds City Council, Fox v Spousal (Midlands) Ltd, Matthews v Associated Portland Cement Manufacturers (1978) Ltd, Pendleton v Stone & Webster Engineering Ltd) [2002] UKHL 22
- Bolitho v City and Hackney Health Authority [1998] AC 232
- Wilsher v Essex Area Health Authority [1988] AC 1074
- Hotson v East Berkshire Health Authority [1987] AC 750
- Sidaway v Board of Governors of the Bethlem Royal Hospital and the Maudsley Hospital [1985] AC 871
- McGhee v National Coal Board [1973] 1 WLR 1
- Bonnington Castings Ltd v Wardlaw [1956] AC 613
- Heneghan v Manchester Dry Docks Ltd & Ors [2016] EWCA Civ 86
- Billett v Ministry of Defence (MOD) [2015] EWCA Civ 773
- Bailey v The Ministry of Defence & Anor [2008] EWCA Civ 883
- Holtby v Brigham & Cowan (Hull) Ltd [2000] ICR 1086
- Thompson v Smiths Shiprepairers (North Shields) Ltd (Blacklock v Swan Hunter Shipbuilders Ltd, Gray v Smiths Shiprepairers (North Shields) Ltd, Mitchell v Vickers Armstrong Ltd, Nicholson v Smiths Shiprepairers (North Shields) Ltd, Waggott v Swan Hunter Shipbuilders Ltd) [1984] QB 405
- Maynard v West Midlands Regional Health Authority [1984] 1 WLR 634
- Bolam v Friern Hospital Management Committee [1957] 1 WLR 582
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
Available to signed-in members.