Case details
Summary
Under regulation 72 of the Public Contracts Regulations 2015, the gateways permitting modification of a public contract without a fresh procurement must be construed narrowly, but that does not create a reverse evidential burden on the contracting authority. A modification is substantial if it possesses any one of the regulation 72(8) characteristics; the characteristics operate disjunctively.
For regulation 72(8)(b)(ii), the question is whether the modification created a real prospect that a different tender would have been accepted. The counterfactual is assessed by reference to the original procurement. Economic balance is assessed against the contract as a whole, and reasonable compensation for a short-term additional service will not necessarily alter that balance.
Factual background
James Waste Management LLP challenged two procurement decisions by Essex County Council. The first was a modification of the Council’s integrated waste handling contract with Veolia, using an additional waste transfer station for a temporary period. The second was the award of a service order to Enovert South Ltd under Lot 1 of a framework agreement.
JW alleged breaches of the Public Contracts Regulations 2015, including unlawful substantial modification, use of the wrong framework lot, lack of transparency, and grounds for civil penalties. The central questions were whether the modification was substantial, whether Lot 1 could be used for residual waste when the mechanical biological treatment facility was not operating, and whether any penalty was required.
Held
Claim dismissed. The modification did not breach procurement law, the Lot 1 award was lawful, and no civil penalty was required.
- Substantial modification. Regulation 72(1)(e) requires a fresh procurement only where the modification is substantial within regulation 72(8). The characteristics in regulation 72(8)(a)–(d) are disjunctive. The gateways in regulation 72(1) are derogations and require narrow construction, subject to an interpretation that preserves their effectiveness. That principle did not impose an evidential burden on the Council.
- The temporary use of the additional waste transfer station did not materially change the character of the contract or considerably extend its scope. The modification remained concerned with the same waste handling services, affected only a limited part of the operation, lasted five months, and represented a small proportion of the contract’s value.
- For regulation 72(8)(b)(ii), the relevant question was whether there was a real, rather than fanciful, prospect that another original tenderer would have won the counterfactual procurement. The assessment was to be made as at the time of the original procurement, with the modification included in the hypothetical contract. The evidence did not establish such a prospect.
- The gate fee and guaranteed mileage did not change the economic balance in Veolia’s favour. Reasonable compensation was an appropriate yardstick where the original payment mechanism could not simply be applied. The assessment concerned the contract as a whole.
- Schedule 21. Although the issue was unnecessary after the conclusion on substantial modification, the Council could not rely on regulation 72(1)(a). Schedule 21 required substantial compliance with its detailed change procedure. The Council omitted the required contractor response and discussion process. The contractual agreement of a variation did not itself establish that the variation was made pursuant to Schedule 21.
- Lot 1 and regulation 18. Lot 1 was not confined to waste produced by the mechanical biological treatment facility. Its reference to RDF and/or MSW permitted disposal of residual municipal waste from another source. The Enovert Service Order was therefore within the framework agreement. No breach of transparency or equal treatment was established.
- Civil penalties. Regulations 98–102 assumed a live contract capable of being declared ineffective or shortened. Since the relevant contracts had ended, regulation 102 did not operate and no civil penalty was mandatory.
The court’s approach to earlier authorities
This feature is available to zoomLaw Pro members.
Appellate history
First-instance decision. No prior appellate decision is stated in the judgment.
Key cases cited
This feature is available to zoomLaw Pro members.
Cases citing this case
This feature is available to zoomLaw Pro members.