High Court: Technology and Construction Court judgments, 2006

87 judgments, newest first. Open any case for its summary, the legal points it decides and how later courts have treated it.

Date Case Cited by
23 Feb 2007
[2006] EWHC 567 (TCC)
A certificate of lawful use issued under section 191 of the Town and Country Planning Act 1990 conclusively establishes the lawfulness of the certified use. A…
21 Dec 2006
[2006] EWHC 3413 (TCC)
Where a construction contract contains adjudication provisions complying with the Housing Grants Construction and Regeneration Act 1996, the express…
14
19 Dec 2006
[2006] EWHC 3426 (TCC)
Where a contract provides that labour time runs from leaving the depot until returning to it, that wording may include travelling time, working time and meal…
18 Dec 2006
[2006] EWHC 3252 (TCC)
On an application for a non-party costs order against professional indemnity insurers, the court may exercise its discretion under Supreme Court Act 1981…
15 Dec 2006
[2006] EWHC 3573 (TCC)
In adjudication enforcement proceedings, a court will not summarily enforce an award where it is reasonably arguable that the claimant was not a party entitled…
3
12 Dec 2006
[2006] EWHC 3635 (TCC)
A supplier is liable where goods fail to comply with an express description, are of unsatisfactory quality, or are not reasonably fit for their purpose. Civil…
8 Dec 2006
[2006] EWHC 3240 (TCC)
An application to set aside summary judgment must be made promptly and must be supported by a good explanation for the earlier non-attendance. The court may…
1
5 Dec 2006
[2006] EWHC 3158 (TCC)
After expiry of the limitation period, the court may permit a new cause of action to be added where it arises out of the same or substantially the same facts…
4
30 Nov 2006
[2006] EWHC 3119 (TCC)
A contractor’s inability to continue work, caused by the lapse of essential insurance and imminent insolvency, may amount to repudiation. The employer may…
1
22 Nov 2006
[2006] EWHC 3003 (TCC)
Permission to appeal an arbitral award under Arbitration Act 1996, section 69, requires a genuine question of law, substantial effect on the parties’ rights…
17 Nov 2006
[2006] EWHC 3156 (TCC)
A contractual time bar may operate in addition to statutory limitation. It cannot extend the period available under the Limitation Act 1980 or redefine when a…
2
17 Nov 2006
[2006] EWHC 2924 (TCC)
A refusal to mediate may be unreasonable even where parties have exchanged settlement offers and one party considers its case strong. The court should assess…
14 Nov 2006
[2006] EWHC 3637 (TCC)
A determination of a building contract’s Final Account does not necessarily make the balance immediately payable. Where a supplemental agreement fixes only the…
5
13 Nov 2006
[2006] EWHC 2909 (TCC)
After expiry of limitation, an amendment adding a new duty or cause of action may be allowed only where the new claim arises from the same or substantially the…
5
8 Nov 2006
[2006] EWHC 2877 (TCC)
In a design and build contract, the contractor’s obligation to complete the works ordinarily includes the detailed design needed to particularise and complete…
7 Nov 2006
[2006] EWHC 3636 (TCC)
An agent who contracts for a principal remains personally liable unless the contract and surrounding circumstances show that personal liability was expressly…
7 Nov 2006
[2006] EWHC 2794 (TCC)
In enforcing an adjudicator’s award, the court should adopt a rigorous and commonsense approach to whether a dispute has arisen. It should examine the…
3 Nov 2006
[2006] EWHC 2857 (TCC)
Service by fax is effective only where the recipient has previously indicated in writing a willingness to accept electronic service. A fax number on a…
14
1 Nov 2006
[2006] EWHC 3622 (TCC)
For a freezing injunction, the claimant must show both a good arguable case and a real risk that a judgment will remain unsatisfied because of asset…
2
27 Oct 2006
[2006] EWHC 2678 (TCC)
A contractual right to modify development plans or substitute materials is limited by the wording of the contract. The developer must use every endeavour to…
2
27 Oct 2006
[2006] EWHC 2640 (TCC)
Incorporation of standard terms requires reasonable notice of the conditions before contract formation. A reference to conditions on the reverse of a fax…
25 Oct 2006
[2006] EWHC 2656 (TCC)
Commercial agreements should be construed, where possible, to preserve rather than defeat the bargain. Once an agreement has come into existence and the…
23 Oct 2006
[2006] EWHC 2756 (TCC)
For non-party disclosure, the threshold in CPR rule 31.17(3)(a) is satisfied where the documents may well support the applicant’s case or adversely affect…
1
13 Oct 2006
[2006] EWHC 2567 (TCC)
A contract is not a sham merely because it is disadvantageous, artificial, later varied, or subsequently operated imperfectly. The question is whether all…
12 Oct 2006
[2006] EWHC 2518 (TCC)
An adjudicator’s decision under a construction contract should generally be enforced pending final determination, even where one party is alleged to have…
11 Oct 2006
[2006] EWHC 2520 (TCC)
Adjudication decisions should ordinarily be enforced unless it is plain that the adjudicator decided a question outside the reference or acted in an obviously…
4
3 Oct 2006
[2006] EWHC 2551 (TCC)
A supplemental agreement which varies the contract price and completion dates, identifies settled and unsettled matters, and remains intertwined with the…
4
26 Sep 2006
[2006] EWHC 2331 (TCC)
For the exemption in section 198(6)(b) of the Town and Country Planning Act 1990 to apply, the nuisance must be actionable, involving actual or imminent damage…
22 Sep 2006
[2006] EWHC 3634 (TCC)
A claimant assembling manufactured components is not liable for alleged product failures unless the defendant proves both the probable mechanism of failure and…
19 Sep 2006
[2006] EWHC 2338 (TCC)
A court-ordered expert statement is ordinarily open and may be used in subsequent proceedings, even if it is also used in mediation. The position changes where…
15 Sep 2006
[2006] EWHC 2322 (TCC)
Under CPR 32.3, the court has a broad discretion to permit evidence by video link. Physical attendance is generally preferable, but the court must assess…
1
8 Sep 2006
[2006] EWHC 2481 (TCC)
Contractual design obligations must be construed objectively from the language used, read with the relevant technical background, surrounding circumstances and…
1
31 Jul 2006
[2006] EWHC 2080 (TCC)
Adjudicators’ decisions under the Housing Grants Construction and Regeneration Act 1996 are ordinarily enforced summarily and on a provisional basis. A party…
2
31 Jul 2006
[2006] EWHC 1994 (TCC)
A construction contract falls within the statutory adjudication regime only if the agreement, including terms material to the dispute, is evidenced in writing.…
1
28 Jul 2006
[2006] EWHC 2014 (TCC)
A settlement offer which includes a term concerning costs is not a valid Part 36 offer. The court may nevertheless exercise its discretion under Civil…
17 Jul 2006
[2006] EWHC 1810 (TCC)
In exercising the costs discretion under Civil Procedure Rules 1998, r 44.3, the court must consider all the circumstances, including conduct, partial success…
13 Jul 2006
[2006] EWHC 1913 (TCC)
An engineer retained to merge an architect’s layout with a survey plan must follow that brief and has little discretion to make material changes. Changes…
13 Jul 2006
[2006] EWHC 1771 (TCC)
A letter of intent may be an appropriate means of commencing construction works before execution of the full contract. Its suitability depends on whether the…
1
10 Jul 2006
[2006] EWHC 1720 (TCC)
For the purposes of section 107 of the Housing Grants, Construction and Regeneration Act 1996, oral instructions given under an existing written construction…
7 Jul 2006
[2006] EWHC 1708 (TCC)
A court which made a charging order has jurisdiction to order sale under CPR 73.10, even where a practice direction allocates such claims to another Division.…
4
6 Jul 2006
[2006] EWHC 1597 (TCC)
A court may use its broad costs discretion under CPR 44.3 to require a party whose disclosure breach caused another party reasonably to incur costs to…
3 Jul 2006
[2006] EWHC 1693 (TCC)
Under section 45 of the Arbitration Act 1996, the court retains a discretion to determine a question of law arising during arbitration, even where the parties…
1
29 Jun 2006
[2006] EWHC 1628 (TCC)
Costs of preliminary issues should ordinarily be reserved where the final accounting, damages or other unresolved matters may materially affect which party was…
3
29 Jun 2006
[2006] EWHC 1586 (TCC)
A binding contract may arise where an offer is accepted by conduct which clearly communicates acceptance, including payment made in the manner requested by the…
23 Jun 2006
[2006] EWHC 1187 (TCC)
A contractual fitness-for-purpose obligation requires the completed works to be capable of performing their specified function without an unacceptable risk of…
22 Jun 2006
[2006] EWHC 1411 (TCC)
In tree-root subsidence claims, the claimant must prove on the balance of probabilities that the defendant’s breach caused or materially contributed to the…
4
13 Jun 2006
[2006] EWHC 1505 (TCC)
An adjudication challenge brought within the contractual time limit is ordinarily concerned with the adjudicator’s final decision, not an interim ruling made…
8 Jun 2006
[2006] EWHC 1569 (TCC)
Enforcement of an adjudicator’s decision is the ordinary course. The court should interfere only where it is plain that the adjudicator decided a question not…
2
8 Jun 2006
[2006] EWHC 1363 (TCC)
An unsuccessful claim does not, by itself, justify indemnity costs. The court must assess all the circumstances, including admissible settlement offers and the…
8 Jun 2006
[2006] EWHC 1325 (TCC)
A contractual exclusion of liability for property damage may encompass claims framed in contract as well as tort. Where liability is preserved for damage that…
7 Jun 2006
[2006] EWHC 1365 (TCC)
Adjudication awards in construction disputes are ordinarily enforceable immediately, even where the losing party has a separate claim which may later require…
5
5 Jun 2006
[2006] EWHC 1341 (TCC)
A later formal agreement may retrospectively supersede an earlier preliminary agreement where that is the parties’ intention. An obligation to use reasonable…
8
5 Jun 2006
[2006] EWHC 1299 (TCC)
An occupier may owe a duty of care to neighbouring property owners where combustible material creates an obvious and significant risk that third parties may…
22 May 2006
[2006] EWHC 1222 (TCC)
Applications to amend pleadings on the first day of trial require a structured and proportionate balancing exercise. The court should consider the prejudice to…
22 May 2006
[2006] EWHC 1094 (TCC)
An alleged construction cost ceiling is unenforceable where the scope of the works, pricing basis and remedial obligations are insufficiently defined. A…
18 May 2006
[2006] EWHC 1185 (TCC)
Where a claimant fails to beat a Civil Procedure Rules 1998 Part 36 offer or payment into court, the usual costs consequence is that the claimant pays the…
2
18 May 2006
[2006] EWHC 1120 (TCC)
Under a reinstatement insurance policy, the insured must identify clearly whether proposed works reproduce the pre-loss building or include improvements.…
3
11 May 2006
[2006] EWHC 2133 (TCC)
A compromise is construed from the words used by the parties in their proper context. Subjective intentions are irrelevant. Wording such as all claims made…
2 May 2006
[2006] EWHC 1258 (TCC)
Pre-action disclosure in construction litigation requires a fact-sensitive assessment under CPR rule 31.16. The applicant must first show a real prospect that…
4
28 Apr 2006
[2006] EWHC 947 (TCC)
An interim contract incorporating terms from a draft agreement incorporates only those terms necessary to define the services, where the wider draft terms…
29 Mar 2006
[2006] EWHC 687 (TCC)
Letters of intent have no fixed legal effect. Their meaning depends on the wording and circumstances. They may create binding contracts for limited work…
1
23 Mar 2006
[2006] EWHC 633 (TCC)
An application for committal for breach of a court undertaking is quasi-criminal. The breach must be proved beyond reasonable doubt, and the undertaking must…
22 Mar 2006
[2006] EWHC 721 (TCC)
Specific disclosure must be confined to documents relevant to pleaded issues and proportionate to the needs of the case. A party may be required to provide…
1
20 Mar 2006
[2006] EWHC 814 (TCC)
A default judgment should be set aside under CPR 13.3 where the defendant has a real prospect of successfully defending the claim and, having regard to all the…
2
20 Mar 2006
[2006] EWHC 761 (TCC)
An adjudicator’s decision under the Housing Grants, Construction and Regeneration Act 1996 is binding and should ordinarily be enforced on an interim basis. A…
10
15 Mar 2006
[2006] EWHC 536 (TCC)
Where a reserved judgment has been sent to the parties before settlement, the court retains a discretion whether to publish it. That discretion exists to…
3
15 Mar 2006
[2006] EWHC 535 (TCC)
An adjudicator’s decision is intended to produce a prompt result with which the parties must comply, even though it may later be revised in arbitration.…
2
9 Mar 2006
[2006] EWHC 3594 (TCC)
Under Arbitration Act 1996, the words “final and binding” do not, by themselves, exclude an appeal on a question of law. The court must construe the parties’…
1
8 Mar 2006
[2006] EWHC 591 (TCC)
Economic duress requires pressure which compels the claimant or removes practical choice, is illegitimate, and significantly induces the contract. Commercial…
6 Mar 2006
[2006] EWHC 848 (TCC)
An adjudicator’s decision should generally be enforced despite an error of law or an arguable failure to consider evidence, provided that the adjudicator…
7
2 Mar 2006
[2006] EWHC 727 (TCC)
On an agreed appeal under section 69(2)(a) of the Arbitration Act 1996, the court must decide genuine questions of law correctly; the Act’s policy of…
20
24 Feb 2006
[2006] EWHC 348 (TCC)
A claimed purchaser’s lien over registered land may be protected by a unilateral notice before the lien has been adjudicated. The court nevertheless retains…
21 Feb 2006
[2006] EWHC 257 (TCC)
Unless Orders are exceptional and should not be imposed routinely for every failure to comply with an earlier order. They are generally appropriate only where…
9 Feb 2006
[2006] EWHC 148 (TCC)
Summary assessment on the standard basis requires a two-stage approach. The court must first decide whether the costs as a whole are disproportionate, having…
6 Feb 2006
[2006] EWHC 741 (TCC)
Adjudication decisions under the Housing Grants, Construction and Regeneration Act 1996 are intended to secure immediate cash flow. Subject to special…
11
2 Feb 2006
[2006] EWHC 174 (TCC)
Successive adjudications concerning extensions of time are permissible where they arise from separate disputes based on different grounds. A contractor may…
3
2 Feb 2006
[2006] EWHC 126 (TCC)
Costs remain a matter of judicial discretion. The starting point is that costs follow the event, but the court must consider all the circumstances, including…
27 Jan 2006
[2006] EWHC 71 (TCC)
In adjudication enforcement proceedings, the court should enforce an adjudicator’s decision unless the adjudicator decided a matter outside the referral or…
25 Jan 2006
[2006] EWHC 43 (TCC)
Under Civil Procedure Rules 1998, a party may use an expert report disclosed by another party where that report was disclosed with permission under CPR 35.4.…
5
23 Jan 2006
[2006] EWHC 6 (TCC)
A professional services contract may impose enforceable obligations as to time in addition to the duty to exercise reasonable skill and care. The obligation is…
20 Jan 2006
[2006] EWHC 31 (TCC)
A settlement offer marked “without prejudice save as to costs” may be admitted to determine whether it was accepted and created a binding compromise. The court…
19 Jan 2006
[2006] EWHC 66 (TCC)
A statutory water undertaker may use an assumed volume to calculate sewerage charges, but its statutory power extends only to services actually provided. A…
16 Jan 2006
[2006] EWHC 89 (TCC)
A construction manager may perform both an agency function for the employer and a decision-making function affecting the parties’ competing interests. When…
5
16 Jan 2006
[2006] EWHC 54 (TCC)
An adjudicator’s decision should ordinarily be enforced by prompt enforcement proceedings in the Technology and Construction Court. A party cannot generally…
10 Jan 2006
[2006] EWHC 5 (TCC)
An architect advising on a complex construction project must give clear, timely and sufficiently detailed advice about design decisions, procurement…
10 Jan 2006
[2006] EWHC 15 (TCC)
On an application to enforce an adjudicator’s decision, summary judgment may be given where the proposed defence has no real prospect of success. The court…
2
6 Jan 2006
[2006] EWHC 29 (TCC)
In determining costs, the court must identify the successful party by assessing the litigation as a whole, while considering partial success, conduct…
1