Summary
An adjudicator’s decision should ordinarily be enforced promptly. On an application to stay enforcement, the court must exercise its discretion with the temporary and binding character of adjudication firmly in mind. A probable inability to repay the award when repayment may fall due can amount to a special circumstance, particularly where the successful party is insolvent. A stay will usually be inappropriate where the successful party’s financial position is materially unchanged from that accepted when the contract was made, or where its financial difficulty was caused substantially by the paying party’s non-payment. An unparticularised counterclaim which does not identify any contractual breach has no real prospect of defeating summary judgment for an agreed debt.
Treatment over time
Cited in 44 later judgments between 2006 and 2026. Applied, followed or approved 39 times, most recently by the High Court in October 2026.
Most often cited for
- Stays of adjudication enforcement are exceptional, balancing prompt enforcement against the claimant’s probable inability to repay and its causes
Factual background
Wimbledon Construction Company 2000 Ltd. v Vago concerned enforcement of an adjudicator’s award arising from residential extension and refurbishment works. The adjudicator awarded the contractor £122,923.34 inclusive of VAT. The employer consented to judgment but sought a stay of execution pending arbitration, alleging that the contractor’s financial position meant that any repayment could not be recovered.
The contractor also sought summary judgment for £6,507.97 for agreed post-contract works. The employer relied on an alleged set-off and counterclaim concerning heating and ventilation defects. The central issues were whether that counterclaim had a real prospect of success and whether enforcement of the adjudication award should be stayed.
Held
- Judgment was entered for the claimant and a stay was refused. The defendant’s proposed counterclaim did not provide a real prospect of defending the agreed £6,507.97 debt. The evidence did not identify the contractual obligations allegedly breached, did not correlate the fitter’s report with the proposed remedial costs, and was internally uncertain as to value.
- Adjudication under the Housing Grants, Construction and Regeneration Act 1996 and the contractual scheme is intended to give a rapid, temporarily binding answer. Adjudicators’ decisions should therefore be enforced summarily and the successful party should generally receive the money awarded.
- Under Rules of the Supreme Court Order 47, rule 1(1)(a), probable inability to repay the judgment sum when repayment might arise may be a special circumstance. The court should assess that risk at the prospective date of repayment, not merely at the date of enforcement. Insolvent liquidation, or uncontroverted insolvency, will usually justify a stay. The court declined to import the precise test in section 726(1) of the Companies Act 1985, although its established discretionary guidance was generally relevant.
- The defendant had not proved that the claimant would probably be unable to repay in nine to twelve months. The claimant was then making a modest profit and its accountant’s evidence answered the allegation of insolvency. Loans from directors and others did not establish a probable inability to repay.
- Independently, a stay would have been wrong because the claimant’s financial position was substantially the same as when the defendant contracted with it. Further, the financial problems on which the defendant relied were caused in significant part by the defendant’s failure to pay sums later found due in adjudication. Summary judgment was entered for £129,431.31 inclusive of VAT, with interest, and execution was not stayed.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
High Court (Technology and Construction Court): Enforcement proceedings followed an adjudicator’s decision of 21 February 2005. Arbitration proceedings challenging aspects of that decision had also been commenced. No appellate history is stated in the judgment.
Often cited alongside this case
Of these 8 cases: 2 cited with it on the same point; 4 cited alongside it for other points; 2 related in other ways.
Cited together forStays of adjudication enforcement are exceptional, balancing prompt enforcement against the claimant’s probable inability to repay and its causes
- AWG Construction Services Ltd v Rockingham Motor Speedway LtdCited together in 5 later judgments
+1 more for signed-in readers
Cited alongside it for other points
- Farrelly (M & E) Building Services Ltd v Byrne Brothers (Formwork) LtdEnforcing parties need not generally disclose confidential financial information to inform a stay applicationCited together in 4 later judgments
+3 more for signed-in readers
Other related cases
- Bewley Homes Plc v CNM Estates (Surbiton) LtdCited together in 3 later judgments
+1 more for signed-in readers
5 more related cases for signed-in readers. A free account is enough.
Key cases cited
5 authorities cited.
- AWG Construction Services v Rockingham Motor Speedway [2004] EWHC 888
- Herschell Engineering Limited v Breen Property Limited unreported, 28th July 2000
- Sir Lindsay Parkinson & Co Ltd v Triplan Ltd [1973] QB 609
- Rainford House Limited v Cadogan Limited unreported, 13.2.01
- Absolute Rentals v Glencor Enterprises Limited unreported, 16.1.00
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
44 later cases · 39 positive · 1 neutral · 4 caution
Most senior citing decisions:
- Gosvenor London Ltd v Aygun Aluminium UK Ltd [2018] EWCA Civ 2695 applied
- Avanton Capital CC Limited v LUC Construction Limited [2026] EWHC 2630 (TCC) applied
- Deerns UK Limited v VDC LHR11 Limited [2026] EWHC 1509 (TCC) applied
- Crest Nicholson Regeneration Limited & Ors v Ardmore Construction Limited (in Administration) & Ors [2026] EWHC 1069 (TCC)
- Laing O’Rourke Delivery Limited v Shepperton Studios Limited [2026] EWHC 612 (TCC)
- Complete Ceiling and Partitioning Systems Limited v DE1 Limited [2024] EWHC 2800 (TCC)
- J & B Hopkins Limited v A & V Building Solution Limited [2023] EWHC 2475 (TCC)
- Bexhill Construction Ltd v Kingsmead Homes Ltd [2023] EWHC 2344 (TCC)
- Alun Griffiths (Contractors) Limited v Carmarthenshire County Council [2023] EWHC 2269 (TCC)
- WRB (N.I.) Limited v Henry Construction Projects Limited [2023] EWHC 278 (TCC)
Sign in for the full treatment table, including the other 34 cases. A free account is enough.