| Date | Case | Cited by |
|---|---|---|
| 21 Dec 2007 |
[2007] EWHC 3049 (TCC)
A binding construction contract may arise despite outstanding detail, provided the parties objectively manifested agreement on sufficiently certain terms.…
|
|
| 19 Dec 2007 |
[2007] EWHC 3027 (TCC)
A professional services contract must be construed according to its agreed fee structure. A contractual entitlement to percentage fees for the basic workscope…
|
|
| 18 Dec 2007 |
[2007] EWHC 3042 (TCC)
Under Civil Procedure Rules 1998 Part 45, fixed costs apply by default where the specified conditions are met, but the court retains discretion to order…
|
5 |
| 18 Dec 2007 |
[2007] EWHC 3023 (TCC)
A claimant recovering damages for professional negligence or breach of contract must prove that the claimed loss was caused by the established breach, was…
|
8 |
| 18 Dec 2007 |
[2007] EWHC 3015 (TCC)
A written arbitration agreement is effective where made in writing, evidenced in writing, or made by reference to written terms. An arbitration clause may be…
|
|
| 11 Dec 2007 |
[2007] EWHC 3100 (TCC)
Substitution of a claimant after limitation has expired is governed primarily by CPR 19.5. A mistake as to the identity of the proper claimant is distinct from…
|
|
| 4 Dec 2007 |
[2007] EWHC 2870 (TCC)
A liquidator’s statutory power to sell company property does not authorise the sale of rights subject to a valid contractual prohibition on assignment. Such a…
|
1 |
| 30 Nov 2007 |
[2007] EWHC 2950 (TCC)
Retention monies held under a construction contract may be subject to both contractual and trustee obligations. Following a request for segregation, the…
|
|
| 30 Nov 2007 |
[2007] EWHC 2862 (TCC)
An interim injunction is appropriate where unauthorised works to jointly owned property raise a serious issue to be tried, the balance of convenience favours…
|
|
| 30 Nov 2007 |
[2007] EWHC 2833 (TCC)
Interim payment provisions in a construction subcontract must be construed as a mechanism for determining the amount to be paid, rather than as a determination…
|
3 |
| 29 Nov 2007 |
[2007] EWHC 3467 (TCC)
Adjudication agreements and notices should be construed commercially and in context. A misdescription of the referring party does not invalidate an…
|
|
| 23 Nov 2007 |
[2007] EWHC 3174 (TCC)
The appropriate forum for proceedings is determined by whether they involve technically complex issues or whether trial by a Technology and Construction Court…
|
|
| 22 Nov 2007 |
[2007] EWHC 3403 (TCC)
A specialist asbestos contractor is responsible for contamination caused by adopting an unsafe removal methodology and carrying out the work recklessly. A main…
|
|
| 20 Nov 2007 |
[2007] EWHC 2743 (TCC)
Risk/reward provisions in a construction subcontract apply to interim payments where the contract makes interim payment subject to adjustments and does not…
|
|
| 15 Nov 2007 |
[2007] EWHC 3454 (TCC)
An extension-of-time notice clause may operate as a condition precedent even without an express warning that non-compliance will remove the entitlement to an…
|
3 |
| 15 Nov 2007 |
[2007] EWHC 2738 (TCC)
A party challenging an adjudicator’s jurisdiction must either agree to be bound by the adjudicator’s decision on jurisdiction or reserve the right to challenge…
|
2 |
| 13 Nov 2007 |
[2007] EWHC 2718 (TCC)
Applications to adduce late expert evidence or amend a pleading require the court to balance the desirability of allowing a reasonably arguable case against…
|
|
| 2 Nov 2007 |
[2007] EWHC 2614 (TCC)
A claim arising from a fire does not automatically qualify for transfer to the Technology and Construction Court. The statutory criteria require either…
|
|
| 2 Nov 2007 |
[2007] EWHC 2544 (TCC)
An appeal from an arbitral award requires a properly arguable question of law. The court will not permit a party to recast a challenge to primary facts…
|
1 |
| 30 Oct 2007 |
[2007] EWHC 2507 (TCC)
When the court enforces an adjudicator’s decision, the cause of action is contractual: it arises from failure to comply with the adjudicator’s decision…
|
1 |
| 25 Oct 2007 |
[2007] EWHC 2420 (TCC)
A contractual adjudication clause remains enforceable despite an alleged oral variation of the underlying construction contract, unless the contract expressly…
|
2 |
| 23 Oct 2007 |
[2007] EWHC 2421 (TCC)
An adjudicator’s decision should be enforced unless the question decided was not the question referred or the adjudicator acted in excess of jurisdiction or…
|
4 |
| 17 Oct 2007 |
[2007] EWHC 2464 (TCC)
Applications to amend pleadings shortly before trial should be assessed by reference to the nature of the proposed case and the prejudice caused by allowing…
|
1 |
| 10 Oct 2007 |
[2007] EWHC 2173 (TCC)
An agent who acquires property in a principal’s name without authority does not thereby confer beneficial ownership on the principal. Beneficial ownership may…
|
2 |
| 3 Oct 2007 |
[2007] EWHC 2293 (TCC)
Preliminary issues should be ordered only where they are likely to produce a substantial saving of time or cost, materially improve settlement prospects, or…
|
|
| 2 Oct 2007 |
[2007] EWHC 3271 (TCC)
For limitation purposes, actual knowledge of damage attributable to negligence requires knowledge of the material facts constituting the essence of the…
|
|
| 1 Oct 2007 |
[2007] EWHC 2270 (TCC)
An interim payment may be ordered after a claimant obtains judgment for a sum to be assessed, provided the payment is just and does not exceed a reasonable…
|
|
| 19 Sep 2007 |
[2007] EWHC 2178 (TCC)
The Pre-action Protocol for Construction and Engineering Disputes applies to disputed claims for professional fees by consulting engineers, even where the…
|
|
| 5 Sep 2007 |
[2007] EWHC 2073 (TCC)
A binding construction contract may arise from informal documents and conduct where the parties, work and price are sufficiently certain. A signature and…
|
2 |
| 24 Aug 2007 |
[2007] EWHC 2021 (TCC)
The statutory enforcement scheme for sewerage duties does not automatically exclude every common-law or human-rights claim. The Marcic principle precludes…
|
6 |
| 31 Jul 2007 |
[2007] EWHC 2546 (TCC)
Professional negligence requires the standard of the reasonably competent professional exercising the relevant skill. An engineer is not negligent for failing…
|
2 |
| 30 Jul 2007 |
[2007] EWHC 2495 (TCC)
An arbitration agreement is not defeated by an ineffective or inapplicable contractual precondition. Where the specified dispute-resolution process cannot…
|
5 |
| 30 Jul 2007 |
[2007] EWHC 1857 (TCC)
An issue determined by the High Court in enforcement proceedings between the parties is binding in later arbitration proceedings where it identified the…
|
|
| 20 Jul 2007 |
[2007] EWHC 1749 (TCC)
Challenges under section 68 of the Arbitration Act 1996 require both a qualifying procedural irregularity and substantial injustice. The court’s role is a…
|
13 |
| 17 Jul 2007 |
[2007] EWHC 1691 (TCC)
Where a construction contract permits sums to be retained following determination, the provision may comply with section 111 of the Housing Grants Construction…
|
1 |
| 16 Jul 2007 |
[2007] EWHC 1773 (TCC)
The rule in Henderson v Henderson addresses abusive re-litigation. It cannot be used to oppose a late amendment in the existing action merely because the…
|
2 |
| 13 Jul 2007 |
[2007] EWHC 2015 (TCC)
Under CPR 38.6, discontinuance normally attracts an order requiring the claimant to pay the defendant’s costs. The court retains a discretion to depart from…
|
|
| 13 Jul 2007 |
[2007] EWHC 1505 (TCC)
A contract for professional design services does not ordinarily contain an implied term that a specified outcome will be achieved unless the desired outcome…
|
|
| 11 Jul 2007 |
[2007] EWHC 1710 (TCC)
A claimant assessing loss after defective construction works must take reasonable steps to mitigate, judged by the circumstances existing at the time and…
|
1 |
| 11 Jul 2007 |
[2007] EWHC 1670 (TCC)
A claimant may establish negligence through res ipsa loquitur where the precise mechanism of an accident cannot be proved, provided the evidence makes it more…
|
|
| 4 Jul 2007 |
[2007] EWHC 1584 (TCC)
The court has an inherent, discretionary jurisdiction to stay proceedings brought in breach of a binding agreement to adjudicate. Where such an agreement…
|
6 |
| 29 Jun 2007 |
[2007] EWHC 3159 (TCC)
Joint-names insurance against specified perils may establish a special contractual regime which displaces ordinary liability for negligence or breach of…
|
|
| 27 Jun 2007 |
[2007] EWHC 1573 (TCC)
In a defective building work claim, the ordinary measure of loss is the reasonable cost of reinstatement or repair. Where competing remedial schemes are…
|
1 |
| 27 Jun 2007 |
[2007] EWHC 1507 (TCC)
Contractual insurance provisions may determine whether a common-law duty of care exists between parties in a construction chain. Although physical damage to…
|
3 |
| 15 Jun 2007 |
[2007] EWHC 1420 (TCC)
Damages must be supported by evidence addressing the value of the individual property or loss claimed. An aggregate valuation, or an expert assumption that…
|
|
| 6 Jun 2007 |
[2007] EWHC 1620 (TCC)
In an unusually complex administration, the court may extend statutory deadlines where necessary to balance orderly administration, proportionality and the…
|
|
| 1 Jun 2007 |
[2007] EWHC 1364 (TCC)
A late amendment should generally be allowed where it permits the real dispute to be determined, provided resulting prejudice can be compensated in costs and…
|
|
| 31 May 2007 |
[2007] EWHC 1375 (TCC)
A construction contract need not comprise a single document or encompass every agreement between the parties. Where the parties have made separate contracts…
|
|
| 31 May 2007 |
[2007] EWHC 1360 (TCC)
An adjudicator’s decision under the Housing Grants, Construction and Regeneration Act 1996 and the Scheme for Construction Contracts must be completed within…
|
5 |
| 25 May 2007 |
[2007] EWHC 1318 (TCC)
Under contractual building guarantee rules, sums are recoverable on demand only if they are sums for which the developer is liable under the scheme. Liability…
|
|
| 24 May 2007 |
[2007] EWHC 1289 (TCC)
A repairing covenant does not generally require a tenant to provide perfect or pristine premises. Where more than one scheme would satisfy the covenant, the…
|
|
| 23 May 2007 |
[2007] EWHC 1055 (TCC)
A construction contract may be enforceable without being sufficiently documented to support statutory adjudication. Under section 107 of the Housing Grants…
|
4 |
| 22 May 2007 |
[2007] EWHC 2018 (TCC)
Leave to appeal an arbitral award under Arbitration Act 1996, section 69, requires an identifiable question of law which the tribunal was asked to determine.…
|
1 |
| 17 May 2007 |
[2007] EWHC 1296 (TCC)
A claimant seeking to use the adjudication provisions of the Housing Grants, Construction and Regeneration Act 1996 must establish both a construction contract…
|
|
| 14 May 2007 |
[2007] EWHC 1262 (TCC)
The High Court may restrain an arbitration under section 37 of the Supreme Court Act 1981, but only where the injunction would not cause injustice to the…
|
1 |
| 11 May 2007 |
[2007] EWHC 1187 (TCC)
Permission to appeal an arbitration award under section 69 of the Arbitration Act 1996 requires a true question of law, an obviously wrong decision (or a…
|
2 |
| 4 May 2007 |
[2007] EWHC 1174 (TCC)
In a construction contract with a residential occupier, contractual adjudication provisions may operate even though Part II of the Housing Grants, Construction…
|
3 |
| 4 May 2007 |
[2007] EWHC 1039 (TCC)
In assessing costs, the court must identify the successful party by substance and reality. Costs generally follow the event, but the court retains a discretion…
|
|
| 3 May 2007 |
[2007] EWHC 1129 (TCC)
A construction contract may arise where the documents identify the parties, work scope and price, and objectively show an intention to create legal relations.…
|
|
| 20 Apr 2007 |
[2007] EWHC 918 (TCC)
Damages for breach of contract and negligence must be caused by the defendant’s wrongdoing and must not arise from an independent cause. Where concurrent…
|
1 |
| 4 Apr 2007 |
[2007] EWHC 857 (TCC)
For the purposes of Article 5(3) of Regulation 44/2001, “matters relating to tort, delict or quasi-delict” is an autonomous European-law concept wider than…
|
|
| 4 Apr 2007 |
[2007] EWHC 856 (TCC)
An application under section 68 of the Arbitration Act 1996 is a longstop remedy. It cannot be used to appeal an arbitrator’s factual assessment or to…
|
1 |
| 4 Apr 2007 |
[2007] EWHC 728 (TCC)
A claimant may recover losses caused by negligent delay in completing contracted works, including reasonable consequential expenditure and loss of profit…
|
3 |
| 3 Apr 2007 |
[2007] EWHC 752 (TCC)
Contractual exclusion clauses require clear words before removing common-law rights or remedies. A warranty preserving rights provided by law may coexist with…
|
1 |
| 2 Apr 2007 |
[2007] EWHC 912 (TCC)
A conventional reasonable-precautions clause in a liability or property insurance policy is not breached by mere negligence. The required standard is…
|
1 |
| 30 Mar 2007 |
[2007] EWHC 1058 (TCC)
An engineer retained for permanent works must take reasonable steps to address a dangerous condition in temporary works where he observes that condition and it…
|
1 |
| 28 Mar 2007 |
[2007] EWHC 698 (TCC)
The court has a broad discretion over costs under CPR 44.3, guided by the overriding objective. A claimant who fails against both defendants will ordinarily…
|
4 |
| 26 Mar 2007 |
[2007] EWHC 1408 (TCC)
An adjudication cannot validly begin unless the adjudication notice is effectively served in accordance with the applicable statutory service provision.…
|
|
| 23 Mar 2007 |
[2007] EWHC 855 (TCC)
Failure to comply with a construction pre-action protocol can justify an early costs order where the breach caused proceedings or litigation costs that might…
|
3 |
| 22 Mar 2007 |
[2007] EWHC 626 (TCC)
A costs order against a non-party funder under section 51 requires a causal link between the funding and costs incurred by the applicant. If those costs would…
|
4 |
| 20 Mar 2007 |
[2007] EWHC 805 (TCC)
Under section 35A of the Supreme Court Act 1981, interest on a restitutionary quantum meruit claim for building work should not necessarily run from handover.…
|
23 |
| 15 Mar 2007 |
[2007] EWHC 1626 (TCC)
Parties may confer or widen an adjudicator’s jurisdiction by agreement, including through their pleadings and conduct. A party that advances substantial…
|
|
| 12 Mar 2007 |
[2007] EWHC 659 (TCC)
After a successful party wins a preliminary issue, the court may make an immediate costs order even though the litigation continues. The usual approach is to…
|
4 |
| 6 Mar 2007 |
[2007] EWHC 447 (TCC)
Legitimate contractual instructions may amount to acts of prevention if they delay completion beyond the contractual date. They do not set time at large where…
|
7 |
| 27 Feb 2007 |
[2007] EWHC 390 (TCC)
A contractual inspection clause forming part of an operative appendix may confer a continuing right to inspect the current version of a linked construction…
|
|
| 22 Feb 2007 |
[2007] EWHC 294 (TCC)
Where separate categories of claim are tried separately, a successful party may receive the costs of a distinct category which it has wholly defeated, even…
|
|
| 21 Feb 2007 |
[2007] EWHC 149 (TCC)
In a construction defects claim, professional liability is governed by the services actually undertaken, not every function normally associated with the…
|
14 |
| 20 Feb 2007 |
[2007] EWHC 271 (TCC)
A settlement is not binding merely because the parties have agreed a headline figure. The court must construe the communications objectively against their…
|
|
| 16 Feb 2007 |
[2007] EWHC 336 (TCC)
On an application for security for costs concerning a counterclaim, the court must first decide whether the counterclaim is a genuine independent claim or…
|
2 |
| 15 Feb 2007 |
[2007] EWHC 361 (TCC)
Words such as “flood” and “burst” in an insurance policy or related construction contract do not have fixed meanings applicable in every context. Their meaning…
|
3 |
| 15 Feb 2007 |
[2007] EWHC 306 (TCC)
Where a court orders payment by a stated deadline but prescribes no payment method, payment by cheque may satisfy the order if the creditor accepts the cheque…
|
|
| 15 Feb 2007 |
[2007] EWHC 305 (TCC)
Where parties orally agree that liquidated and ascertained damages will not apply, the court must determine objectively whether they intended to preserve a…
|
|
| 14 Feb 2007 |
[2007] EWHC 323 (TCC)
On an application under CPR 31.19 to challenge redactions or claims to privilege, the court should proceed principally on the evidence. If the asserted right…
|
8 |
| 9 Feb 2007 |
[2007] EWHC 318 (TCC)
Enforcement of an arbitral award under Arbitration Act 1996 section 66 is discretionary, but a detailed re-analysis of the arbitrator’s reasoning is…
|
|
| 9 Feb 2007 |
[2007] EWHC 291 (TCC)
On an application for security for costs against a company’s counterclaim, the statutory condition that the company may be unable to pay costs does not itself…
|
|
| 8 Feb 2007 |
[2007] EWHC 236 (TCC)
A first-instance court retains jurisdiction over a judgment until the order giving effect to it has been drawn up and sealed. That jurisdiction may include…
|
3 |
| 1 Feb 2007 |
[2007] EWHC 144 (TCC)
An adjudicator’s decision binds the parties until final determination or subsequent agreement. A party cannot obtain a further adjudication of the same or…
|
10 |
| 1 Feb 2007 |
[2007] EWHC 131 (TCC)
A contractual adjudication procedure that fails to comply with the statutory requirements is displaced by the adjudication provisions of the Scheme for…
|
3 |
| 31 Jan 2007 |
[2007] EWHC 93 (TCC)
For limitation purposes, an amendment does not add a new claim merely because it corrects the identity of a contractual document. The court must identify the…
|
|
| 31 Jan 2007 |
[2007] EWHC 145 (TCC)
Contractual responsibility for temporary works depends on construing the agreement as a whole in its commercial and factual context. Where schedules are…
|
1 |
| 26 Jan 2007 |
[2007] EWHC 70 (TCC)
A contractual limitation clause may be incorporated where the relevant document gives reasonable notice that contractual conditions apply. An unusually onerous…
|
|
| 19 Jan 2007 |
[2007] EWHC 49 (TCC)
A letter of intent headed subject to contract does not necessarily prevent contractual liability, but the question is one of construction. Where the…
|
1 |
| 19 Jan 2007 |
[2007] EWHC 4 (TCC)
An adjudicator’s decision is reached when the adjudicator has completed it, but the time for reaching it may be contractually extended on conditions agreed by…
|
3 |
| 15 Jan 2007 |
[2007] EWHC 55 (TCC)
A later claim may constitute an abuse of process even where it is brought against defendants who were not directly sued in the earlier proceedings. The court…
|
|
| 10 Jan 2007 |
[2007] EWHC 20 (TCC)
An adjudicator’s jurisdiction is confined by the scope of the pre-existing dispute. The referring party cannot enlarge that jurisdiction merely by drafting a…
|