Summary
In construing tradeable financial instruments, the contractual language has paramount importance. Commercial consequences may be evaluated, but hindsight and retrospective commercial common sense cannot justify departing from clear wording.
A court may add words by construction, or imply a term, only where the agreement is incomplete or commercially incoherent without them, the omission was inadvertent, and the proposed provision is sufficiently certain. A contractual mechanism for calculating interest must be applied according to its terms, including the priority given to payments under a post-default waterfall.
Where interest has been capitalised under the underlying loan agreement, it may reduce assumed available interest collections if the contractual calculation is cumulative. A provision dealing with cash-flow shortfalls does not ordinarily govern later-discovered miscalculations.
Factual background
The claim concerned seven issues arising from the calculation of payments due on a Class X note in the Windermere VII commercial mortgage-backed securitisation. The claimants, as holders of the Class X note, challenged calculations made for the January and October 2015 payment dates.
The principal questions concerned the construction of the Senior Rate and Junior Rate provisions in an intercreditor agreement, the treatment of default interest and servicing fees under a post-default waterfall, the effect of capitalised interest under an underlying French-law mortgage loan, and whether any underpayment generated further interest or an event of default.
Held
- Construction and correction. The court applied the ordinary principles of contractual construction, with particular weight placed on the language of tradeable financial instruments and on evaluating rival interpretations in their commercial setting. The definitions of Senior Rate and Junior Rate were carefully constructed provisions central to the bargain. There was no sufficiently clear mistake, and it was not clear that the parties would have adopted the additional wording proposed by Hayfin. The court therefore declined to correct or imply those words.
- January 2015 calculations. The assumed payment of default interest under the definition of Expected Available Interest Collections did not mean that the sums would be available to the Issuer. Under the post-default waterfall, default interest was subordinated to prior-ranking interest and principal payments. Sums applied to principal rather than interest did not qualify as Expected Available Interest Collections. Servicing fees and related costs payable first under the waterfall likewise reduced the amounts transferable to the Issuer and therefore reduced the relevant calculation.
- Capitalised interest. On the cumulative basis assumed by the parties, the Issuer correctly reduced Expected Available Interest Collections to reflect interest capitalised under clause 22.3 of the Adductor Mortgage Loan Agreement and Article 1154 of the French Civil Code. The contractual power to capitalise interest formed part of the arrangements and its natural effect was to reduce unpaid interest while permitting compound interest thereafter.
- Shortfalls and events of default. Condition 5(i) provided a mechanism for deferring amounts determined to be due where available collections were insufficient. It did not provide a general contractual rate of interest for subsequently discovered miscalculations. Conditions 5(c) and 5(d) meant that the amounts due and payable were those determined by the Cash Manager. A later-discovered miscalculation therefore did not create a Note Event of Default under Condition 10(a)(i).
- The court expressed provisional views that applying the Class X Interest Rate to an underpayment would likely engage the penalty doctrine and might be exorbitant, but that issue was not finally determined. The claimants failed on the substantive issues, and the court directed counsel to agree declarations giving effect to its conclusions.
The court’s approach to earlier authorities
Available to signed-in members.
Key cases cited
16 authorities cited.
- Marks and Spencer plc v BNP Paribas Securities Services Trust Company (Jersey) Limited and another [2015] UKSC 72
- Cavendish Square Holding BV v Talal El Makdessi [2015] UKSC 67
- Arnold v Britton and others [2015] UKSC 36
- In re Sigma Finance Corpn [2010] 1 All ER 571
- Chartbrook Limited (Respondents) v Persimmon Homes Limited and others (Appellants) and another (Respondent) [2009] UKHL 38
- Attorney General of Belize v Belize Telecom Ltd [2009] UKPC 10
- Investors Compensation Scheme Ltd v West Bromwich Building Society (Investors Compensation Scheme Ltd v Hopkins & Sons) [1997] UKHL 28
- BP Refinery (Westernport) Pty Ltd v The President Councillors and Ratepayers of the Shire of Hastings (1977) 180 CLR 266
- Napier Park European Credit Opportunities Fund Ltd v Harbourmaster Pro-Rata Clo 2 B.V. & Ors [2014] EWCA Civ 984
- KPMG LLP v Network Rail Infrastructure Ltd [2007] EWCA Civ 363
- Deutsche Trustee Company Ltd v Cheyne Capital (Management) UK (LLP) & Anor [2015] EWHC 2282 (Ch)
- Philips Electronique Grand Public SA v British Sky Broadcasting Ltd [1995] EMLR 472
- ATKINS INTERNATIONAL H.A. v. ISLAMIC REPUBLIC OF IRAN SHIPPING LINES [1987] 2 Lloyd's Rep 37
- Shirlaw v Southern Foundries (1926) Ltd [1939] 2 KB 206
- Reigate v Union Manufacturing Co (Ramsbottom) Ltd [1918] 1 KB 592
- The Moorcock (1889) 14 PD 64
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
3 later cases · 2 neutral · 1 negative
Most senior citing decisions:
- Credit Suisse Asset Management LLC v Titan Europe 2006-1 PLC & Ors [2016] EWCA Civ 1293 considered
- Deutsche Trustee Company Ltd v Duchess VI CLO B.V. & Ors [2019] EWHC 778 (Ch) considered
- Credit Suisse Asset Management LLC v Titan Europe 2006-1 Plc & Ors [2016] EWHC 969 (Ch) not followed
Sign in for the full treatment table. A free account is enough.