Summary
A claimant recovering damages for professional negligence or breach of contract must prove that the claimed loss was caused by the established breach, was reasonably incurred and was not too remote. In construction disputes, reinstatement costs are recoverable only to the extent reasonably necessary to remedy defects for which the defendant is responsible. Reliance on expert advice is relevant to reasonableness but does not itself establish causation or liability for unrelated works. A global “top-down” assessment is inappropriate where individual breaches and unrelated expenditure can be identified. A settlement with a third party is recoverable only if its reasonableness and causal connection with the defendant’s breach are proved. General damages for inconvenience, distress and discomfort remain modest.
Factual background
AXA Insurance UK Plc claimed damages from Cunningham Lindsey United Kingdom, loss adjusters appointed to administer subsidence-related reinstatement works at an old farmhouse. AXA alleged professional negligence and breach of contract in the specification, supervision and administration of the works, and claimed that Cunningham’s failures caused substantial additional remedial expenditure, delay and settlement payments to the insured.
The court considered the scope of Cunningham’s retainer, the breaches established, causation, the reasonableness of remedial expenditure and settlement, and the appropriate measure of damages.
Held
- Liability. Cunningham’s retainer was limited principally to taking forward the existing repair scheme, procuring and supervising the remedial works, administering the building contract and adjusting related losses. It was not employed to redesign or supervise the insured’s extensive independent refurbishment works. The contractual duty was to exercise the reasonable care, skill and diligence expected of reasonably competent loss adjusters providing this service.
- Cunningham was liable for specified failures, including the absence of an adequate condition survey, the inappropriate use and poor installation of concrete lintels for crack repairs, unsuitable lightweight plaster, bridging of the damp-proof course, defective repointing, certain defective brickwork, overpayments, failure to obtain a proper programme, inadequate supervision during a surveyor’s absence, and inadequate records of instructions, meetings and lintel locations. Other alleged breaches were not proved.
- Causation and measure. The court applied the effective-cause approach in [1994] 1 WLR 1360 and held that AXA had to connect each recoverable item to an established breach. The extensive refurbishment, structural alterations and improvements undertaken or demanded by the insured were not attributable to Cunningham. A “top-down” claim for overall project expenditure was therefore inappropriate. Damages had to be assessed item by item, allowing reasonable enabling and consequential works but excluding betterment and unrelated defects.
- Expert advice could materially support the reasonableness of a remedial decision, but it did not make expenditure recoverable where the underlying defect was outside Cunningham’s responsibility. The settlement with the insured was not shown to be reasonable or causally attributable to Cunningham, except for £5,400 representing general damages for twelve months’ delay and aggravation.
- Judgment was entered for AXA in the sum of £282,902.67. The question of interest was reserved for further submissions.
The court’s approach to earlier authorities
Available to signed-in members.
Key cases cited
20 authorities cited.
- Banque Bruxelles Lambert SA v Eagle Star Insurance Co Ltd (BNP Mortgages Ltd v Goadsby & Harding Ltd, BNP Mortgages Ltd v Key Surveyors Nationwide Ltd, United Bank of Kuwait Plc v Prudential Property Services Ltd, South Australia Asset Management Corpn v York Montague Ltd) [1997] AC 191
- Ruxley Electronics and Construction Ltd v Forsyth (Laddingford Enclosures Ltd v Forsyth) [1996] AC 344
- Banco de Portugal v Waterlow & Sons Ltd [1932] AC 452
- British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways Co of London Ltd [1912] AC 673
- SOUTHAMPTON CONTAINER TERMINALS LTD. v. SCHIFFAHRTSGESELLSCHAFT “HANSA AUSTRALIA” M.b.H. & CO. (THE “MAERSK COLOMBO”) [2001] EWCA Civ 717 [2001] 2 Lloyd's Rep 275
- Galoo Ltd v Bright Grahame Murray [1994] 1 WLR 1360
- Watts v Morrow [1991] 1 WLR 1421
- Darbishire v Warran [1963] 1 WLR 1067
- John F Hunt Demolition Ltd v ASME Engineering Ltd [2007] EWHC 1507 (TCC)
- Hadley v Baxendale (1854) 9 Ex 341
- McGlinn v Waltham Contractors Co Ltd [2007] 111 Com LR 1
- Hoadley v Edwards [2001] PNLR 41
- GENERAL FEEDS INC. PANAMA v. SLOBODNA PLOVIDBA YUGOSLAVIA [1999] 1 Lloyd's Rep 688
- Ezekiel v McDade [1994] 43 Con LR 45
- Board of Governors of the Hospitals for Sick Children v McLaughlin and Harvey and Others [1987] 19 Con LR 25
- Quinn v Burch Bros (Builders) Ltd [1966] 2 QB 370
- East Ham Corpn v Bernard Sunley & Sons Ltd [1966] AC 406
- Biggin & Co Ltd v Permanite Ltd [1951] 2 KB 314
- Heskell v Continental Express Ltd [1950] 1 All ER 1033
- Livingston v Rawyards Coal Co [1880] 5 App.Cas 25
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
8 later cases · 7 positive · 1 neutral
Most senior citing decisions:
- Ioannis Mallas v Persimmon Homes Limited & Anor [2025] EWHC 2581 (TCC) applied
- Vitsoe Limited v Waugh Thistleton Architects Limited [2025] EWHC 850 (TCC) applied
- St James's Oncology SPC Ltd v Lendlease Construction (Europe) Limited & Anor [2022] EWHC 2504 (TCC) followed
- Marlet Homes Limited v Mulalley & Co. Limited [2022] EWHC 1813 (TCC)
- Melhuish & Saunders Ltd v Hurden & Anor [2012] EWHC 3119 (TCC)
- Carillion JM Ltd v Phi Group Ltd [2011] EWHC 1379 (TCC)
- Costain Ltd v Charles Haswell & Partners Ltd [2009] EWHC 3140 (TCC)
- Galliford Try Infrastructure Ltd & Anor v Mott MacDonald Ltd [2008] EWHC 1570 (TCC)
Sign in for the full treatment table. A free account is enough.