Summary
In public-procurement proceedings, the three-month period must run from the date when the claimant knew, or ought to have known, of the infringement. The incompatible requirement to bring proceedings promptly is disapplied, but the short period remains effective.
Knowledge exists when the claimant knows facts which apparently clearly indicate an infringement. It need not have conclusive evidence, complete particulars, or a real likelihood of success. A genuine statutory letter before action alleging a breach will ordinarily demonstrate sufficient knowledge of that breach. Later information which merely strengthens or particularises the same alleged infringement does not restart time.
Treatment over time
Cited in 26 later judgments between 2011 and 2026. Applied, followed or approved 23 times, most recently by the High Court in November 2026.
Most often cited for
- Limitation starts when known facts indicate an infringement, without requiring proof or certainty of success
- Distinct procurement breaches may have separate limitation periods, but further particulars of the same breach do not restart time
Factual background
Sita UK Limited, an unsuccessful tenderer for a long-term waste-disposal contract, alleged that the authority had materially renegotiated the preferred bidder’s proposal without reopening competition. It commenced proceedings alleging breaches of procurement duties of transparency and equal treatment.
Mann J struck out the claim as time-barred under regulation 32(4) of the Public Services Contracts Regulations 1993. Sita appealed. The principal issue was when it had sufficient actual knowledge of an alleged procurement infringement for the three-month period to begin, and whether later-disclosed material constituted separate breaches or merely further evidence of the same claim.
Held
Appeal dismissed unanimously. Elias LJ, with whom Rimer LJ agreed, held that Directive 89/665, as interpreted in Uniplex UK Limited v NHS Business Services Authority [2010] 2 CMLR 47, required the removal of the promptness requirement in regulation 32(4)(b). It did not require the three-month period to be abandoned. The court must instead ensure, through the statutory power to extend time, that the period runs from actual or constructive knowledge. This preserved both legal certainty and the Directive’s requirement for rapid remedies.
The requisite knowledge was knowledge of facts which apparently clearly indicated an infringement, although they need not prove it. The claimant need not possess the evidence required to plead every particular, nor know that the claim has a real likelihood of success. The distinction is between grounds of complaint and evidence supporting those grounds.
A genuine statutory letter before action alleging a breach will normally make it difficult for its sender to deny sufficient knowledge of that breach. Sita’s April and May 2009 letters asserted procurement breaches and threatened proceedings. They showed that it already had sufficient knowledge, notwithstanding its requests for further information.
The later disclosure of the Ernst & Young re-evaluation and further information about the facility were additional evidence and particulars of the same alleged failure to reopen the competition. They were not separate causes of action and did not restart time. Withholding information does not freeze time where the tenderer already has enough information to commence proceedings.
The claim was properly struck out. The refusal to extend time disclosed no error of principle, perversity, or conclusion plainly against the weight of the evidence.
Arden LJ agreed that the appeal should be dismissed. She would adhere closely to the language in Uniplex: time begins when the tenderer has sufficient information to form an informed view as to infringement and the appropriateness of proceedings, without any further prospects-of-success threshold.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
- Court of Appeal (Civil Division): dismissed Sita’s appeal in Sita UK Ltd v Greater Manchester Waste Disposal Authority [2011] EWCA Civ 156 .
- High Court (Chancery Division): Mann J struck out Sita’s procurement claim as commenced outside the applicable limitation period.
Appeal route
- Appealed fromNot stated in the judgmentThis appealappeal dismissed (unanimously)
- This judgment · 24 February 2011 [2011] EWCA Civ 156 Court of Appeal (Civil Division)
Other judgments in these proceedings
2 judgments in these proceedings, earliest first. Linked by appeals and by the court numbers the judgments share.
- 29 March 2010Sita UK Ltd v Greater Manchester Waste Disposal Authority (Rev 1)
- 24 February 2011Sita UK Ltd v Greater Manchester Waste Disposal Authority
Often cited alongside this case
Of these 8 cases: 1 cited with it on one of its points; 5 cited alongside it for other points; 2 related in other ways.
Cited together forDistinct procurement breaches may have separate limitation periods, but further particulars of the same breach do not restart time
- SRCL Ltd v The National Health Service Commissioning Board (NHS)Cited together in 7 later judgments
Cited alongside it for other points
- Mermec UK Ltd v Network Rail Infrastructure LtdExtending procurement time requires a good reason; short delay alone is insufficientCited together in 7 later judgments
+4 more for signed-in readers
Other related cases
- Bromcom Computers Plc v United Learning Trust & AnorCited together in 3 later judgments
+1 more for signed-in readers
5 more related cases for signed-in readers. A free account is enough.
Key cases cited
3 authorities cited.
- Three Rivers District Council v. Governor and Company of the Bank of England [2001] UKHL 16
- Uniplex UK Limited v NHS Business Services Authority [2010] 2 CMLR 47
- Lämmerzahl v Freie Hansestadt Bremen [2007] ECR 1-8415
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
26 later cases · 23 positive · 3 neutral
Most senior citing decisions:
- Lancashire County Council v Brookhouse Group Limited [2024] EWCA Civ 717 approved
- D&G Cars Ltd v Essex Police Authority [2013] EWCA Civ 514 considered
- Bouygues (U.K.) Limited v Secretary of State for Education [2026] EWHC 2998 (TCC) applied
- The New Lottery Company Limited & Anor v The Gambling Commission [2026] EWHC 891 (TCC)
- Oracle Security Services Limited v Barts Health NHS Trust & Anor [2024] EWHC 1201 (TCC)
- Siemens Mobility Limited v High Speed Two (HS2) Limited [2023] EWHC 2768 (TCC)
- Altiatech Ltd v Birmingham City Council [2023] EWHC 1371 (TCC)
- Bromcom Computers Plc v United Learning Trust & Anor [2022] EWHC 3262 (TCC)
- Siemens Mobility Limited v High Speed Two (HS2) Limited [2022] EWHC 2451 (TCC)
- CAMELOT UK LOTTERIES LIMITED v THE GAMBLING COMMISSION [2022] EWHC 1664 (TCC)
Sign in for the full treatment table, including the other 16 cases. A free account is enough.