Summary
In commercial litigation involving competing monetary claims, the party entitled to the net payment will generally be the overall successful party for costs. That is only the starting point. Under the Civil Procedure Rules, the court must make a just costs order after considering success on distinct issues, common costs, admissible settlement offers and the parties’ conduct.
An issue-based order should be used where required, but a proportionate costs order will often be more practical. A party may suffer a costs penalty for rejecting a nearly sufficient admissible offer without attempting negotiation. Conversely, a debtor’s persistent failure to make a realistic global offer may justify an adjustment in favour of the overall winner.
Treatment over time
Cited in 55 later judgments between 2009 and 2024. Applied, followed or approved 36 times, most recently by the Court of Appeal in February 2024. 2 negative treatments, including by the Court of Appeal in 2010; most recently by the High Court in 2013.
Most often cited for
- Costs should reflect overall success and relative issue outcomes, while allowing recovery of common costs
- Rejecting a nearly sufficient offer without negotiation may justify a costs penalty
Factual background
Following judgment in a long-running construction dispute, Jackson J determined the outstanding costs of the action. The principal issues concerned costs relating to three Scott Schedules and a separate preliminary issue.
Multiplex Constructions (UK) Ltd recovered a net balance of £6,154,246.79. It had, however, failed comprehensively on Scott Schedule 4 and had rejected a substantially more favourable admissible offer concerning Scott Schedule 1. Both parties had also missed opportunities to settle.
The central question was what costs order fairly reflected the overall result, the parties’ differing success on the schedules, their settlement conduct, and the practical choice between issue-based and proportionate costs orders.
Held
Costs order. Cleveland Bridge was ordered to pay Multiplex 20% of Multiplex’s costs of the action, to be assessed on the standard basis. Each party was to bear its own costs of preliminary issue 11.
In commercial litigation involving reciprocal monetary claims, the overall winner is generally the party who receives the net payment. That conclusion supplies the starting point that costs should follow the event under the Civil Procedure Rules, r 44.3. It does not preclude adjustment for partial success, offers and conduct. This approach followed AL Barnes Ltd v Time Talk (UK) Ltd [2003] EWCA Civ 402 and Burchell v Bullard [2005] EWCA Civ 358.
The court should consider an issue-based order where it is needed, but should hesitate before adopting it because of its practical difficulty and the direction in r 44.3(7). A proportionate order may instead reflect relative success on particular issues while allowing the overall winner to recover common costs. The court applied the guidance in AEI Rediffusion Music Ltd v Phonographic Performance Ltd [1999] 1 WLR 1507, Summit Property Ltd v Pitmans [2001] EWCA Civ 2020 and Aspin v Metric Group Ltd [2007] EWCA Civ 922.
The court treated the post-amendment approach in Carver v BAA Plc [2008] EWCA Civ 412 as generally applicable, not confined to personal injury litigation. Where an admissible settlement offer was nearly sufficient and was rejected without negotiation, a costs penalty might be appropriate. The court must also assess the parties’ wider conduct in seeking settlement.
Multiplex was the overall winner because Cleveland Bridge had to pay the net balance. Its recovery of costs nevertheless required substantial reduction. Multiplex had unreasonably rejected Cleveland Bridge’s December 2007 offer on Schedule 1 and had recovered only nominal damages on Schedule 4. Those matters justified allowing no recovery for the Schedule 1 costs and allowing Cleveland Bridge the Schedule 4 costs. Multiplex succeeded on Schedule 2 and was entitled to the common costs. The resulting provisional 10% recovery was increased to 20% because Cleveland Bridge bore the greater responsibility for failing to make a realistic offer to settle the whole action.
Preliminary issue 11 was a discrete phase. Multiplex won the design issue and Cleveland Bridge won the fabrication issue. As time and preparation costs were substantially equal, and disclosure failings offset each other, each party was ordered to bear its own costs of that issue.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
not stated in the judgment.
Other judgments in these proceedings
12 judgments in these proceedings, earliest first. Linked by the shared court number HT-04-314, and by appeals.
- 5 June 2006Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd
- 20 December 2006Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor
- 31 January 2007Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd (No. 2)
- 12 March 2007Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd (No. 3)
- 27 April 2007Cleveland Bridge UK Ltd & Anor v Multiplex Constructions (UK) Ltd
- 21 December 2007Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor
- 6 February 2008Multiplex Construction Ltd v Cleveland Bridge Ltd & Anor
- 19 March 2008Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor
- 29 September 2008Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor
- 29 September 2008Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor
- 19 February 2010Cleveland Bridge UK Ltd & Anor v Multiplex Constructions (UK) Ltd
- 31 March 2010Cleveland Bridge UK Ltd & Anor v Multiplex Constructions (UK) Ltd
Related cases
Not part of these proceedings, but heard together with this judgment or between the same parties.
- 31 August 2005Cleveland Bridge UK Ltd v Multiplex Constructions (UK) Ltd
- 7 February 2008Multiplex Construction (UK) Ltd v Cleveland Bridge UK Ltd
Often cited alongside this case
Of these 8 cases: 4 cited with it on the same point; 4 cited alongside it for other points.
Cited together forCosts should reflect overall success and relative issue outcomes, while allowing recovery of common costs
4 related cases for signed-in readers
Cited alongside it for other points
- J Murphy & Sons Ltd v Johnston Precast Ltd (Formerly Johnston Pipes Ltd) [No 2 Costs]Failure on some issues alone does not justify an issue-based costs orderCited together in 7 later judgments
- Carver v BAA PlcPart 36 comparisons require a broad assessment of whether the judgment was worth pursuingCited together in 8 later judgments
- HLB Kidsons (a firm) v Lloyds Underwriters (Policy No 621/PKID00101) & OrsA successful party’s costs are not automatically reduced for losing individual issuesCited together in 10 later judgments
+1 more for signed-in readers
5 more related cases for signed-in readers. A free account is enough.
Key cases cited
12 authorities cited.
- Carver v BAA Plc [2008] EWCA Civ 412
- Hall & Ors v Stone [2007] EWCA Civ 1354
- Aspin v Metric Group Ltd [2007] EWCA Civ 922
- National Westminster Bank Plc v Kotonou [2007] EWCA Civ 223
- Burchell v Bullard & Ors [2005] EWCA Civ 358
- Painting v University of Oxford [2005] EWCA Civ 161
- A L Barnes Ltd. v Time Talk (UK) Ltd. [2003] EWCA Civ 402
- Summit Property Limited v Pitmans (a firm) [2001] EWCA Civ 2020
- AEI Rediffusion Music Ltd v Phonographic Performance Ltd [1999] 1 WLR 1507
- QUORUM A.S. v. SCHRAMM (No. 2) [2002] 2 Lloyd's Rep 72
- Johnsey Estates (1990) Limited v Secretary of State for the Environment, Transport and the Regions [2001] All ER (D) 135
- Liverpool City Council v Rosemary Chavasse Limited
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
55 later cases · 36 positive · 12 neutral · 5 caution · 2 negative
Most senior citing decisions:
- Robert Taylor v Peter Jones & Anor [2024] EWCA Civ 170 followed
- Coll v Secretary of State for Justice [2015] EWCA Civ 328 followed
- Dufoo v Tolaini & Ors [2014] EWCA Civ 1536 explained
- Coward v Phaestos Ltd & Ors [2014] EWCA Civ 1256
- Walker Construction (UK) Ltd v Quayside Homes Ltd & Or [2014] EWCA Civ 93
- Royal Bank of Scotland Plc v Highland Financial Partners LP & Ors [2013] EWCA Civ 472
- Hutchinson & Anor v Neale & Anor [2012] EWCA Civ 345
- Acre 1127 Ltd (Formerly known as Castle Galleries Ltd) v De Montfort Fine Art Ltd [2011] EWCA Civ 130
- Gibbon v Manchester City Council [2010] EWCA Civ 726
- Sonmez v Kebabery Wholesale Ltd [2009] EWCA Civ 1386
Sign in for the full treatment table, including the other 45 cases. A free account is enough.