Balfour Beatty Engineering Services (HY) Ltd v Shepherd Construction Ltd

[2009] EWHC 2218 (TCC)

Cited by 7 later cases7 positiveCites 14 authorities

Summary

An adjudicator’s jurisdiction is defined by the disputed claim referred, not by every argument or item of evidence advanced. A broad claim may encompass matters raised in the defence and reply, provided the adjudicator does not re-decide a dispute already resolved by an earlier adjudication. A later decision is unenforceable only to the extent that it materially overrides the earlier binding decision.

Challenges based on natural justice require a material procedural breach concerning a decisive or potentially important issue. Adjudication decisions need intelligible reasons showing what was decided and why, but courts should allow for the expedited and non-final nature of adjudication. Errors of fact, law, emphasis or grammar do not ordinarily prevent enforcement.

Treatment over time

Cited in 7 later judgments between 2009 and 2023. Applied, followed or approved 7 times, most recently by the Court of Appeal in July 2023.

Most often cited for

  1. An adjudicator’s reasons need only make the essential reasoning intelligible5 judgments

Factual background

The claimant, formerly Haden Young Ltd, was a mechanical and electrical subcontractor employed by the defendant on a hospital project. The claimant sought enforcement of an adjudicator’s decision awarding approximately £1.44 million, including an extension of time to the actual completion date and repayment of liquidated damages and prolongation costs.

A first adjudicator had rejected a prospective extension-of-time claim based on delayed access to Block Z. In the second adjudication, the claimant relied principally on retrospective delay analysis concerning air balancing, cause-and-effect testing and pharmacy works, while also relying on earlier access and watertightness delays as background and causative matters. The defendant challenged the second decision for excess of jurisdiction, inconsistency with the first adjudication, breach of natural justice, bias and inadequate reasoning.

Held

  1. Enforcement. Judgment was given for the claimant. The adjudicator’s decision was enforceable. Interest of £3,126.89 was awarded under section 35A of the Supreme Court Act 1981. Costs were summarily assessed at £45,000, payable within 14 days. Permission to appeal was refused.
  2. Jurisdiction. The dispute referred was the claimant’s challenged claim for an extension of time based on the air-balancing, cause-and-effect testing and pharmacy delays. The earlier access and watertightness delays were expressly relied on as explaining and contributing to those later delays. The scope of the dispute was also widened, or at least clarified, by the defendant’s case that the delays were caused by the claimant’s own defaults. The adjudicator therefore had jurisdiction to find that the earlier delays caused the relevant delay.
  3. The second adjudicator did not impermissibly re-decide the first adjudication. The first decision concerned a prospective claim based on delayed access to Block Z as assessed in October 2007. The second decision dealt with retrospective delay and could consider Block Z access as one factor in the actual delay, provided it did not override the earlier decision.
  4. Natural justice. The adjudicator was entitled to draw conclusions from the evidence and was not bound by ordinary court rules of evidence. He had given advance notice of the possibility of an adverse inference from non-production of documents. In any event, his decision did not depend on such an inference: the defendant’s cross-claim failed because the claimant had obtained a full extension of time and because the defendant had not proved its case.
  5. Bias. Criticism of the defendant’s expert and the inference that his reports had not addressed earlier access delays did not establish actual or apparent bias. The adjudicator was entitled to reject the expert’s account and draw an inference from the scope of his reports.
  6. Reasons. The decision was poorly expressed, repetitive and grammatically defective, but its reasoning was intelligible. It identified the late or denied access as the operative cause of delay, explained why reprogramming did not defeat the extension-of-time claim, and concluded that the claimant was entitled to an extension to 10 June 2008. The court need not agree with the reasoning, and an adjudicator need not address every argument, provided the essential route to the decision is apparent.

The court’s approach to earlier authorities

Available to signed-in members.

Cases on related points

Of these 8 cases: 1 cited alongside it for another point; 7 related in other ways.

Cited alongside it for other points

  1. Carillion Construction Ltd v Devonport Royal Dockyard Ltd[2005] EWCA Civ 1358 · Court of Appeal (Civil Division)Adjudicators’ decisions should be enforced unless jurisdictional excess or serious unfairness is plainCited together in 4 later judgments

Other related cases

  1. Herbosh -Kiere Marine Contractors Ltd v Dover Harbour Board[2012] EWHC 84 (TCC) · High Court (Technology and Construction Court)Relies on 3 of the same authorities
  2. J J Rhatigan & Co (UK) Ltd v Rosemary Lodge Developments Ltd[2019] EWHC 1152 (TCC) · High Court (Technology and Construction Court)Relies on 3 of the same authorities

+5 more for signed-in readers

Key cases cited

14 authorities cited.

Sign in to see how the court treated each authority. A free account is enough.

Cases citing this case

7 later cases · 7 positive

Most senior citing decisions:

Sign in for the full treatment table. A free account is enough.