| Date | Case | Cited by |
|---|---|---|
| 23 Feb 2007 |
[2006] EWHC 567 (TCC)
A certificate of lawful use issued under section 191 of the Town and Country Planning Act 1990 conclusively establishes the lawfulness of the certified use. A…
|
|
| 21 Dec 2006 |
[2006] EWHC 3413 (TCC)
Where a construction contract contains adjudication provisions complying with the Housing Grants Construction and Regeneration Act 1996, the express…
|
14 |
| 19 Dec 2006 |
[2006] EWHC 3426 (TCC)
Where a contract provides that labour time runs from leaving the depot until returning to it, that wording may include travelling time, working time and meal…
|
|
| 18 Dec 2006 |
[2006] EWHC 3252 (TCC)
On an application for a non-party costs order against professional indemnity insurers, the court may exercise its discretion under Supreme Court Act 1981…
|
|
| 15 Dec 2006 |
[2006] EWHC 3573 (TCC)
In adjudication enforcement proceedings, a court will not summarily enforce an award where it is reasonably arguable that the claimant was not a party entitled…
|
3 |
| 12 Dec 2006 |
[2006] EWHC 3635 (TCC)
A supplier is liable where goods fail to comply with an express description, are of unsatisfactory quality, or are not reasonably fit for their purpose. Civil…
|
|
| 8 Dec 2006 |
[2006] EWHC 3240 (TCC)
An application to set aside summary judgment must be made promptly and must be supported by a good explanation for the earlier non-attendance. The court may…
|
1 |
| 5 Dec 2006 |
[2006] EWHC 3158 (TCC)
After expiry of the limitation period, the court may permit a new cause of action to be added where it arises out of the same or substantially the same facts…
|
4 |
| 30 Nov 2006 |
[2006] EWHC 3119 (TCC)
A contractor’s inability to continue work, caused by the lapse of essential insurance and imminent insolvency, may amount to repudiation. The employer may…
|
1 |
| 22 Nov 2006 |
[2006] EWHC 3003 (TCC)
Permission to appeal an arbitral award under Arbitration Act 1996, section 69, requires a genuine question of law, substantial effect on the parties’ rights…
|
|
| 17 Nov 2006 |
[2006] EWHC 3156 (TCC)
A contractual time bar may operate in addition to statutory limitation. It cannot extend the period available under the Limitation Act 1980 or redefine when a…
|
2 |
| 17 Nov 2006 |
[2006] EWHC 2924 (TCC)
A refusal to mediate may be unreasonable even where parties have exchanged settlement offers and one party considers its case strong. The court should assess…
|
|
| 14 Nov 2006 |
[2006] EWHC 3637 (TCC)
A determination of a building contract’s Final Account does not necessarily make the balance immediately payable. Where a supplemental agreement fixes only the…
|
5 |
| 13 Nov 2006 |
[2006] EWHC 2909 (TCC)
After expiry of limitation, an amendment adding a new duty or cause of action may be allowed only where the new claim arises from the same or substantially the…
|
5 |
| 8 Nov 2006 |
[2006] EWHC 2877 (TCC)
In a design and build contract, the contractor’s obligation to complete the works ordinarily includes the detailed design needed to particularise and complete…
|
|
| 7 Nov 2006 |
[2006] EWHC 3636 (TCC)
An agent who contracts for a principal remains personally liable unless the contract and surrounding circumstances show that personal liability was expressly…
|
|
| 7 Nov 2006 |
[2006] EWHC 2794 (TCC)
In enforcing an adjudicator’s award, the court should adopt a rigorous and commonsense approach to whether a dispute has arisen. It should examine the…
|
|
| 3 Nov 2006 |
[2006] EWHC 2857 (TCC)
Service by fax is effective only where the recipient has previously indicated in writing a willingness to accept electronic service. A fax number on a…
|
14 |
| 1 Nov 2006 |
[2006] EWHC 3622 (TCC)
For a freezing injunction, the claimant must show both a good arguable case and a real risk that a judgment will remain unsatisfied because of asset…
|
2 |
| 27 Oct 2006 |
[2006] EWHC 2678 (TCC)
A contractual right to modify development plans or substitute materials is limited by the wording of the contract. The developer must use every endeavour to…
|
2 |
| 27 Oct 2006 |
[2006] EWHC 2640 (TCC)
Incorporation of standard terms requires reasonable notice of the conditions before contract formation. A reference to conditions on the reverse of a fax…
|
|
| 25 Oct 2006 |
[2006] EWHC 2656 (TCC)
Commercial agreements should be construed, where possible, to preserve rather than defeat the bargain. Once an agreement has come into existence and the…
|
|
| 23 Oct 2006 |
[2006] EWHC 2756 (TCC)
For non-party disclosure, the threshold in CPR rule 31.17(3)(a) is satisfied where the documents may well support the applicant’s case or adversely affect…
|
1 |
| 13 Oct 2006 |
[2006] EWHC 2567 (TCC)
A contract is not a sham merely because it is disadvantageous, artificial, later varied, or subsequently operated imperfectly. The question is whether all…
|
|
| 12 Oct 2006 |
[2006] EWHC 2518 (TCC)
An adjudicator’s decision under a construction contract should generally be enforced pending final determination, even where one party is alleged to have…
|
|
| 11 Oct 2006 |
[2006] EWHC 2520 (TCC)
Adjudication decisions should ordinarily be enforced unless it is plain that the adjudicator decided a question outside the reference or acted in an obviously…
|
4 |
| 3 Oct 2006 |
[2006] EWHC 2551 (TCC)
A supplemental agreement which varies the contract price and completion dates, identifies settled and unsettled matters, and remains intertwined with the…
|
4 |
| 26 Sep 2006 |
[2006] EWHC 2331 (TCC)
For the exemption in section 198(6)(b) of the Town and Country Planning Act 1990 to apply, the nuisance must be actionable, involving actual or imminent damage…
|
|
| 22 Sep 2006 |
[2006] EWHC 3634 (TCC)
A claimant assembling manufactured components is not liable for alleged product failures unless the defendant proves both the probable mechanism of failure and…
|
|
| 19 Sep 2006 |
[2006] EWHC 2338 (TCC)
A court-ordered expert statement is ordinarily open and may be used in subsequent proceedings, even if it is also used in mediation. The position changes where…
|
|
| 15 Sep 2006 |
[2006] EWHC 2322 (TCC)
Under CPR 32.3, the court has a broad discretion to permit evidence by video link. Physical attendance is generally preferable, but the court must assess…
|
1 |
| 8 Sep 2006 |
[2006] EWHC 2481 (TCC)
Contractual design obligations must be construed objectively from the language used, read with the relevant technical background, surrounding circumstances and…
|
1 |
| 31 Jul 2006 |
[2006] EWHC 2080 (TCC)
Adjudicators’ decisions under the Housing Grants Construction and Regeneration Act 1996 are ordinarily enforced summarily and on a provisional basis. A party…
|
2 |
| 31 Jul 2006 |
[2006] EWHC 1994 (TCC)
A construction contract falls within the statutory adjudication regime only if the agreement, including terms material to the dispute, is evidenced in writing.…
|
1 |
| 28 Jul 2006 |
[2006] EWHC 2014 (TCC)
A settlement offer which includes a term concerning costs is not a valid Part 36 offer. The court may nevertheless exercise its discretion under Civil…
|
|
| 17 Jul 2006 |
[2006] EWHC 1810 (TCC)
In exercising the costs discretion under Civil Procedure Rules 1998, r 44.3, the court must consider all the circumstances, including conduct, partial success…
|
|
| 13 Jul 2006 |
[2006] EWHC 1913 (TCC)
An engineer retained to merge an architect’s layout with a survey plan must follow that brief and has little discretion to make material changes. Changes…
|
|
| 13 Jul 2006 |
[2006] EWHC 1771 (TCC)
A letter of intent may be an appropriate means of commencing construction works before execution of the full contract. Its suitability depends on whether the…
|
1 |
| 10 Jul 2006 |
[2006] EWHC 1720 (TCC)
For the purposes of section 107 of the Housing Grants, Construction and Regeneration Act 1996, oral instructions given under an existing written construction…
|
|
| 7 Jul 2006 |
[2006] EWHC 1708 (TCC)
A court which made a charging order has jurisdiction to order sale under CPR 73.10, even where a practice direction allocates such claims to another Division.…
|
4 |
| 6 Jul 2006 |
[2006] EWHC 1597 (TCC)
A court may use its broad costs discretion under CPR 44.3 to require a party whose disclosure breach caused another party reasonably to incur costs to…
|
|
| 3 Jul 2006 |
[2006] EWHC 1693 (TCC)
Under section 45 of the Arbitration Act 1996, the court retains a discretion to determine a question of law arising during arbitration, even where the parties…
|
1 |
| 29 Jun 2006 |
[2006] EWHC 1628 (TCC)
Costs of preliminary issues should ordinarily be reserved where the final accounting, damages or other unresolved matters may materially affect which party was…
|
3 |
| 29 Jun 2006 |
[2006] EWHC 1586 (TCC)
A binding contract may arise where an offer is accepted by conduct which clearly communicates acceptance, including payment made in the manner requested by the…
|
|
| 23 Jun 2006 |
[2006] EWHC 1187 (TCC)
A contractual fitness-for-purpose obligation requires the completed works to be capable of performing their specified function without an unacceptable risk of…
|
|
| 22 Jun 2006 |
[2006] EWHC 1411 (TCC)
In tree-root subsidence claims, the claimant must prove on the balance of probabilities that the defendant’s breach caused or materially contributed to the…
|
4 |
| 13 Jun 2006 |
[2006] EWHC 1505 (TCC)
An adjudication challenge brought within the contractual time limit is ordinarily concerned with the adjudicator’s final decision, not an interim ruling made…
|
|
| 8 Jun 2006 |
[2006] EWHC 1569 (TCC)
Enforcement of an adjudicator’s decision is the ordinary course. The court should interfere only where it is plain that the adjudicator decided a question not…
|
2 |
| 8 Jun 2006 |
[2006] EWHC 1363 (TCC)
An unsuccessful claim does not, by itself, justify indemnity costs. The court must assess all the circumstances, including admissible settlement offers and the…
|
|
| 8 Jun 2006 |
[2006] EWHC 1325 (TCC)
A contractual exclusion of liability for property damage may encompass claims framed in contract as well as tort. Where liability is preserved for damage that…
|
|
| 7 Jun 2006 |
[2006] EWHC 1365 (TCC)
Adjudication awards in construction disputes are ordinarily enforceable immediately, even where the losing party has a separate claim which may later require…
|
5 |
| 5 Jun 2006 |
[2006] EWHC 1341 (TCC)
A later formal agreement may retrospectively supersede an earlier preliminary agreement where that is the parties’ intention. An obligation to use reasonable…
|
8 |
| 5 Jun 2006 |
[2006] EWHC 1299 (TCC)
An occupier may owe a duty of care to neighbouring property owners where combustible material creates an obvious and significant risk that third parties may…
|
|
| 22 May 2006 |
[2006] EWHC 1222 (TCC)
Applications to amend pleadings on the first day of trial require a structured and proportionate balancing exercise. The court should consider the prejudice to…
|
|
| 22 May 2006 |
[2006] EWHC 1094 (TCC)
An alleged construction cost ceiling is unenforceable where the scope of the works, pricing basis and remedial obligations are insufficiently defined. A…
|
|
| 18 May 2006 |
[2006] EWHC 1185 (TCC)
Where a claimant fails to beat a Civil Procedure Rules 1998 Part 36 offer or payment into court, the usual costs consequence is that the claimant pays the…
|
2 |
| 18 May 2006 |
[2006] EWHC 1120 (TCC)
Under a reinstatement insurance policy, the insured must identify clearly whether proposed works reproduce the pre-loss building or include improvements.…
|
3 |
| 11 May 2006 |
[2006] EWHC 2133 (TCC)
A compromise is construed from the words used by the parties in their proper context. Subjective intentions are irrelevant. Wording such as all claims made…
|
|
| 2 May 2006 |
[2006] EWHC 1258 (TCC)
Pre-action disclosure in construction litigation requires a fact-sensitive assessment under CPR rule 31.16. The applicant must first show a real prospect that…
|
4 |
| 28 Apr 2006 |
[2006] EWHC 947 (TCC)
An interim contract incorporating terms from a draft agreement incorporates only those terms necessary to define the services, where the wider draft terms…
|
|
| 29 Mar 2006 |
[2006] EWHC 687 (TCC)
Letters of intent have no fixed legal effect. Their meaning depends on the wording and circumstances. They may create binding contracts for limited work…
|
1 |
| 23 Mar 2006 |
[2006] EWHC 633 (TCC)
An application for committal for breach of a court undertaking is quasi-criminal. The breach must be proved beyond reasonable doubt, and the undertaking must…
|
|
| 22 Mar 2006 |
[2006] EWHC 721 (TCC)
Specific disclosure must be confined to documents relevant to pleaded issues and proportionate to the needs of the case. A party may be required to provide…
|
1 |
| 20 Mar 2006 |
[2006] EWHC 814 (TCC)
A default judgment should be set aside under CPR 13.3 where the defendant has a real prospect of successfully defending the claim and, having regard to all the…
|
2 |
| 20 Mar 2006 |
[2006] EWHC 761 (TCC)
An adjudicator’s decision under the Housing Grants, Construction and Regeneration Act 1996 is binding and should ordinarily be enforced on an interim basis. A…
|
10 |
| 15 Mar 2006 |
[2006] EWHC 536 (TCC)
Where a reserved judgment has been sent to the parties before settlement, the court retains a discretion whether to publish it. That discretion exists to…
|
3 |
| 15 Mar 2006 |
[2006] EWHC 535 (TCC)
An adjudicator’s decision is intended to produce a prompt result with which the parties must comply, even though it may later be revised in arbitration.…
|
2 |
| 9 Mar 2006 |
[2006] EWHC 3594 (TCC)
Under Arbitration Act 1996, the words “final and binding” do not, by themselves, exclude an appeal on a question of law. The court must construe the parties’…
|
1 |
| 8 Mar 2006 |
[2006] EWHC 591 (TCC)
Economic duress requires pressure which compels the claimant or removes practical choice, is illegitimate, and significantly induces the contract. Commercial…
|
|
| 6 Mar 2006 |
[2006] EWHC 848 (TCC)
An adjudicator’s decision should generally be enforced despite an error of law or an arguable failure to consider evidence, provided that the adjudicator…
|
7 |
| 2 Mar 2006 |
[2006] EWHC 727 (TCC)
On an agreed appeal under section 69(2)(a) of the Arbitration Act 1996, the court must decide genuine questions of law correctly; the Act’s policy of…
|
20 |
| 24 Feb 2006 |
[2006] EWHC 348 (TCC)
A claimed purchaser’s lien over registered land may be protected by a unilateral notice before the lien has been adjudicated. The court nevertheless retains…
|
|
| 21 Feb 2006 |
[2006] EWHC 257 (TCC)
Unless Orders are exceptional and should not be imposed routinely for every failure to comply with an earlier order. They are generally appropriate only where…
|
|
| 9 Feb 2006 |
[2006] EWHC 148 (TCC)
Summary assessment on the standard basis requires a two-stage approach. The court must first decide whether the costs as a whole are disproportionate, having…
|
|
| 6 Feb 2006 |
[2006] EWHC 741 (TCC)
Adjudication decisions under the Housing Grants, Construction and Regeneration Act 1996 are intended to secure immediate cash flow. Subject to special…
|
11 |
| 2 Feb 2006 |
[2006] EWHC 174 (TCC)
Successive adjudications concerning extensions of time are permissible where they arise from separate disputes based on different grounds. A contractor may…
|
3 |
| 2 Feb 2006 |
[2006] EWHC 126 (TCC)
Costs remain a matter of judicial discretion. The starting point is that costs follow the event, but the court must consider all the circumstances, including…
|
|
| 27 Jan 2006 |
[2006] EWHC 71 (TCC)
In adjudication enforcement proceedings, the court should enforce an adjudicator’s decision unless the adjudicator decided a matter outside the referral or…
|
|
| 25 Jan 2006 |
[2006] EWHC 43 (TCC)
Under Civil Procedure Rules 1998, a party may use an expert report disclosed by another party where that report was disclosed with permission under CPR 35.4.…
|
5 |
| 23 Jan 2006 |
[2006] EWHC 6 (TCC)
A professional services contract may impose enforceable obligations as to time in addition to the duty to exercise reasonable skill and care. The obligation is…
|
|
| 20 Jan 2006 |
[2006] EWHC 31 (TCC)
A settlement offer marked “without prejudice save as to costs” may be admitted to determine whether it was accepted and created a binding compromise. The court…
|
|
| 19 Jan 2006 |
[2006] EWHC 66 (TCC)
A statutory water undertaker may use an assumed volume to calculate sewerage charges, but its statutory power extends only to services actually provided. A…
|
|
| 16 Jan 2006 |
[2006] EWHC 89 (TCC)
A construction manager may perform both an agency function for the employer and a decision-making function affecting the parties’ competing interests. When…
|
5 |
| 16 Jan 2006 |
[2006] EWHC 54 (TCC)
An adjudicator’s decision should ordinarily be enforced by prompt enforcement proceedings in the Technology and Construction Court. A party cannot generally…
|
|
| 10 Jan 2006 |
[2006] EWHC 5 (TCC)
An architect advising on a complex construction project must give clear, timely and sufficiently detailed advice about design decisions, procurement…
|
|
| 10 Jan 2006 |
[2006] EWHC 15 (TCC)
On an application to enforce an adjudicator’s decision, summary judgment may be given where the proposed defence has no real prospect of success. The court…
|
2 |
| 6 Jan 2006 |
[2006] EWHC 29 (TCC)
In determining costs, the court must identify the successful party by assessing the litigation as a whole, while considering partial success, conduct…
|
1 |