Summary
Where parties agree to the trial of a preliminary issue of contractual construction, the tribunal should decide that issue rather than ask whether a party's construction is merely arguable, provided the relevant evidence and submissions are before it or should have been produced under the directions given. The contract must be read as a whole in its relevant context.
Under the shipbuilding contracts considered, a provision governing the consequences of modifications requested by the buyer did not give the builder a separate right to alter the work unilaterally and increase the price. The builder's assumption of work previously subcontracted was a change in its method of performance, not a modification of the specified work. Additional costs arising from the subcontractor's insolvency therefore fell outside the contractual price-adjustment and delivery-security mechanism.
Factual background
AS, the buyer, entered into four materially identical shipbuilding contracts with EB, the builder. A subcontractor became insolvent and EB claimed additional costs. The contracts contained a mechanism for payment or security of disputed amounts before delivery.
The parties agreed that an arbitral tribunal should determine preliminary delivery issues in their consolidated arbitrations. The tribunal decided that EB had an arguable claim that the subcontractor-related costs arose from a modification under the contracts, but declined to decide that claim finally on the material then available.
AS appealed under section 69 of the Arbitration Act 1996. The central question was whether the claim for those costs concerned a modification or change of the work to be performed by EB within Article VI(1), so that it fell within the delivery-security mechanism.
Held
The appeal was allowed. The tribunal should have decided the construction issue directed for trial as a preliminary issue. The parties had been given ample opportunity to plead their cases and produce relevant evidence. No contested contextual issue was identified. An arguability review might be appropriate on a summary judgment or strike-out application, but it was not the proper approach to this preliminary issue ([15]–[17], [20]).
The contracts had to be construed as a whole, applying the principles summarised in Songa Product and Chemical Tankers III AS v Kairos Shipping II LLC (Songa Pride) [2025] EWCA Civ 1227. The second paragraph of Article VI(1) dealt with consequences of modifications requested by the buyer under its first paragraph. It did not confer a separate right on the builder to make a unilateral change and increase the price. Its reference to written agreement pointed back to the first paragraph, and the builder's proposed reading gave no answer to a buyer's objection to a unilateral change ([12], [24]–[27], [30]).
The contractual context supported that reading. The builder remained responsible for subcontracted work as if it had performed the work itself. Taking over work previously intended for a subcontractor changed the builder's method of performance, rather than the specification of the work. Later events could not determine the contract's meaning. The additional costs resulting from the subcontractor's insolvency therefore fell outside the price-adjustment provision and the delivery-security mechanism ([28]–[30]).
The builder accepted that its estoppel argument depended on an otherwise arguable modification claim under the proper construction. It therefore did not arise. The force majeure notice issue was likewise immaterial in view of the construction adopted ([31]–[32]).
Subject to submissions on the form of order, the judge proposed to answer the question in the claim form in the negative, set aside paragraph [145(5)] of the award and vary paragraph [145(6)] by substituting €23,535,511.52 for €34,363,966.15. The judge invited submissions on costs ([33]–[35]).
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
- High Court (Commercial Court): AS's appeal under section 69 of the Arbitration Act 1996 was allowed. The judge proposed to set aside one part of the award and vary another, subject to submissions on the form of order.
- Arbitral tribunal: In a partial final award dated 21 April 2026, the tribunal held that EB had an arguable modification claim but declined to decide it finally on the material then available.
Key cases cited
1 authority cited.
- Songa Product and Chemical Tankers III AS v Kairos Shipping II LLC [2025] EWCA Civ 1227
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
Available to signed-in members.