Summary
In a complex construction project, an independent Category 3 checker engaged by a subcontractor did not owe the main contractor a duty of care for economic loss arising from defective temporary works. The duty had to be defined by reference to the kind of loss claimed, not considered abstractly. Objectively assessed assumption of responsibility, reliance, contractual structure, proximity and fairness were material. A detailed contractual allocation of design responsibility and risk may exclude any tortious duty between parties lacking contractual links, particularly where the claimant already had a contractual claim against the subcontractor. Knowledge that a certificate would be passed to the main contractor was insufficient. The certificates also contained no warranties directly enforceable by the main contractor where there was no contract, collateral warranty, authority or consideration between the parties.
Factual background
Multiplex was the main contractor for a major construction project. Bathgate, formerly Dunne, was its design-and-build subcontractor and had responsibility for the temporary works. Dunne engaged RNP Associates Ltd to perform an independent Category 3 design check of a slipform rig. RNP supplied certificates to Dunne, which later provided altered or delayed versions to Multiplex. RNP was subsequently liquidated and Multiplex pursued Argo, its insurers, under the Third Parties (Rights against Insurers) Act 2010.
The parties agreed preliminary issues concerning whether RNP owed Multiplex duties or obligations in respect of the certificates and whether RNP provided warranties directly to Multiplex. The court also determined the contractual terms governing RNP's engagement by Dunne.
Held
- Contract formation. Dunne's letter enclosing a proposed Consultancy Agreement was a counter-offer. There was no evidence that Dunne later accepted RNP's quotation or that RNP accepted the proposed Consultancy Agreement. A contract nevertheless existed on simple terms: RNP would perform the Category 3 check for the agreed fee and would use reasonable care and skill. RNP's standard terms were not incorporated.
- Duty of care. The court applied the principles in South Australia Asset Management Corp v York Montague Ltd [1996] UKHL 10, Caparo Industries plc v Dickman [1990] UKHL 2 and Customs and Excise Commissioners v Barclays Bank plc [2006] UKHL 28. The scope of any duty had to be determined by reference to the kind of loss claimed. Assumption of responsibility was an objective inquiry, assessed against the whole commercial, factual and contractual context. The three-part and incremental approaches were alternative analytical routes which would ordinarily lead to the same result.
- RNP did not assume responsibility to Multiplex. Dunne had full contractual responsibility to Multiplex for the design of the temporary works and for obtaining the Category 3 check. RNP contracted only with Dunne, had no direct contact with Multiplex, received limited information, and provided no services directly to Multiplex. The contractual structure would be short-circuited by imposing a direct tortious duty. Knowledge that the certificate should reach the Temporary Works Co-ordinator did not establish responsibility for Multiplex's economic loss. Nor was this a liability-gap case. The first preliminary issue was answered No.
- Actual reliance was not part of the preliminary issues, but legal reliance remained relevant. Multiplex did not allow the certificates to operate on its mind so as to cause the claimed economic loss. The certificate had to be considered as a whole, including its notes and observations.
- Warranties. There was no contract or collateral warranty between RNP and Multiplex. Dunne had no authority to contract with RNP as Multiplex's agent, and payments by Multiplex to Dunne were not consideration for a separate contract with RNP. The certificates were not contractual warranties given directly to Multiplex. The second preliminary issue was answered No. The answers were unchanged even if the certifying words were considered separately from the certificates as a whole.
The court’s approach to earlier authorities
Available to signed-in members.
Key cases cited
14 authorities cited.
- Her Majesty's Commissioners of Customs and Excise (Respondents) v. Barclays Bank plc (Appellants) [2006] UKHL 28
- Williams v Natural Life Health Foods Ltd [1998] 1 WLR 830
- Banque Bruxelles Lambert SA v Eagle Star Insurance Co Ltd (BNP Mortgages Ltd v Goadsby & Harding Ltd, BNP Mortgages Ltd v Key Surveyors Nationwide Ltd, United Bank of Kuwait Plc v Prudential Property Services Ltd, South Australia Asset Management Corpn v York Montague Ltd) [1997] AC 191
- Marc Rich & Co AG v Bishop Rock Marine Co Ltd (The Nicholas H) [1996] AC 211
- White v Jones [1995] 2 AC 207
- Henderson v Merrett Syndicates Ltd (Feltrim Underwriting Agencies Ltd v Arbuthnott, Gooda Walker Ltd v Deeny, Hughes v Merrett Syndicates Ltd, Hallam-Eames v Merrett Syndicates Ltd, The Lloyd’s Litigation: the Merrett, Gooda Walker and Feltrim Cases) [1995] 2 AC 145
- Caparo Industries plc v Dickman [1990] 2 AC 605
- Hedley Byrne & Co Ltd v Heller & Partners Ltd [1964] AC 465
- Lejonvarn v Burgess & Anor [2017] EWCA Civ 254
- Hunt v Optima (Cambridge) Ltd & Ors [2014] EWCA Civ 714
- James McNaughton Paper Group Ltd v Hicks Anderson & Co [1991] 2 QB 113
- Arrowhead Capital Finance Ltd v KPMG LLP [2012] EWHC 1801 (Comm)
- Galliford Try Infrastructure Ltd & Anor v Mott MacDonald Ltd [2008] EWHC 1570 (TCC)
- Riyad Bank v Ahli United Bank (UK) plc [2006] EWHC Civ 780
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
1 later case · 1 positive
Most senior citing decisions:
- Beattie Passive Norse Ltd & Anor v Canham Consulting Ltd [2021] EWHC 1116 (TCC) applied
Sign in for the full treatment table. A free account is enough.