Summary
A guarantee is construed by reference to the instrument as a whole and its commercial context. References to a demand, unconditional liability or liability as principal obligor do not alone establish a demand guarantee. A suretyship guarantee may require proof of the principal debtor’s underlying liability, but not a prior judgment or arbitral award unless the contract so provides.
Contractual admissions, particularly irrevocable admissions integral to a payment agreement, may operate as binding contractual promises. A seller retaining title may claim the price under Sale of Goods Act 1979, section 49(2), where payment is due on an ascertainable date, including one fixed by reference to a future or contingent event, and the payment obligation is not concurrent with delivery.
Factual background
CE Energy DMCC sought summary judgment in two related actions. In one, it claimed against Alhaji Abdulrahman Musa Bashar under a personal guarantee supporting payment obligations owed by Ultimate Oil & Gas DMCC. In the other, it claimed against Ultimate Oil & Gas for the price of a cargo supplied under a later spot contract.
The defendants relied on proposed amended defences concerning the nature of the guarantee, the effect of admissions in a payment agreement, retention of title, allocation of payments and liability for demurrage and interest. The central questions were whether the defences had a realistic prospect of success and whether the seller could recover the price while retaining title.
Held
- Summary judgment. The applicable test was that in Easyair Ltd v Opal Telecom [2009] EWHC 339 (Ch). A defence need only have a realistic, rather than fanciful, prospect of success. The court must avoid a mini-trial, although it may decide a short and determinative legal issue. The proposed defences had no realistic prospect of success.
- Nature of the guarantee. The guarantee was a contract of suretyship, not a demand guarantee. Its essential promise was to secure Ultimate Oil & Gas’s performance of its payment obligations. The relevant indications included the focus on the company’s obligations and sums payable by it, the waiver of suretyship defences, the open-ended nature of the security and the commercial context of an individual owner guaranteeing company debts. The demand machinery governed the timing and mechanics of payment and did not convert the instrument into a demand guarantee.
- The claimant therefore had to establish Ultimate Oil & Gas’s underlying liability, but it did not have to obtain a prior judgment or arbitral award. The guarantee expressly excluded any need to obtain an award or judgment first. Liability and adjudication of liability were distinct matters.
- Contractual admissions. The irrevocable admissions in the payment agreement were contractual promises, not merely evidential admissions. They were integral to the payment mechanism and its purpose of establishing a binding basis for settlement. Ultimate Oil & Gas was contractually bound by them, and Mr Bashar was equally bound because he guaranteed its payment obligations and independently accepted the stated indebtedness.
- Claim for the price. Although Sale of Goods Act 1979, section 49 was treated as a complete code under FG Wilson (Engineering) Ltd v John Holt & Co (Liverpool) Ltd [2013] EWCA Civ 1232, section 49(2) applied. Following Readie Construction Ltd v Geo Quarries Ltd [2021] EWHC 3030 (QB) and persuasive authorities, a day certain meant an ascertainable date. It could be fixed by a contingent event or by an act of a party or third party. The contractual notice of readiness identified such a date, and payment was not made concurrent with delivery.
- The remaining arguments, including the alleged irrational allocation of payments and challenges to demurrage and interest, offered no realistic prospect of success. Summary judgment was granted against both defendants and permission to amend was refused. Costs and the form of order were reserved for further submissions.
The court’s approach to earlier authorities
Available to signed-in members.
Key cases cited
23 authorities cited.
- PST Energy 7 Shipping LLC and another v O W Bunker Malta Limited and another [2016] UKSC 23
- Braganza v BP Shipping Limited and another [2015] UKSC 17
- Shanghai Shipyard Co Ltd v Reignwood International Investment (Group) Co Ltd [2021] EWCA Civ 1147
- Richards v Wood [2014] EWCA Civ 327
- Caterpillar (NI) Ltd v John Holt & Company (Liverpool) Ltd [2013] EWCA Civ 1232
- AC Ward & Son v Catlin (Five) Ltd & Ors [2009] EWCA Civ 1098
- Marubeni Hong Kong & South China Ltd v Ministry of Finance of Mongolia [2005] EWCA Civ 395
- Hughes & Ors v Richards (t/a Colin Richards & Co) [2004] EWCA Civ 266
- Otis Vehicle Rentals Ltd v Ciceley Commercials Ltd [2002] EWCA Civ 1064
- Rolls-Royce Holdings Plc v Goodrich Corporation & Ors [2023] EWHC 1637 (Comm)
- Readie Construction Ltd v Geo Quarries Ltd [2021] EWHC 3030 (QB)
- Autoridad Del Canal De Panamá v Sacyr, S.A. & Ors [2017] EWHC 2228 (Comm)
- PST Energy 7 Shipping LLC & Anor v OW Bunker Malta Ltd & Anor (Res Cogitans) [2015] EWHC 2022 (Comm)
- Easyair Ltd (t/a Openair) v Opal Telecom Ltd [2009] EWHC 339 (Ch)
- Mitsubishi Corp RTM International Pte Ltd v Kyen Resources Pte Ltd [2016] SGHCR 6
- Shell-Mex, Ltd v Elton Cop Dyeing Co, Ltd (1928) 34 Com Cas 39
- MULLER, MACLEAN & CO. v. LESLIE & ANDERSON. (1921) 8 Ll L Rep 328
- Stein Forbes & Co v County Tailoring Co (1916) 115 LT 215
- Workman, Clark & Co Ltd v Lloyd BrazileÑo [1908] 1 KB 968
- Dunlop v Grote (1845) 2 Car & K 153
- Maclean v Dunn (1828) 4 Bing NC
- The Merchant Shipping Co v Armitage
- Pordage v Cole 1 Wms. Saund. (1669) 319
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
1 later case · 1 caution
Most senior citing decisions:
- Trans Trade RK SA v State Food and Grain Corporation of Ukraine [2025] EWHC 1803 (Comm) explained
Sign in for the full treatment table. A free account is enough.