| Date | Case | Cited by |
|---|---|---|
| 20 Feb 2009 |
[2008] EWHC 370 (TCC)
Under Arbitration Act 1996, section 66, an arbitration award may be summarily enforced where the tribunal had substantive jurisdiction and no sufficient ground…
|
|
| 19 Dec 2008 |
[2008] EWHC 3226 (TCC)
The court may alter the ordinary 14-day period for complying with a money judgment and may order payment by instalments. In exercising that discretion, it may…
|
4 |
| 19 Dec 2008 |
[2008] EWHC 3183 (TCC)
Contract formation in a commercial “battle of the forms” is determined objectively from the parties’ words and conduct. A quotation may be rejected by a…
|
1 |
| 19 Dec 2008 |
[2008] EWHC 3160 (TCC)
An adjudicator may investigate his own jurisdiction, but the parties must clearly reserve any objection to that jurisdiction. A reservation remains effective…
|
3 |
| 16 Dec 2008 |
[2008] EWHC 3171 (TCC)
A settlement described as full and final settlement of all claims and cross-claims arising from a construction agreement ordinarily prevents a party pursuing…
|
|
| 16 Dec 2008 |
[2008] EWHC 3104 (TCC)
The unsuccessful party will ordinarily pay the successful party’s costs. An issue-based costs order is appropriate only where the successful party’s failure on…
|
9 |
| 11 Dec 2008 |
[2008] EWHC 3139 (TCC)
Construction adjudication does not prevent either party seeking a final determination from the court. CPR Part 8 may be used where the dispute falls within its…
|
3 |
| 11 Dec 2008 |
[2008] EWHC 3134 (TCC)
In adjudication-enforcement proceedings, an adjudicator is not required to conduct a site inspection. The question is whether, exercising discretion in the…
|
4 |
| 10 Dec 2008 |
[2008] EWHC 3047 (TCC)
An adjudicator may determine whether additional work formed part of the contract containing the adjudication clause, even where that issue overlaps with the…
|
5 |
| 10 Dec 2008 |
[2008] EWHC 3024 (TCC)
A contract for the manufacture and supply of goods may be inferred where the transaction has been fully performed and the parties, price and workscope are…
|
1 |
| 9 Dec 2008 |
[2008] EWHC 3138 (TCC)
An adjudicator’s decision must be enforced unless the adjudicator answered a question not referred or proceeded in an obviously unfair manner. An error of fact…
|
|
| 9 Dec 2008 |
[2008] EWHC 3028 (TCC)
Where building works are agreed without a fixed lump-sum price or an agreed cap, the contractor is ordinarily entitled to a reasonable price for the work and…
|
|
| 8 Dec 2008 |
[2008] EWHC 3434 (TCC)
A party cannot both rely on an adjudicator’s decision as valid and challenge its validity. Reliance on the decision to prevent a second adjudication may amount…
|
12 |
| 5 Dec 2008 |
[2008] EWHC 3315 (TCC)
An adjudicator determining a money claim has jurisdiction to consider any defence open to the responding party, even if the defence was not raised before the…
|
4 |
| 4 Dec 2008 |
[2008] EWHC 3029 (TCC)
A contractual agreement to mediate may justify a stay, but the court should first determine whether summary judgment is available. Where a claim has no defence…
|
5 |
| 21 Nov 2008 |
[2008] EWHC 2847 (TCC)
On a summary judgment application, extensive evidence does not of itself make a claim unsuitable for determination under CPR Part 24. The court must examine…
|
2 |
| 20 Nov 2008 |
[2008] EWHC 2930 (TCC)
For an interim injunction, the court must first ask whether there is a serious issue to be tried. It must then consider whether damages would be an adequate…
|
|
| 17 Nov 2008 |
[2008] EWHC 2802 (TCC)
For section 107 of the Housing Grants, Construction and Regeneration Act 1996, all express contractual terms must be recorded in writing. Whether an orally…
|
3 |
| 10 Nov 2008 |
[2008] EWHC 2726 (TCC)
In the absence of an agreed price, a contractor is entitled to a reasonable price for work carried out. Contract formation is assessed objectively. Silence may…
|
|
| 7 Nov 2008 |
[2008] EWHC 2862 (TCC)
A contractual scope of services is determined objectively from the agreed documents and surrounding circumstances. In an evolving design process, work required…
|
|
| 31 Oct 2008 |
[2008] EWHC 2657 (TCC)
Where a claimant succeeds on liability and recovers damages, the ordinary costs rule will generally apply even if the sum recovered is substantially less than…
|
2 |
| 31 Oct 2008 |
[2008] EWHC 2617 (TCC)
A sectional completion agreement is enforceable where, read as a whole and purposively, it identifies the contractual dates for completion of each section.…
|
|
| 24 Oct 2008 |
[2008] EWHC 2672 (TCC)
An application under section 69 of the Arbitration Act 1996 must identify a clear question of law arising from the arbitrator’s accepted findings of fact. It…
|
|
| 22 Oct 2008 |
[2008] EWHC 2616 (TCC)
A Part 36 offer is not rendered incapable of later acceptance merely because it was previously rejected. Nor does the commencement of trial create an implied…
|
5 |
| 17 Oct 2008 |
[2008] EWHC 2454 (TCC)
A final third party debt order requires a present debt due from the third party to the judgment debtor. The court must examine the underlying agreement and…
|
1 |
| 10 Oct 2008 |
[2008] EWHC 2379 (TCC)
A commercial contract must be construed as a whole, against the relevant objective background, while giving proper weight to the words used. A final agreement…
|
5 |
| 30 Sep 2008 |
[2008] EWHC 2527 (TCC)
Under CPR Rule 44.3(6)(g), the court has a broad discretion to award interest on costs from a date before judgment. The discretion is not confined to costs…
|
|
| 29 Sep 2008 |
[2008] EWHC 2280 (TCC)
In commercial litigation involving competing monetary claims, the party entitled to the net payment will generally be the overall successful party for costs.…
|
55 |
| 29 Sep 2008 |
[2008] EWHC 2220 (TCC)
Contractual valuation under a construction subcontract depends on work and materials actually completed, supplied or procured. Time elapsed does not itself…
|
7 |
| 25 Sep 2008 |
[2008] EWHC 2270 (TCC)
Under Civil Procedure Rules 1998 rule 19.5, a party may be substituted after expiry of limitation where the party named in the claim form was named through a…
|
|
| 25 Sep 2008 |
[2008] EWHC 2254 (TCC)
An adjudicator who considers a claim and refuses payment has made a decision, even if the decision gives inadequate reasons or suggests that the claim may be…
|
|
| 19 Sep 2008 |
[2008] EWHC 2210 (TCC)
In assessing tort damages for delay, the court must identify the loss actually caused by the tort and must not treat unexplained differences in expenditure as…
|
|
| 19 Sep 2008 |
[2008] EWHC 2172 (TCC)
A consumer arbitration clause in a standard-form construction contract may be unfair under the Unfair Terms in Consumer Contracts Regulations 1999. The…
|
2 |
| 18 Sep 2008 |
[2008] EWHC 2349 (TCC)
An unless order may provide that specified consequences follow automatically upon non-compliance, without a further order. Because that consequence can be…
|
1 |
| 17 Sep 2008 |
[2008] EWHC 2333 (TCC)
Adjudication is intended to be a quick, one-off process. A party cannot refer substantially the same dispute to a second adjudicator by advancing a new legal…
|
10 |
| 16 Sep 2008 |
[2008] EWHC 2316 (TCC)
An application for pre-action disclosure requires the applicant to identify an arguable underlying claim and to satisfy each jurisdictional condition in CPR…
|
4 |
| 16 Sep 2008 |
[2008] EWHC 2283 (TCC)
The TCC has jurisdiction to determine whether a construction contract exists and what terms it contains where that determination may establish a party’s right…
|
5 |
| 15 Sep 2008 |
[2008] EWHC 2181 (TCC)
A payment by a third party discharges another person’s debt only where the payment is made as that person’s agent, for and on their account, with their prior…
|
|
| 9 Sep 2008 |
[2008] EWHC 2180 (TCC)
Compensation for mining subsidence under the Coal Mining Subsidence Act 1991 requires physical subsidence damage to the claimant’s land or property. Pure…
|
|
| 20 Aug 2008 |
[2008] EWHC 2037 (TCC)
In a civil claim, the claimant bears the burden of proving causation on the balance of probabilities. A court is not required to choose between competing…
|
5 |
| 15 Aug 2008 |
[2008] EWHC 2082 (TCC)
An adjudicator’s decision should generally be enforced unless it is plain that the question decided was not referred or the adjudicator acted in an obviously…
|
2 |
| 15 Aug 2008 |
[2008] EWHC 2025 (TCC)
An adjudicator has power under a contractual provision requiring him to set his own procedure to extend time for a response, subject to the overall timetable…
|
5 |
| 7 Aug 2008 |
[2008] EWHC 2510 (TCC)
A supplier applying a compliant sports-floor sealant may owe obligations extending beyond supplying a product meeting the relevant standard. The product must…
|
|
| 31 Jul 2008 |
[2008] EWHC 2003 (TCC)
Where a claim is compromised but the parties cannot agree costs, the court must account for the compromise and should ordinarily make no order unless the facts…
|
1 |
| 30 Jul 2008 |
[2008] EWHC 2005 (TCC)
The Party Wall etc Act 1996 provides an exhaustive procedure for disputes falling within its scope. A building owner cannot rely on statutory protection for…
|
2 |
| 25 Jul 2008 |
[2008] EWHC 1994 (TCC)
A party must comply substantively and clearly with a court order for disclosure. Alleged deficiencies in the other party’s disclosure do not answer…
|
|
| 25 Jul 2008 |
[2008] EWHC 1927 (TCC)
An adjournment of a complex trial should be granted only where necessary to secure a fair and effective hearing consistent with the overriding objective. The…
|
|
| 25 Jul 2008 |
[2008] EWHC 1836 (TCC)
In adjudication proceedings, a party may suggest a suitable adjudicator or disclose relevant technical or legal requirements to the nominating institution…
|
4 |
| 25 Jul 2008 |
[2008] EWHC 1806 (TCC)
A consent costs order must be construed objectively, in the context of the order as a whole and the background reasonably available when it was made. The…
|
|
| 22 Jul 2008 |
[2008] EWHC 1926 (TCC)
A supplier is not liable for a fire merely because an electrical installation later becomes unsafe. Liability depends on proof that the supplier breached an…
|
|
| 17 Jul 2008 |
[2008] EWHC 1864 (TCC)
Costs are determined by applying the general rule that the successful party should recover its costs, subject to the court’s discretion and all the…
|
|
| 17 Jul 2008 |
[2008] EWHC 1570 (TCC)
A consultant does not ordinarily owe a tortious duty to a contractor for economic loss merely because the contractor receives and may use tender drawings…
|
5 |
| 16 Jul 2008 |
[2008] EWHC 2039 (TCC)
A non-party may be ordered to pay litigation costs where it funded and controlled the proceedings and was the real beneficiary of the litigation. The court may…
|
|
| 9 Jul 2008 |
[2008] EWHC 1721 (TCC)
In an unopposed assessment of damages, the claimant retains the burden of proving its entitlement and the amount of loss. The court must scrutinise the…
|
|
| 2 Jul 2008 |
[2008] EWHC 1518 (TCC)
A marine surveyor who undertakes to advise whether a vessel is capable of MCA coding must exercise the reasonable skill and care expected of a reasonably…
|
|
| 25 Jun 2008 |
[2008] EWHC 1439 (TCC)
A letter of intent may create a binding interim contract even where the parties expect a formal construction contract to follow. The question is one of…
|
3 |
| 24 Jun 2008 |
[2008] EWHC 1392 (TCC)
The court has a wide discretion to appoint an assessor under CPR 35.15. The discretion must be exercised consistently with the overriding objective, including…
|
|
| 16 Jun 2008 |
[2008] EWHC 1508 (TCC)
In TCC proceedings issued at a regional centre, transfer to London is justified only where the balance of convenience and fairness favours London. The size…
|
1 |
| 16 Jun 2008 |
[2008] EWHC 1325 (TCC)
A contractual reference to the NHBC Buildmark Scheme ordinarily identifies the prescribed Buildmark warranty and insurance document, rather than a generic…
|
1 |
| 13 Jun 2008 |
[2008] EWHC 1497 (TCC)
Compliance with a pre-action protocol is assessed in substance, not by technical or semantic objections. Minor omissions do not justify costs sanctions where…
|
|
| 13 Jun 2008 |
[2008] EWHC 1438 (TCC)
An irregular extension of time does not automatically deprive the court of jurisdiction. Under the Civil Procedure Rules 1998, the court retains a broad…
|
|
| 13 Jun 2008 |
[2008] EWHC 1391 (TCC)
Indemnity costs require conduct that is unreasonable to a high degree and takes the litigation out of the ordinary norm. A claim that is merely weak, or…
|
1 |
| 13 Jun 2008 |
[2008] EWHC 1386 (TCC)
On an application to vary an interim injunction, the court must first consider whether there is a reasonably arguable claim and defence. If so, it must assess…
|
|
| 13 Jun 2008 |
[2008] EWHC 1301 (TCC)
Contract construction requires the court to consider the factual background reasonably available to the parties, while maintaining proper weight for the words…
|
|
| 19 May 2008 |
[2008] EWHC 1420 (TCC)
An expert determination is binding if the expert decides the question referred to him, even where the decision contains errors. The court will not generally…
|
1 |
| 16 May 2008 |
[2008] EWHC 1087 (TCC)
A letter of intent may create a binding interim contract even though the parties expect to agree fuller terms later. The court must identify objectively the…
|
1 |
| 9 May 2008 |
[2008] EWHC 1020 (TCC)
In a battle of standard terms, the court determines incorporation objectively from the parties’ communications and conduct. Specifically identified contractual…
|
2 |
| 8 May 2008 |
[2008] EWHC 1016 (TCC)
Contract formation is assessed objectively from the parties’ words and conduct viewed as a whole. Parties may intend to be bound while leaving terms for later…
|
2 |
| 7 May 2008 |
[2008] EWHC 992 (TCC)
A contractual term should be implied only where the strict requirements for implication are satisfied. A contract’s commercial purpose and a party’s alleged…
|
|
| 30 Apr 2008 |
[2008] EWHC 238 (TCC)
A liquidator may assign the fruits of proceedings as company property, but cannot assign personal statutory powers to prosecute or control those proceedings.…
|
3 |
| 29 Apr 2008 |
[2008] EWHC 933 (TCC)
Where an employer takes partial possession of works and the contract contains no provision for sectional completion, the principle in Bramall & Ogden v…
|
1 |
| 23 Apr 2008 |
[2008] EWHC 817 (TCC)
Time limits for court intervention in arbitration reflect the finality and expedition policies of the Arbitration Act 1996. In an application to extend the…
|
5 |
| 17 Apr 2008 |
[2008] EWHC 825 (TCC)
Section 14(1) of the Arbitration Act 1996 requires an agreement as to when arbitral proceedings are to be regarded as commenced. The agreement need not…
|
|
| 1 Apr 2008 |
[2008] EWHC 619 (TCC)
In complex group litigation, the court may make a costs capping order without requiring exceptional circumstances. The order may be mutual and should…
|
|
| 27 Mar 2008 |
[2008] EWHC 727 (TCC)
A contractual restriction preventing proceedings before certification of completion must be construed in its contractual and commercial context, while…
|
|
| 20 Mar 2008 |
[2008] EWHC 730 (TCC)
Reasonableness of contractual plant rates is assessed by reference to the circumstances when the contract was made. Later use of a rate in a different contract…
|
|
| 19 Mar 2008 |
[2008] EWHC 569 (TCC)
Amendments sought during trial should be allowed where they are needed to determine the real dispute, unless the resulting prejudice cannot fairly be…
|
|
| 18 Mar 2008 |
[2008] EWHC 526 (TCC)
A contractual reference to an employer’s agent’s certificates does not, without clear language and an adequate contractual mechanism, create a freestanding…
|
|
| 14 Mar 2008 |
[2008] EWHC 724 (TCC)
A restitutionary claim for an unrequested improvement to another’s land is subject to the distinct principles governing mistaken improvements to land. Relief…
|
|
| 14 Mar 2008 |
[2008] EWHC 603 (TCC)
Negotiations genuinely aimed at resolving a dispute are protected by the without prejudice rule even if no formal claim has yet been made and the…
|
|
| 14 Mar 2008 |
[2008] EWHC 502 (TCC)
Commercial contracts are construed by giving their words their natural and ordinary meaning in the context of the agreement as a whole and its relevant…
|
|
| 13 Mar 2008 |
[2008] EWHC 570 (TCC)
On an application to enforce an adjudicator’s decision, the court should first determine any jurisdiction challenge. If the adjudicator had jurisdiction, the…
|
2 |
| 13 Mar 2008 |
[2008] EWHC 426 (TCC)
An arbitration clause specifying a geographical place as the seat does not necessarily determine the juridical seat where the contract, read as a whole…
|
5 |
| 12 Mar 2008 |
[2008] EWHC 584 (TCC)
Applications to transfer county court proceedings to the Technology and Construction Court should be made to the receiving court, with notice to the county…
|
2 |
| 6 Mar 2008 |
[2008] EWHC 413 (TCC)
Pre-action costs may in principle be included in security for costs, but the discretion should be exercised cautiously. Costs of a separate pre-action…
|
3 |
| 27 Feb 2008 |
[2008] EWHC 282 (TCC)
An adjudicator must determine the essential disputed claim, rather than confining the reference to the parties’ pre-referral arguments or evidence. A…
|
62 |
| 26 Feb 2008 |
[2008] EWHC 343 (TCC)
On an application for summary judgment, a claim should proceed if it has a real, even weak, prospect of success. The court must avoid conducting a mini-trial…
|
|
| 12 Feb 2008 |
[2008] EWHC 223 (TCC)
The court should take a pragmatic and commercially realistic approach when deciding whether non-compliance with a construction pre-action protocol justifies a…
|
2 |
| 8 Feb 2008 |
[2008] EWHC 66 (TCC)
A structural engineer advising on building movement must investigate the nature of the subsoil, foundations and existing damage sufficiently to assess risks…
|
|
| 7 Feb 2008 |
[2008] EWHC 231 (TCC)
When deciding an application to amend shortly before a long and complex trial, the court must exercise its discretion in accordance with the overriding…
|
|
| 7 Feb 2008 |
[2008] EWHC 168 (TCC)
When a contractual representation refers without qualification to an expert report, the reference ordinarily covers the report as a whole. It is not confined…
|
|
| 1 Feb 2008 |
[2008] EWHC 147 (TCC)
Amendments should generally be permitted where they enable the real dispute to be adjudicated, unless the opposing party would suffer prejudice that a costs…
|
|
| 29 Jan 2008 |
[2008] EWHC 123 (TCC)
Under CPR 35.11, any party may rely at trial on an expert report disclosed by another party, even where the disclosing party has subsequently ceased to…
|
3 |
| 25 Jan 2008 |
[2008] EWHC 83 (TCC)
A notification under a claims-made professional indemnity policy covers the specific circumstances objectively identified in the notice. It may include defects…
|
5 |
| 11 Jan 2008 |
[2008] EWHC 6 (TCC)
A duty of care in tort may exist alongside contractual duties where negligent work causes physical damage and consequential financial loss. The contractual…
|
|
| 4 Jan 2008 |
[2008] EWHC 12 (TCC)
Costs ordinarily follow the event, but the court may make a proportionate order where the successful party failed on a distinct and significant issue. In…
|