Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd (No. 2)

[2007] EWHC 145 (TCC)

Cited by 1 later case1 positiveCites 3 authorities

Summary

Contractual responsibility for temporary works depends on construing the agreement as a whole in its commercial and factual context. Where schedules are incorporated into the contract, their categories and descriptions may allocate different elements of work between lump-sum and cost-plus payment. A concluded antecedent agreement may be used where it gives clear guidance on the meaning of the later agreement. Commercial common sense may require a court to reject a literal construction which produces an impractical or commercially incoherent result. Design, drafting and fabrication of roof temporary works were connected with erection and therefore fell within the cost-plus provision, whereas temporary works for the bowl and arch fell within the lump-sum provision.

Factual background

This was the trial of the eleventh preliminary issue in litigation concerning the Wembley Stadium project. The parties had entered into a Heads of Agreement and later a Supplemental Agreement which reduced the defendant’s lump-sum work and placed specified activities on a cost-plus basis.

The issue was whether, after 15 February 2004, the design, drafting and fabrication of temporary works for the bowl, arch and roof fell within the lump-sum provision for all remaining works, the cost-plus provision for erection and site works, or the schedule item described as “temp works – roof props”. The court determined the contractual allocation of those responsibilities.

Held

  1. Construction of the incorporated schedules. The schedules referred to in the Heads of Agreement became contractual documents. The category 1 schedule covered the design, drafting and fabrication of temporary works relating to the bowl and arch. Those works therefore fell within the £12 million lump sum.

  2. The category 2 description “temp works – roof props”, read in context, meant all design, drafting and fabrication of temporary works for the roof, not merely the conversion of the toblerone sections. The quotation of £3.053 million, the absence of roof temporary works from category 1, and the practical connection between temporary works and erection supported that construction.

  3. A concluded antecedent agreement may be considered when it gives clear guidance on the point in issue. Applying that principle, the Heads of Agreement confirmed that roof temporary works were outside the lump-sum scope. See Ladbroke Group plc v Bristol City Council [1998] 1 EGLR 126.

  4. Clause 3.1 of the Supplemental Agreement was construed in accordance with the reasonable-person and commercial-context approach stated in Investors Compensation Scheme Ltd v West Bromwich Building Society [1998] 1 WLR 896, and supported by Sirius International Insurance Co (Publ) v FAI General Insurance Ltd [2004] UKHL 54; [2004] 1 WLR 3251. Its effect was that fabrication of the listed items was excluded from the lump sum, but remained within the subcontract and was payable on a cost-plus basis unless replaced by a new agreement or notice under clause 8.

  5. The words “erection and site works” in schedule 1 paragraph (c) were broad enough to include off-site costs connected with erection. Roof temporary-works fabrication, design and drafting were intimately connected with erecting the roof and could not sensibly be separated from it. They therefore fell within paragraph (c), as well as within “temp works – roof props”.

  6. The court answered preliminary issue 11 by allocating bowl and arch temporary works to paragraph (b), and roof temporary works to paragraph (c) and schedule 3 Part A. CB succeeded on responsibility for payment for the roof temporary works.

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

The judgment records that the decision on the first ten preliminary issues was under appeal, but the present judgment was given at the parties’ request without waiting for the Court of Appeal’s decision. No appellate decision on the present issue is stated.

Appeal route

  1. This judgment · 31 January 2007 [2007] EWHC 145 (TCC) High Court (Technology and Construction Court)
  2. Appealed to · 21 December 2007Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor[2007] EWCA Civ 1372 Court of Appeal (Civil Division)Partly reversed this judgmentAppeal allowed in part (unanimous)

Other judgments in these proceedings

12 judgments in these proceedings, earliest first. Linked by the shared court number HT-04-314, and by appeals.

  1. 5 June 2006Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd[2006] EWHC 1341 (TCC) · High Court (Technology and Construction Court)
  2. 20 December 2006Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor[2006] EWCA Civ 1834 · Court of Appeal (Civil Division)
  3. 31 January 2007Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd (No. 2)[2007] EWHC 145 (TCC) · High Court (Technology and Construction Court) · this judgment
  4. 12 March 2007Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd (No. 3)[2007] EWHC 659 (TCC) · High Court (Technology and Construction Court)
  5. 27 April 2007Cleveland Bridge UK Ltd & Anor v Multiplex Constructions (UK) Ltd[2007] EWCA Civ 443 · Court of Appeal (Civil Division)
  6. 21 December 2007Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor[2007] EWCA Civ 1372 · Court of Appeal (Civil Division)
  7. 6 February 2008Multiplex Construction Ltd v Cleveland Bridge Ltd & Anor[2008] EWCA Civ 133 · Court of Appeal (Civil Division)
  8. 19 March 2008Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor[2008] EWHC 569 (TCC) · High Court (Technology and Construction Court)
  9. 29 September 2008Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor[2008] EWHC 2220 (TCC) · High Court (Technology and Construction Court)
  10. 29 September 2008Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor[2008] EWHC 2280 (TCC) · High Court (Technology and Construction Court)
  11. 19 February 2010Cleveland Bridge UK Ltd & Anor v Multiplex Constructions (UK) Ltd[2010] EWCA Civ 139 · Court of Appeal (Civil Division)
  12. 31 March 2010Cleveland Bridge UK Ltd & Anor v Multiplex Constructions (UK) Ltd[2010] EWCA Civ 449 · Court of Appeal (Civil Division)

Related cases

Not part of these proceedings, but heard together with this judgment or between the same parties.

  1. 31 August 2005Cleveland Bridge UK Ltd v Multiplex Constructions (UK) Ltd[2005] EWHC 2101 (TCC) · High Court (Technology and Construction Court) · Same parties
  2. 7 February 2008Multiplex Construction (UK) Ltd v Cleveland Bridge UK Ltd[2008] EWHC 231 (TCC) · High Court (Technology and Construction Court) · Same parties

Key cases cited

3 authorities cited.

Sign in to see how the court treated each authority. A free account is enough.

Cases citing this case

1 later case · 1 positive

Most senior citing decisions:

Sign in for the full treatment table. A free account is enough.