High Court: Technology and Construction Court judgments, 2004

64 judgments, newest first. Open any case for its summary, the legal points it decides and how later courts have treated it.

Date Case Cited by
21 Dec 2004
[2004] EWHC 3336 (TCC)
An adjudicator’s award must be enforced in accordance with what the adjudicator decided. An employer may set off liquidated damages where the adjudicator’s…
10
21 Dec 2004
[2004] EWHC 3054 (TCC)
Insurance conditions must be construed commercially and in the context of the insured premises. A cleaning obligation does not require impossible or…
1
20 Dec 2004
[2004] EWHC 3319 (TCC)
A liquidated damages clause linked to sectional completion is void for uncertainty where the contract does not define the contents of each section or provide a…
3
9 Dec 2004
[2004] EWHC 3053 (TCC)
A contractual cause of action generally accrues when the claimant first has the right to sue. Contractual notice, assessment or invoicing procedures do not…
2
9 Dec 2004
[2004] EWHC 2938 (TCC)
Expert evidence supporting a substantial construction claim must provide a sufficiently particularised and intelligible basis for the figures advanced. Where…
8 Dec 2004
[2004] EWHC 3052 (TCC)
A repairing covenant requiring premises to be delivered up in good and substantial repair does not require perfect or pristine condition. The relevant standard…
5
6 Dec 2004
[2004] EWHC 3286 (TCC)
A cost-plus construction contract may arise from correspondence, drawings, site discussions and conduct even though no fixed price, programme or completion…
8
18 Nov 2004
[2004] EWHC 2749 (TCC)
Permission to adduce further evidence late in a trial may be granted where fairness requires the claimant to answer a case that emerged during…
12 Nov 2004
[2004] EWHC 2609 (TCC)
A costs-capping order should normally be prospective and sought at an early stage, so that the parties can plan the litigation with knowledge of the…
12 Nov 2004
[2004] EWHC 2560 (TCC)
Under art 23 of the Council Regulation (EC) No. 44/2001, a clause selecting a particular court in a Member State may confer exclusive jurisdiction over…
11 Nov 2004
[2004] EWHC 2642 (TCC)
Where a contribution is awarded, an interest rate substantially above base rate requires supporting commercial evidence. In the absence of such evidence, a…
10 Nov 2004
[2004] EWHC 3051 (TCC)
On an appeal under Arbitration Act 1996, an arbitrator’s costs decision may raise a question of law where the arbitrator fails to identify the dispute by…
10 Nov 2004
[2004] EWHC 2610 (TCC)
Partial disclosure of privileged material may be required where a party deploys part of a document and fairness requires the opposing party to see the material…
9 Nov 2004
[2004] EWHC 2809 (TCC)
A contractual payment becomes enforceable according to the agreed payment regime, including any contractual period allowed for payment. A contractor cannot…
1
5 Nov 2004
[2004] EWHC 2898 (TCC)
Under CPR 6.4(2), service on a solicitor is valid where the solicitor is authorised to accept service and has notified the serving party in writing of that…
5 Nov 2004
[2004] EWHC 2512 (TCC)
In a construction contract, the ordinary measure of damages for defective work is the reasonable cost of reinstatement. It is unavailable where that measure is…
1
4 Nov 2004
[2004] EWHC 2556 (TCC)
Late amendments to pleadings may be permitted where any prejudice can be remedied by costs. An amendment should nevertheless be refused if it is irrelevant to…
4 Nov 2004
[2004] EWHC 2450 (TCC)
A letter of intent which anticipates execution of a standard building contract does not incorporate that contract merely because it identifies the proposed…
29 Oct 2004
[2004] EWHC 2439 (TCC)
An adjudicator may determine a later extension-of-time dispute even where an earlier adjudication concerned related delay events, provided the later…
1
22 Oct 2004
[2004] EWHC 2991 (TCC)
Acknowledgment under section 29(5)(a) of the Limitation Act 1980 does not revive a claim for unliquidated damages in tort. A liquidated pecuniary claim is a…
2
22 Oct 2004
[2004] EWHC 2494 (TCC)
For ostensible authority to arise, the principal must make, or permit, a representation that the agent has authority to bind it. An agent’s own conduct cannot…
2
22 Oct 2004
[2004] EWHC 2363 (TCC)
Permission to amend pleadings may be granted despite prolixity or imperfect particularity where the claimant cannot substantially simplify the case and refusal…
21 Oct 2004
[2004] EWHC 3264 (TCC)
For limitation purposes, a proposed amendment raises a new cause of action where it introduces a distinct factual situation entitling the claimant to a remedy.…
19 Oct 2004
[2004] EWHC 2365 (TCC)
A dispute is suitable for adjudication by reference to whether the adjudicator can reach a fair and impartial decision within the statutory or agreed…
3
14 Oct 2004
[2004] EWHC 2615 (TCC)
Contract formation is determined objectively. A party’s private belief, or a pleading assertion about the contracting party, carries little weight unless…
11 Oct 2004
[2004] EWHC 2339 (TCC)
A dispute does not arise merely because a claim is notified. It arises when, viewed objectively, the claim is not admitted. The circumstances may include…
20
6 Oct 2004
[2004] EWHC 2206 (TCC)
A series of letters of intent may create successive “if” contracts. Where the final letter governs the parties’ relationship, its express financial limit…
30 Sep 2004
[2004] EWHC 3298 (TCC)
In contracts for the sale of goods, an agreed specification may form an express contractual term. A general disclaimer does not permit delivery of goods…
30 Sep 2004
[2004] EWHC 3057 (TCC)
When exercising the costs discretion under CPR Part 44.3, the court should consider the identity of the successful party, success on individual issues…
30 Sep 2004
[2004] EWHC 2408 (TCC)
Terms are implied into a construction-related lease only where necessary to give the contract business efficacy or because they went without saying. A separate…
2 Sep 2004
[2004] EWHC 1916 (TCC)
A contract is not concluded merely because the parties have agreed substantial commercial terms. The court must consider the correspondence and conduct…
20 Aug 2004
[2004] EWHC 2326 (TCC)
An arbitration notice does not lapse merely because the party serving it delays applying for the appointment of an arbitrator. A term requiring appointment or…
18 Aug 2004
[2004] EWHC 2021 (TCC)
In negligence, nuisance and statutory breach claims arising from the same facts, causation ordinarily requires a single approach where the statutory duty does…
30 Jul 2004
[2004] EWHC 2357 (TCC)
Where negotiations are expressed to be subject to contract, that qualification ordinarily continues unless removed by express agreement or necessary…
30 Jul 2004
[2004] EWHC 1748 (TCC)
Contractual valuation provisions must be applied by reference to the agreed contractual mechanism. Additional or substituted work is valued by analogy with…
1
28 Jul 2004
[2004] EWHC 2340 (TCC)
Litigation privilege attaches to a document prepared by a third party only where litigation is reasonably in prospect and the dominant purpose of its…
28 Jul 2004
[2004] EWHC 1766 (TCC)
A court will give effect to clear express contractual terms, even where a different arrangement might appear commercially preferable. A term may be implied…
27 Jul 2004
[2004] EWHC 2407 (TCC)
A carefully negotiated written agreement may be treated as the complete record of the parties’ contract, preventing reliance on an inconsistent collateral…
22 Jul 2004
[2004] EWHC 1778 (TCC)
Under CPR Part 19.5, a party may be added or substituted after limitation has expired where the limitation period was current when proceedings began and the…
21 Jul 2004
[2004] EWHC 1750 (TCC)
A professional designer’s contractual duty to exercise reasonable care and skill in designing a structure includes verifying provisional design assumptions on…
2
8 Jul 2004
[2004] EWHC 1660 (TCC)
A performance contract must be construed as a whole, giving effect to its language and commercial purpose. Under contractual “absolute guarantees”, recovery of…
25 Jun 2004
[2004] EWHC 1638 (TCC)
Under CPR Part 6.5(6), a proprietor’s “last known place of business” means the last place of business known to the claimant, rather than the last objectively…
4
25 Jun 2004
[2004] EWHC 1518 (TCC)
For the purposes of statutory adjudication, a construction agreement may be in writing even though it contains implied terms. Written evidence of acceptance…
11 Jun 2004
[2004] EWHC 1300 (TCC)
Under section 108(1)(b) of the Housing Grants, Construction and Regeneration Act 1996, a construction contract must enable referral of a dispute within seven…
2
9 Jun 2004
[2004] EWHC 3421 (TCC)
Where negotiations and correspondence do not establish a concluded construction contract, the parties’ rights are assessed on a quantum meruit basis. The…
28 May 2004
[2004] EWHC 1285 (TCC)
An adjudicator’s decision is binding only until the underlying dispute is finally determined. A party may obtain that determination before enforcement, and…
7
28 May 2004
[2004] EWHC 1185 (TCC)
Inspection of disclosed documents is governed by the disclosure order as well as the Civil Procedure Rules. Where relevant material is confidential, relevance…
18 May 2004
[2004] EWHC 993 (TCC)
Repairing and decorating covenants require substantial compliance, judged by the age, character and locality of the premises and the needs of a reasonably…
3
12 May 2004
[2004] EWHC 2030 (TCC)
An adjudicator must decide the dispute, and the legal and factual basis of that dispute, which the referring party has submitted. The adjudicator may take the…
1
11 May 2004
[2004] EWHC 1232 (TCC)
Where parties have concluded a contract containing an agreement in principle to settle a matter later, failure to agree the detailed machinery does not…
7 May 2004
[2004] EWHC 1017 (TCC)
A series of interim orders for design, procurement and site works does not become a contract for the whole project merely because the parties expect to execute…
21 Apr 2004
[2004] EWHC 695 (TCC)
A contractual performance obligation must be construed by reference to the language used and the relevant background. A recipe identifying ingredients and…
7 Apr 2004
[2004] EWHC 2651 (TCC)
In a claim for damage caused by neighbouring excavation and construction works, the claimant must establish that the works were the most likely cause of the…
5 Apr 2004
[2004] EWHC 899 (TCC)
For the purposes of section 105(2)(c) of the Housing Grants, Construction and Regeneration Act 1996, the relevant site is assessed as a whole. Whether its…
1
5 Apr 2004
[2004] EWHC 888 (TCC)
An adjudicator’s jurisdiction depends on the dispute which the parties agreed to refer and the basis on which it was referred. The process is not confined…
7
26 Mar 2004
[2004] EWHC 737 (TCC)
A conditional fee agreement satisfying the statutory conditions under section 58 of the Courts and Legal Services Act 1990 is not unenforceable for champerty…
27 Feb 2004
[2004] EWHC 393 (TCC)
An adjudication award will not be enforced where the circumstances establish a real possibility of adjudicator bias or a breach of natural justice.…
27 Feb 2004
[2004] EWHC 137 (TCC)
A Tomlin Order may contain implied terms requiring the parties to co-operate, exchange necessary information and act with reasonable speed where its factual…
26 Feb 2004
[2004] EWHC 275 (TCC)
A contractual right to terminate for breach must be construed in its commercial context. A clause permitting termination for breach of any term may, depending…
2
20 Feb 2004
[2004] EWHC 138 (TCC)
A letter of intent may create an interim agreement without incorporating the proposed standard-form contract. A subsequent offer of complete contractual terms…
3
20 Feb 2004
[2004] EWHC 136 (TCC)
In a construction professional-negligence claim, delay-related financing loss is recoverable in principle where the claimant proves a direct causal connection…
4
16 Jan 2004
[2004] EWHC 8 (TCC)
Where parties agree an architect’s instruction as a variation to an existing construction contract, the instruction may have contractual effect even though the…
16 Jan 2004
[2004] EWHC 36 (TCC)
The appointment procedure in the Scheme for Construction Contracts must be followed. After notice of adjudication, the named adjudicator must first be…
3
16 Jan 2004
[2004] EWHC 2 (TCC)
A contractor may recover reasonable additional remuneration where the employer varies the contract and materially enlarges its scope. Contractual payment…