Grove Developments Ltd v S&T (UK) Ltd

[2018] EWHC 123 (TCC)

Summary

A payment or pay less notice is construed objectively, in its factual context, by asking how a reasonable recipient would understand it. Incorporation by reference is permissible where the referenced document is clearly identified and enables the recipient to understand the sum and its calculation. Validity remains a matter of fact and degree.

Where an employer has failed to serve an effective payment or pay less notice, it must pay the sum stated as due, but may thereafter commence a separate adjudication concerning the true value of the relevant application. The notice regime regulates cash flow and does not deem the stated sum to be the true valuation.

Contractual notices concerning liquidated damages are effective where sent and received in the required sequence, absent any specified interval between them.

Treatment over time

Cited in 11 later judgments between 2018 and 2025. Applied, followed or approved 8 times, most recently by the High Court in January 2025.

Most often cited for

  1. Later interim applications may correct the true value of earlier work3 judgments
  2. An employer must pay the notified sum before commencing a true-value adjudication3 judgments

Factual background

The claimant employer engaged the defendant contractor under a JCT Design and Build Contract 2011 for the construction of a hotel. Following adjudications concerning incorporation of amendments, extension of time and payment, the parties disputed the validity of the employer’s pay less notice and the enforceability of the third adjudication decision.

The court also considered whether the employer could seek a separate adjudication as to the true value of an interim application if its payment notices were ineffective, and whether notices concerning liquidated damages had been served in the required sequence.

Held

  1. Pay less notice. The notice was valid. It clearly identified the sum said to be due, the liquidated damages deduction and the earlier payment certificate containing the detailed valuation. A reasonable recipient would have understood the calculation. The contract required specification of the basis of calculation, not transmission of every supporting document at the same time. The contrary construction was artificial and contrived.
  2. The construction of payment and pay less notices is objective and contextual. The notice must make clear its contractual character, the sum said to be due or deducted, and the basis of calculation. Whether those requirements are met is a matter of fact and degree. The same general approach applies to contractor and employer notices.
  3. The third adjudication decision was not enforceable. The court had finally determined the only dispute referred in that adjudication, namely the content of the pay less notice. The first adjudicator’s decision concerning incorporation of the Schedule of Amendments also remained binding, so the notice was served within the applicable contractual period.
  4. True value. On the assumption that the employer’s notice was deficient, the employer would still have been entitled, after paying the sum stated as due, to commence a separate adjudication concerning the true value of the interim application. The court and adjudicator had power to open up, review and revise notices and applications. The valuation dispute was different from the notice-validity dispute and had not been decided in the earlier adjudication.
  5. The contract distinguished between “the sum due”, representing the contractual true valuation, and “the sum stated as due”, which became payable under the notice regime. Failure to serve an effective notice did not create a deemed agreement that the contractor’s figure was the true value. The same principle applied to interim and final payments. The court declined to follow the different approach in ISG Construction Ltd v Seevic College and Galliford Try Building Ltd v Estura Ltd, considering there was a powerful reason to do so.
  6. Liquidated damages notices. The warning and deduction notices were sent and received in the required sequence. Clause 2.29 prescribed no minimum interval between them. Their validity was therefore not affected by the fact that they were received only seconds apart.
  7. Issues A, B, C and D were decided in Grove’s favour. No interest was payable on the agreed basis.

The court’s approach to earlier authorities

Available to signed-in members.

Appeal route

  1. This judgment · 27 February 2018 [2018] EWHC 123 (TCC) High Court (Technology and Construction Court)
  2. Appealed to · 7 November 2018S&T (UK) Ltd v Grove Developments Ltd[2018] EWCA Civ 2448 Court of Appeal (Civil Division)Upheld this judgmentAppeal dismissed (unanimous)

Other judgments in these proceedings

2 judgments in these proceedings, earliest first. Linked by appeals and by the court numbers the judgments share.

  1. 27 February 2018Grove Developments Ltd v S&T (UK) Ltd[2018] EWHC 123 (TCC) · High Court (Technology and Construction Court) · this judgment
  2. 7 November 2018S&T (UK) Ltd v Grove Developments Ltd[2018] EWCA Civ 2448 · Court of Appeal (Civil Division)

Cases on related points

Of these 8 cases: 1 cited alongside it for another point; 7 related in other ways.

Cited alongside it for other points

  1. Henry Boot Construction Ltd. v Alstom Combined Cycles Ltd.[2005] EWCA Civ 814 · Court of Appeal (Civil Division)Non-conclusive certificates may be reviewed and revised to determine the true amount payableCited together in 3 later judgments

Other related cases

  1. RGB Plastering Ltd v TAWE Drylining and Plastering Ltd[2020] EWHC 3028 (TCC) · High Court (Technology and Construction Court)Relies on 2 of the same authorities
  2. Hutton Construction Lted v Wilson Properties (London) Ltd[2017] EWHC 517 (TCC) · High Court (Technology and Construction Court)Relies on 5 of the same authorities

+5 more for signed-in readers

Key cases cited

The 30 most senior of 31 authorities cited.

Sign in to see how the court treated each authority and the other 1. A free account is enough.

Cases citing this case

11 later cases · 8 positive · 1 neutral · 2 caution

Most senior citing decisions:

Sign in for the full treatment table, including the other 1 cases. A free account is enough.