Summary
An adjudication award will ordinarily be enforced summarily, but enforcement must yield where the adjudicator decides the dispute on a novel, determinative basis which the parties had no fair opportunity to address. A point is not fairly canvassed merely because the underlying contract or documents were available.
A breach of natural justice is material where the unanswered point has a reasonable prospect of success, unless it is so obviously unarguable that it could not have affected the result. Insolvency may also justify refusing or staying enforcement where it deprives the respondent of security for a cross-claim.
Factual background
The claimant, a building contractor in administration, sought summary judgment to enforce an adjudication award requiring the defendant employer to pay approximately £102,829 plus interest, VAT and fees. The underlying contract concerned the conversion of commercial premises into apartments.
The adjudicator rejected the parties’ competing contractual routes to payment but awarded a balance under a different analysis, treating the contractual payment machinery as having fallen away. The defendant argued that this basis had not been advanced or fairly canvassed, and relied additionally on the claimant’s insolvency, loss of security for its cross-claim and alleged champerty in the funding arrangements.
Held
- Natural justice. The court applied the robust approach to adjudication enforcement, subject to jurisdictional error and material breach of natural justice. The parties’ cases concerned common-law damages or payment under clauses 8.7.4 and 8.7.5. The adjudicator instead held that clause 8 had fallen away and awarded payment on a residual contractual basis.
- The parties’ possession of the contract and their responses to a general question about clause 8.3.1 did not give notice of that approach. It was a novel and determinative basis, not an intermediate position between the cases advanced. The failure to invite submissions was therefore a breach of natural justice.
- Following Corebuild and ABB, the breach was material because the unanswered point had a reasonable prospect of success. The court did not decide the point itself. The defendant also had a realistically arguable case that, for an insolvent contractor, clauses 8.7.3 to 8.7.5 applied under clause 8.5.3 whether or not a termination notice had been served.
- The award was unenforceable and the application for summary judgment was dismissed.
- Had the natural-justice challenge failed, the court would have given judgment but stayed enforcement. Insolvency may displace the pay-now-argue-later approach where enforcement deprives the respondent of security for a cross-claim. The proposed ring-fencing and guarantees were inadequate. The damages-based agreement was non-compliant with the Damages-Based Agreements Regulations 2013, but the funding arrangement was not realistically arguable as an abuse of process.
The court’s approach to earlier authorities
Available to signed-in members.
Key cases cited
22 authorities cited.
- Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd [2020] UKSC 25
- John Doyle Construction Ltd v Erith Contractors Ltd [2021] EWCA Civ 1452
- Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd [2019] EWCA Civ 27
- Carillion v Devonport Royal Dockyard [2005] EWCA 1358
- The Refugee Legal Centre, R (on the application of) v Secretary of State for the Home Department [2004] EWCA Civ 1481
- Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd [2001] 1 All ER (Comm.) 1041
- BEXHEAT LIMITED v ESSEX SERVICES GROUP LIMITED [2022] EWHC 936 (TCC)
- Van Oord UK Ltd v Dragados UK Ltd [2022] CSOH 30
- Styles & Wood (in administration) v CE GIF Trustees [2020] EWHC 2694 (TCC)
- Corebuild Ltd v Cleaver & Anor [2019] EWHC 2170 (TCC)
- Meadowside Building Developments Ltd (in liquidation) v 12-28 Street Management Company Ltd [2019] EWHC 2651
- Aecom Design Build Ltd v Staptina Engineering Services Ltd [2017] EWHC 723 (TCC)
- Roe Brickwork Ltd v Wates Construction Ltd [2013] EWHC 3417 (TCC)
- ABB Limited v BAM Nuttall Limited [2013] EWHC 1984 (TCC)
- Squibb Group Ltd v Vertase FLI Ltd. [2012] EWHC 1958 (TCC)
- Straw Realisations (No.1) Ltd v Shaftsbury House (Developments) Ltd [2010] EWHC 2597
- Primus Build Ltd v Pompey Centre Ltd & Anor [2009] EWHC 1487 (TCC)
- Cantillon Limited v Urvasco Limited [2008] EWHC 282
- Wimbledon Construction Company 2000 Ltd. v Vago [2005] EWHC 1086 (TCC)
- Carillion v Devonport Royal Dockyard [2005] EWHC 788 (TCC)
- Macob Civil Engineering Limited v Morrison Construction Limited [1999] CLC 739
- Swissport (UK) Ltd (in liq) v Aer Lingus Ltd [2009] BCC 113
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
1 later case · 1 positive
Most senior citing decisions:
- Malin Industrial Concrete Floors Limited (in administration) v Volkerfitzpatrick Limited [2024] EWHC 2890 (TCC) applied
Sign in for the full treatment table. A free account is enough.