Summary
A contractual “dispute or difference” is interpreted inclusively where it controls access to arbitration. A dispute may readily be inferred once liability is not accepted, although its existence always depends on the contractual and factual context.
An engineer deciding a dispute under clause 66 of the ICE Conditions must act independently, honestly and with flexible fairness. The engineer need not conduct a judicial process or invariably hear both parties. An inherent conflict arising from the engineer’s contractual role does not itself disqualify the engineer.
For the scope of a subsequent arbitration, “the matter” means the dispute or difference referred to the engineer, rather than only the points expressly decided by the engineer.
Factual background
Serious defects appeared in roller bearings installed by Amec during renovation of the Thelwell Viaduct. Shortly before the perceived expiry of the limitation period, the Secretary of State asserted that Amec was responsible, referred the dispute to the contractual Engineer under clause 66 of the ICE Conditions, obtained a decision and served notice of arbitration.
The arbitrator rejected Amec’s jurisdictional objections. Jackson J dismissed Amec’s appeal under section 67 of the Arbitration Act 1996: [2004] EWHC 2339 (TCC).
The Court of Appeal considered whether a dispute or difference existed when the matter was referred, whether the Engineer’s procedure or conflict of interest invalidated his decision, and whether the arbitration was confined to the defects expressly itemised in that decision.
Held
The appeal was dismissed unanimously. May LJ delivered the leading judgment, with which Hooper LJ agreed. Rix LJ agreed in the result but differed concerning the Engineer’s obligation of procedural fairness.
A dispute or difference capable of reference under clause 66 existed after the meeting at which Amec indicated that it did not accept responsibility. The words were ordinary English words whose meaning depended on context. “Difference” was wider and less hard-edged than “dispute”. Commercial good sense favoured an inclusive construction which did not create opportunistic technical obstacles to commencing arbitration before limitation expired. A claim need not be fully developed through completed technical investigation before a dispute can arise.
The Engineer was required to act independently and honestly. Fairness was a flexible obligation shaped by the facts and occasion; it did not import the rules of natural justice or require a judicial process. The Engineer could use existing knowledge of the contract and, where the other party’s position was already known, could decide without a formal invitation for further representations. If material representations beyond the request itself were received from one party, fairness might require an opportunity for the other to respond, but this was not an inflexible rule. A properly considered speedy decision could be requested and given where limitation was imminent.
The Engineer’s position as the Employer’s agent, and the possibility that the same defects might expose the Engineer to a claim, did not disqualify him. Such conflicts were an inherent potential consequence of the contractual machinery. On the facts, the decision was made independently, honestly and after sufficient consideration.
Rix LJ considered that the dispute-settlement role under clause 66 carried a stronger duty of fairness and that the Engineer should have heard Amec’s response. Nevertheless, even an invalid or unenforceable decision would remain a decision capable of triggering arbitration. A valid Engineer’s decision was not invariably a condition of arbitration because failure to decide within three months also permitted a reference.
“The matter” capable of reference to arbitration was the dispute or difference referred to the Engineer, not merely the matters expressly decided. The reference and notice embraced all actual or suspected defects within the asserted responsibility for the viaduct, including related defects revealed by later investigation.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
Court of Appeal (Civil Division): Dismissed Amec’s appeal in [2005] EWCA Civ 291 and upheld the conclusion that the arbitration was validly commenced with the claimed scope.
High Court, Technology and Construction Court: Jackson J dismissed Amec’s appeal under section 67 of the Arbitration Act 1996 and granted permission for a further appeal: [2004] EWHC 2339 (TCC) .
Arbitration: The arbitrator rejected Amec’s objections to jurisdiction and its proposed restriction on the scope of the arbitration.
Appeal route
- Appealed from[2004] EWHC 2339 (TCC)This appealappeal dismissed unanimously
- This judgment [2005] EWCA Civ 291 Court of Appeal (Civil Division)
Key cases cited
22 authorities cited.
- Beaufort Developments (NI) Ltd v Gilbert-Ash NI Ltd [1999] 1 AC 266
- Collins (Contractors) Ltd. v Baltic Quay Management (1994) Ltd [2004] EWCA Civ 1757
- Amec Capital Projects Ltd v Whitefriars City Estates Ltd [2004] EWCA Civ 1418
- Halki Shipping Corpn v Sopex Oils Ltd [1998] 1 WLR 726
- PETERSON FARMS INC. v. C&M FARMING LTD. [2004] EWHC 121 (Comm) [2004] 1 Lloyd's Rep 603
- Re Application for Wasted Costs [2003] EWHC 822 (TCC)
- Electrosteel Castings Ltd v Scan-Trans Shipping & Chartering Sdn Bhd [2002] EWHC 1993 (Comm)
- Sindall Ltd v Solland (TCC) 15 June 2001
- CRUDEN CONSTRUCTION LTD. v. COMMISSION FOR THE NEW TOWNS [1995] 2 Lloyd's Rep 387
- HAYTER v. NELSON AND HOME INSURANCE CO. [1990] 2 Lloyd's Rep 265
- Ellerine Brothers (Pty) Ltd v Klinger [1982] 1 WLR 1375
- In re Wheeler (A Debtor) [1982] 1 WLR 175
- Tradax Internacional S.A. v Cerrahogullari T.A.S. [1981] 3 All ER 344
- Sutcliffe v Thackrah [1974] AC 727
- Hounslow London Borough Council v Twickenham Garden Developments Ltd [1971] Ch 233
- F & G Sykes v Fine Fare [1967] 1 LLR 53
- A C Hatrick (NZ) Ltd v Nelson Carlton Construction Co Ltd [1965] NZLR 144
- Monmouthshire County Council v Costelloe 5 BLR 83
- A C Hatrick (NZ) Ltd v Nelson Carlton Construction Co Ltd [1964] NZLR 72
- Panamena Europea Navigacion (Cia Limitada) v Frederick Leyland & Co Ltd (J Russell & Co) [1947] AC 428
- Page v Llandaff and Dinas Powis Rural District Council (1901) 2 Hudson's Building Contracts (4th ed) 316
- Sindall Limited v Solland
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
20 later cases · 16 positive · 1 neutral · 3 caution
Most senior citing decisions:
- Norfolk County Council v Blanmar 2 LLP [2023] EWHC 2120 (TCC) followed
- BRAVEJOIN COMPANY LIMITED v PROSPERITY MOSELEY STREET LIMITED [2021] EWHC 3598 (TCC) explained
- MW High Tech Projects UK Ltd v Balfour Beatty Kilpatrick Ltd [2020] EWHC 1413 (TCC) applied
- LJH Paving Ltd v Meeres Civil Engineering Ltd [2019] EWHC 2601 (TCC)
- Griffin v Wainwright & Anor [2017] EWHC 2122 (Ch)
- AMD Environmental Ltd v Cumberland Construction Company Ltd [2016] EWHC 285 (TCC)
- CSK Electrical Contractors Ltd v Kingwood Electrical Services Ltd [2015] EWHC 667 (TCC)
- St Austell Printing Company Ltd v Dawnus Construction Holdings Ltd [2015] EWHC 96 (TCC)
- Beck Interiors Ltd v UK Flooring Contractors Ltd [2012] EWHC 1808 (TCC)
- Witney Town Council v Beam Construction (Cheltenham) Ltd [2011] EWHC 2332 (TCC)
Sign in for the full treatment table, including the other 10 cases. A free account is enough.