Case details
Summary
A case must be properly pleaded, but a formal amendment may be unnecessary where the proposed point is a matter of legal construction and the opposing party has received clear and adequate notice of it. The decision is a case-management exercise governed by the overriding objective, including considerations of proportionality, complexity, importance, financial position, delay, prejudice, and fair and expeditious conduct. An appellate court will be slow to interfere with the trial judge’s exercise of that discretion, particularly where the judge controls the trial and has considered the relevant material. A party seeking permission on a preliminary procedural issue should act promptly so that the trial judge knows the appellate position before the hearing begins.
Factual background
KLH Developments Limited v John Akins (Development) Limited & Anor arose from a building contract for hotel works. After the works were stopped, the proceedings included a counterclaim concerning alleged defects, including structural design defects. KLH sought to rely on the contention that Yeadon Consultant Design Limited was solely responsible for the structural design, although that contention had not been expressly pleaded.
Judge Taylor ordered on 31 January 2000 that no amendment was required because the issue was one of law and the defendants had sufficient notice. A later application to join Yeadon was refused, but that order was not pursued. The central issue was whether the judge had erred in permitting the point to be taken without a formal amendment and whether his case-management discretion could be challenged on grounds of lateness or prejudice.
Held
The Court of Appeal unanimously refused permission to appeal. The applicant was ordered to pay the respondents’ costs, summarily assessed at £2,500.
- Pleading and notice. The general requirement that a case must be properly pleaded remained valid. Parties should not ordinarily be required to anticipate unpleaded issues and incur costs in addressing them. However, where the proposed contention concerns the legal construction of contractual documents and the opposing party has plainly received adequate notice of it, the trial judge may conclude that a formal amendment is unnecessary.
- Case-management discretion. The decision whether amendment is required is a matter for the trial judge’s case-management discretion. Judge Taylor had considered the documentation and submissions and was entitled to find that the defendants had known since July 1999 that the point would be taken at trial. The Court of Appeal could not successfully interfere with that discretionary decision, particularly as the judge had charge of the proceedings and had already conducted 16 hearing days.
- Delay in seeking appellate intervention. A party wishing to challenge a preliminary procedural ruling should bring the matter before the Court of Appeal expeditiously, preferably before the trial begins. This enables the trial judge and the parties to know the appellate position. Lord Justice Swinton Thomas stated that this was not the central basis of the decision, but Sir Christopher Slade agreed that the delay point could not succeed.
- The refusal to require amendment was therefore upheld in substance, and permission to appeal was refused.
The court’s approach to earlier authorities
This feature is available to zoomLaw Pro members.
Appellate history
- Court of Appeal (Civil Division): On 21 July 2000, the court refused permission to appeal and ordered the applicant to pay £2,500 costs, as recorded in [2000] EWCA Civ 378.
- Construction & Technology Court: Judge Taylor ordered on 31 January 2000 that no amendment was required to plead the contractual construction point because it was a matter of law and adequate notice had been given. A separate order dated 23 February 2000 refusing joinder of Yeadon Consultant Design Limited was not pursued.
Lower court decision
Key cases cited
This feature is available to zoomLaw Pro members.
Cases citing this case
This feature is available to zoomLaw Pro members.