| Date | Case | Cited by |
|---|---|---|
| 21 Dec 2004 |
[2004] EWHC 3336 (TCC)
An adjudicator’s award must be enforced in accordance with what the adjudicator decided. An employer may set off liquidated damages where the adjudicator’s…
|
10 |
| 21 Dec 2004 |
[2004] EWHC 3054 (TCC)
Insurance conditions must be construed commercially and in the context of the insured premises. A cleaning obligation does not require impossible or…
|
1 |
| 20 Dec 2004 |
[2004] EWHC 3319 (TCC)
A liquidated damages clause linked to sectional completion is void for uncertainty where the contract does not define the contents of each section or provide a…
|
3 |
| 9 Dec 2004 |
[2004] EWHC 3053 (TCC)
A contractual cause of action generally accrues when the claimant first has the right to sue. Contractual notice, assessment or invoicing procedures do not…
|
2 |
| 9 Dec 2004 |
[2004] EWHC 2938 (TCC)
Expert evidence supporting a substantial construction claim must provide a sufficiently particularised and intelligible basis for the figures advanced. Where…
|
|
| 8 Dec 2004 |
[2004] EWHC 3052 (TCC)
A repairing covenant requiring premises to be delivered up in good and substantial repair does not require perfect or pristine condition. The relevant standard…
|
5 |
| 6 Dec 2004 |
[2004] EWHC 3286 (TCC)
A cost-plus construction contract may arise from correspondence, drawings, site discussions and conduct even though no fixed price, programme or completion…
|
8 |
| 18 Nov 2004 |
[2004] EWHC 2749 (TCC)
Permission to adduce further evidence late in a trial may be granted where fairness requires the claimant to answer a case that emerged during…
|
|
| 12 Nov 2004 |
[2004] EWHC 2609 (TCC)
A costs-capping order should normally be prospective and sought at an early stage, so that the parties can plan the litigation with knowledge of the…
|
|
| 12 Nov 2004 |
[2004] EWHC 2560 (TCC)
Under art 23 of the Council Regulation (EC) No. 44/2001, a clause selecting a particular court in a Member State may confer exclusive jurisdiction over…
|
|
| 11 Nov 2004 |
[2004] EWHC 2642 (TCC)
Where a contribution is awarded, an interest rate substantially above base rate requires supporting commercial evidence. In the absence of such evidence, a…
|
|
| 10 Nov 2004 |
[2004] EWHC 3051 (TCC)
On an appeal under Arbitration Act 1996, an arbitrator’s costs decision may raise a question of law where the arbitrator fails to identify the dispute by…
|
|
| 10 Nov 2004 |
[2004] EWHC 2610 (TCC)
Partial disclosure of privileged material may be required where a party deploys part of a document and fairness requires the opposing party to see the material…
|
|
| 9 Nov 2004 |
[2004] EWHC 2809 (TCC)
A contractual payment becomes enforceable according to the agreed payment regime, including any contractual period allowed for payment. A contractor cannot…
|
1 |
| 5 Nov 2004 |
[2004] EWHC 2898 (TCC)
Under CPR 6.4(2), service on a solicitor is valid where the solicitor is authorised to accept service and has notified the serving party in writing of that…
|
|
| 5 Nov 2004 |
[2004] EWHC 2512 (TCC)
In a construction contract, the ordinary measure of damages for defective work is the reasonable cost of reinstatement. It is unavailable where that measure is…
|
1 |
| 4 Nov 2004 |
[2004] EWHC 2556 (TCC)
Late amendments to pleadings may be permitted where any prejudice can be remedied by costs. An amendment should nevertheless be refused if it is irrelevant to…
|
|
| 4 Nov 2004 |
[2004] EWHC 2450 (TCC)
A letter of intent which anticipates execution of a standard building contract does not incorporate that contract merely because it identifies the proposed…
|
|
| 29 Oct 2004 |
[2004] EWHC 2439 (TCC)
An adjudicator may determine a later extension-of-time dispute even where an earlier adjudication concerned related delay events, provided the later…
|
1 |
| 22 Oct 2004 |
[2004] EWHC 2991 (TCC)
Acknowledgment under section 29(5)(a) of the Limitation Act 1980 does not revive a claim for unliquidated damages in tort. A liquidated pecuniary claim is a…
|
2 |
| 22 Oct 2004 |
[2004] EWHC 2494 (TCC)
For ostensible authority to arise, the principal must make, or permit, a representation that the agent has authority to bind it. An agent’s own conduct cannot…
|
2 |
| 22 Oct 2004 |
[2004] EWHC 2363 (TCC)
Permission to amend pleadings may be granted despite prolixity or imperfect particularity where the claimant cannot substantially simplify the case and refusal…
|
|
| 21 Oct 2004 |
[2004] EWHC 3264 (TCC)
For limitation purposes, a proposed amendment raises a new cause of action where it introduces a distinct factual situation entitling the claimant to a remedy.…
|
|
| 19 Oct 2004 |
[2004] EWHC 2365 (TCC)
A dispute is suitable for adjudication by reference to whether the adjudicator can reach a fair and impartial decision within the statutory or agreed…
|
3 |
| 14 Oct 2004 |
[2004] EWHC 2615 (TCC)
Contract formation is determined objectively. A party’s private belief, or a pleading assertion about the contracting party, carries little weight unless…
|
|
| 11 Oct 2004 |
[2004] EWHC 2339 (TCC)
A dispute does not arise merely because a claim is notified. It arises when, viewed objectively, the claim is not admitted. The circumstances may include…
|
20 |
| 6 Oct 2004 |
[2004] EWHC 2206 (TCC)
A series of letters of intent may create successive “if” contracts. Where the final letter governs the parties’ relationship, its express financial limit…
|
|
| 30 Sep 2004 |
[2004] EWHC 3298 (TCC)
In contracts for the sale of goods, an agreed specification may form an express contractual term. A general disclaimer does not permit delivery of goods…
|
|
| 30 Sep 2004 |
[2004] EWHC 3057 (TCC)
When exercising the costs discretion under CPR Part 44.3, the court should consider the identity of the successful party, success on individual issues…
|
|
| 30 Sep 2004 |
[2004] EWHC 2408 (TCC)
Terms are implied into a construction-related lease only where necessary to give the contract business efficacy or because they went without saying. A separate…
|
|
| 2 Sep 2004 |
[2004] EWHC 1916 (TCC)
A contract is not concluded merely because the parties have agreed substantial commercial terms. The court must consider the correspondence and conduct…
|
|
| 20 Aug 2004 |
[2004] EWHC 2326 (TCC)
An arbitration notice does not lapse merely because the party serving it delays applying for the appointment of an arbitrator. A term requiring appointment or…
|
|
| 18 Aug 2004 |
[2004] EWHC 2021 (TCC)
In negligence, nuisance and statutory breach claims arising from the same facts, causation ordinarily requires a single approach where the statutory duty does…
|
|
| 30 Jul 2004 |
[2004] EWHC 2357 (TCC)
Where negotiations are expressed to be subject to contract, that qualification ordinarily continues unless removed by express agreement or necessary…
|
|
| 30 Jul 2004 |
[2004] EWHC 1748 (TCC)
Contractual valuation provisions must be applied by reference to the agreed contractual mechanism. Additional or substituted work is valued by analogy with…
|
1 |
| 28 Jul 2004 |
[2004] EWHC 2340 (TCC)
Litigation privilege attaches to a document prepared by a third party only where litigation is reasonably in prospect and the dominant purpose of its…
|
|
| 28 Jul 2004 |
[2004] EWHC 1766 (TCC)
A court will give effect to clear express contractual terms, even where a different arrangement might appear commercially preferable. A term may be implied…
|
|
| 27 Jul 2004 |
[2004] EWHC 2407 (TCC)
A carefully negotiated written agreement may be treated as the complete record of the parties’ contract, preventing reliance on an inconsistent collateral…
|
|
| 22 Jul 2004 |
[2004] EWHC 1778 (TCC)
Under CPR Part 19.5, a party may be added or substituted after limitation has expired where the limitation period was current when proceedings began and the…
|
|
| 21 Jul 2004 |
[2004] EWHC 1750 (TCC)
A professional designer’s contractual duty to exercise reasonable care and skill in designing a structure includes verifying provisional design assumptions on…
|
2 |
| 8 Jul 2004 |
[2004] EWHC 1660 (TCC)
A performance contract must be construed as a whole, giving effect to its language and commercial purpose. Under contractual “absolute guarantees”, recovery of…
|
|
| 25 Jun 2004 |
[2004] EWHC 1638 (TCC)
Under CPR Part 6.5(6), a proprietor’s “last known place of business” means the last place of business known to the claimant, rather than the last objectively…
|
4 |
| 25 Jun 2004 |
[2004] EWHC 1518 (TCC)
For the purposes of statutory adjudication, a construction agreement may be in writing even though it contains implied terms. Written evidence of acceptance…
|
|
| 11 Jun 2004 |
[2004] EWHC 1300 (TCC)
Under section 108(1)(b) of the Housing Grants, Construction and Regeneration Act 1996, a construction contract must enable referral of a dispute within seven…
|
2 |
| 9 Jun 2004 |
[2004] EWHC 3421 (TCC)
Where negotiations and correspondence do not establish a concluded construction contract, the parties’ rights are assessed on a quantum meruit basis. The…
|
|
| 28 May 2004 |
[2004] EWHC 1285 (TCC)
An adjudicator’s decision is binding only until the underlying dispute is finally determined. A party may obtain that determination before enforcement, and…
|
7 |
| 28 May 2004 |
[2004] EWHC 1185 (TCC)
Inspection of disclosed documents is governed by the disclosure order as well as the Civil Procedure Rules. Where relevant material is confidential, relevance…
|
|
| 18 May 2004 |
[2004] EWHC 993 (TCC)
Repairing and decorating covenants require substantial compliance, judged by the age, character and locality of the premises and the needs of a reasonably…
|
3 |
| 12 May 2004 |
[2004] EWHC 2030 (TCC)
An adjudicator must decide the dispute, and the legal and factual basis of that dispute, which the referring party has submitted. The adjudicator may take the…
|
1 |
| 11 May 2004 |
[2004] EWHC 1232 (TCC)
Where parties have concluded a contract containing an agreement in principle to settle a matter later, failure to agree the detailed machinery does not…
|
|
| 7 May 2004 |
[2004] EWHC 1017 (TCC)
A series of interim orders for design, procurement and site works does not become a contract for the whole project merely because the parties expect to execute…
|
|
| 21 Apr 2004 |
[2004] EWHC 695 (TCC)
A contractual performance obligation must be construed by reference to the language used and the relevant background. A recipe identifying ingredients and…
|
|
| 7 Apr 2004 |
[2004] EWHC 2651 (TCC)
In a claim for damage caused by neighbouring excavation and construction works, the claimant must establish that the works were the most likely cause of the…
|
|
| 5 Apr 2004 |
[2004] EWHC 899 (TCC)
For the purposes of section 105(2)(c) of the Housing Grants, Construction and Regeneration Act 1996, the relevant site is assessed as a whole. Whether its…
|
1 |
| 5 Apr 2004 |
[2004] EWHC 888 (TCC)
An adjudicator’s jurisdiction depends on the dispute which the parties agreed to refer and the basis on which it was referred. The process is not confined…
|
7 |
| 26 Mar 2004 |
[2004] EWHC 737 (TCC)
A conditional fee agreement satisfying the statutory conditions under section 58 of the Courts and Legal Services Act 1990 is not unenforceable for champerty…
|
|
| 27 Feb 2004 |
[2004] EWHC 393 (TCC)
An adjudication award will not be enforced where the circumstances establish a real possibility of adjudicator bias or a breach of natural justice.…
|
|
| 27 Feb 2004 |
[2004] EWHC 137 (TCC)
A Tomlin Order may contain implied terms requiring the parties to co-operate, exchange necessary information and act with reasonable speed where its factual…
|
|
| 26 Feb 2004 |
[2004] EWHC 275 (TCC)
A contractual right to terminate for breach must be construed in its commercial context. A clause permitting termination for breach of any term may, depending…
|
2 |
| 20 Feb 2004 |
[2004] EWHC 138 (TCC)
A letter of intent may create an interim agreement without incorporating the proposed standard-form contract. A subsequent offer of complete contractual terms…
|
3 |
| 20 Feb 2004 |
[2004] EWHC 136 (TCC)
In a construction professional-negligence claim, delay-related financing loss is recoverable in principle where the claimant proves a direct causal connection…
|
4 |
| 16 Jan 2004 |
[2004] EWHC 8 (TCC)
Where parties agree an architect’s instruction as a variation to an existing construction contract, the instruction may have contractual effect even though the…
|
|
| 16 Jan 2004 |
[2004] EWHC 36 (TCC)
The appointment procedure in the Scheme for Construction Contracts must be followed. After notice of adjudication, the named adjudicator must first be…
|
3 |
| 16 Jan 2004 |
[2004] EWHC 2 (TCC)
A contractor may recover reasonable additional remuneration where the employer varies the contract and materially enlarges its scope. Contractual payment…
|